STPP Solar System
STPP Solar System
Prepared for
2*600MW STPP, Jaipur
Mancheriyal, Telangana State
Detailed Project Report for Installation of Grid-Connected Solar Rooftop Power generating plants for STPP
Suggested format for citation
Executive Summary
This report presents the detailed feasibility study for installation on solar power
generation system at 2x600MW SingareniThermal Power Plant (STPP) area at
Mancheriyal, Telangana State. The Site visit was conducted to first assess the
suitable space for solar power plant installation considering availability of space,
future plans of expansion and
shadowanalysisoftheselectlocations.Consideringthesecriteria,various buildings in
the campus were identified as potential locations for installation of solar PV power
plants on rooftops of these
buildings.FeasibleRooftopAreaforSPVisidentifiedtobe7653sq.mon
therooftopsofvariousbuildings,whichissufficientforinstallationof1582kWp.
It was observed that all of these buildings had substantial loads in the same premises.
Typically the electrical loads comprised of indoor loads and Outdoor loads. Indoor
loads mainly consisted of lighting, fans, air conditioners (AC‟s), water coolers etc.
The outdoor loads are mostly for outdoor lighting. But this load is not very suitable
for solar power generation systems as the load is only during night time. The final
sizes of the proposed rooftopsolarsystemsatallthebuildingsweredecidedafter
analyzing theshadowfreearea available at the rooftops via Helioscope.
SolarPVpowerisarapidlyemergingsectorwithlotofnewemergingtechnologiessuchas
crystalline solar PV (mono crystalline and poly crystalline), Thin film solar PV and
third generationtechnologiessuch asConcentratingPV, dyesensitized
PVandorganicsolar PV.
OutofthesecrystallinePVtechnologyiscommerciallywellprovenandreliabletechnology
considering Indian as well as global experience. The same technology is therefore
recommended.
The basic engineering for solar PV power plants is also prepared along with detailed bill
of material. Considering the initial discussions with STPP employees, grid tied plant
without storage was considered for designing.
The total capacity of 1582kWp generates about 23.41 MUs annually. Forthe techno-
commercial study, capital cost of the system is considered as INR 34.5/Wp
comprising of capital costsofall major componentsandoperation
andmaintenancecosts. The techno- commercial study also includes the evaluation of
the tracking systems for solar PV panels. The use oftracking systems (singleand
double axis tracking systems)is not recommended as the increase in annual energy
generationdoesnotjustifyincreaseincapitalcost(trackers) and operation and
maintenance costs.
To assist in actual implementation of the solar PV power plants, the report has also
given project implementationschedule ofaround15 weeks. The various operation
and maintenanceactivities related totheproject,necessaryman-power
andorganizational structure for O&M activity and typical cost for O&M activity is
also given. The total operation andmaintenance staff of 4 people is suggested with
estimated operation and
maintenancecostsofabout1.3%ofthecapitalcostsperannumwith3%annualescalation.
There are also various governmentinitiatives topromotesolar PVpowergeneration.
The Government of India and State Governments have been promoting use of solar
energy technologies through variety ofpromotional schemes, policies and regulatory
measures. Some of themeasuressuch as capital subsidies touserandmanufacturers,
low interest
loans,duties&taxesexemptionsandsoonformpartoffiscalandfinancialincentiveswhileot
hers such as mandatory renewable energy purchase obligations are Part of regulatory
initiatives.
RPOs (Renewable Purchase Obligations) are one the major of the government policy
initiatives where in the government is making it mandatory for power consumers to buy
certain percentage of its power consumption to be met from power produced using
renewable energy sources. These obligations are for utilities (also known as DISCOMs
(DistributionCompanies) and consumers who use captive power or who buy power
from generators directly and not through utilities. The RPOs are part of the EA2003
(Electricity act2003) which is the basis for the development of regulatory frame-work in
power sector in India.
At STPP area total of 7653sq. m. of rooftop area is feasible for the installation of
solar PV power plant. This area is suitable for maximum capacity installation of
1582kWp considering shadow area.
Suggested type ofphotovoltaictechnologyisc-Si
Suggested type of system is grid tied systemwithoutstoragebackup
The modulemounting structures will haveto besuch thatcurrentroof slabs
arenot disturbed. Typical load of rooftop solar power plant is about 15-20
kg/sq. m. which seems manageable for the existing building structures.
However, this detail will need to be confirmed by structural consultant during
actual implementation.
AverageCapacityUtilizationFactor(CUF)ofthepowerplantsis ~16%.
InstallingsolarPVsystemisaviablebusinesspropositionasNPVispositiveand
project IRR is more than 13 %.
The detailed financial analysis is also carried out to calculate important financial
parameterssuchasNPV, IRR, and simple paybackperiodetc.Theseparameterswouldbeverymuch
helpfulfordecisionmakerstoevaluatefinancialsideofthesolarPVpowerplantsthatcan
beinstalledatthe STPP .ThefinancialresultsfortheproposedPVpowerplantareas given below.
E:D30:70
Parameter Withoutsubsidy
Systemcapacity(kWp) 1582
Solargeneration(kWh) 156,62,004
Capitalcost(INR) 489,32,000
LCOE(INR/kWh) 2.8547
EquityIRR (%) 10.94%
Table of contents
EXECUTIVE SUMMARY............................................... III
1.INTRODUCTION................................................ 1
1.1............................................................................................................... P
ower supply positionin Telangana.......................................................... 1
1.2............................................................................................................... R
egulatory and Policy Frame work topromote solarroof-topinTelangana 2
1.3............................................................................................................... P
rocedureforavailingnet-metering........................................................... 4
1.4............................................................................................................... A
pplicabilityofprojectunderRECscheme................................................... 5
2.METHODOLOGY ADOPTED TO DETERMINE ACTUAL
POTENTIAL ON IDENTIFIED BUILDINGSIN STPP
AREA, TELANGANA........................................... 7
2.1............................................................................................................... Si
tesurvey.................................................................................................. 7
2.2............................................................................................................... A
ssessment and selection of suitable space with Helioscope..................7
2.3.............................................................................................................. Id
entificationofinstalledelectricalequipmentandloads............................. 12
2.4.............................................................................................................. Lo
admanagement...................................................................................... 13
3.TECHNOLOGYSELECTION
......................................................................
13
4.BASICENGINEERINGOFSOLARPOWERGENERATIONS
YSTEM
......................................................................
14
4.1.............................................................................................................. La
yout of solar PV power plant................................................................. 14
4.2.............................................................................................................. Te
chnical description and specifications.................................................. 16
4.3.............................................................................................................. Es
timation of water and auxiliary power requirements........................... 19
4.4.............................................................................................................. Pr
oject implementation schedule............................................................. 19
4.5.............................................................................................................. Pr
oposed solar PV powersystem.............................................................. 20
Energy ConsumptionandGenerationateachsite..............................20
5.TECHNO-COMMERCIALSTUDY
......................................................................
26
5.1.............................................................................................................. Bu
sinessmodels......................................................................................... 26
5.2.............................................................................................................. Ad
vantagesandDisadvantagesofeachbusinessmodel................................ 28
5.3.............................................................................................................. Fi
nancialanalysis...................................................................................... 29
5.4.............................................................................................................. Re
sultsandDiscussion................................................................................ 31
5.5.............................................................................................................. Re
sultsandDiscussion................................................................................ 33
6. REDUCTIONOFCO2EMISSIONS............................................................................ 34
7.POWERPLANTOPERATION PLANNING
......................................................................
34
7.1.............................................................................................................. M
an-powerplanning................................................................................. 34
7.2.............................................................................................................. Op
erationandmaintenance........................................................................ 34
7.3.............................................................................................................. Vi
abilityoftrackingsystem......................................................................... 35
7.4.............................................................................................................. Ri
sk analysis............................................................................................. 35
7.5.............................................................................................................. Lis
tof SolarPVtechnologyproviders........................................................... 36
8 CONCLUSIONANDRECOMMENDATIONS
.......................................................................
37
8.1............................................................................................... Conclusion
............................................................................................................. 37
8.2 Recommendation…………………………………………………………………………………………………..........37
List of figures
FIGURE 5: REVENUE FLOW IN NET METERING AND THIRD PARTY OWNED MODEL
.................................................................................................................... 28
FIGURE 6: REVENUE FLOW IN NET METERING AND THIRD PARTY OWNED MODEL
.................................................................................................................... 28
List of tables
TABLE1: RESULTS OF FINANCIAL ANALYSIS (GRID TIED SOLAR PV SYSTEM)...IV
TABLE3: CONNECTEDLOADSINDIFFERENTBUILDINGS...................................12
TABLE4:TECHNICALDESCRIPTIONANDSPECIFICATIONS.................................16
TABLE5:TECHNICALDESCRIPTIONANDSPECIFICATIONSOFCIVIL WORK............19
TABLE6: PROJECTIMPLEMENTATIONSCHEDULE........................................... 19
TABLE7:SITEWISESPECIFICATIONSOF THEMAXIMUMCAPACITY.......................24
TABLE8:ASSUMPTIONSFORFINANCIALANALYSIS...........................................30
TABLE9:RESULTSOFFINANCIALANALYSIS.................................................... 32
TABLE10:ASSUMPTIONSFORFINANCIALANALYSIS.........................................32
TABLE13:ENERGYCONSUMPTIONANDGENERATIONATEACHSITE............22
Detailed Project Report for Installation of Grid-
Connected Solar Rooftop Power generating
plants for STPP Properties
1. Introduction
Telangana is the 29thstate of India which was createdon 2ndJune, 2014 after its
separation from Andhra Pradesh. The capital of Telangana state is Hyderabad which it
will be sharing with the state of Andhra Pradesh for next 10 years. Telangana will
have 10 districts of Andhra Pradesh under its jurisdiction. It has an area of114,840
square kilometers (44,340sq mi),and a population of 35,286,757(2011census). Its
major cities include Hyderabad, Warangal, Nizamabad, and Karimnagar. Electricity is
a critical element required for the smooth functioning of the state economy. The
availability of reliable, quality and affordable power helps in the rapid development of
agriculture and industrial sector and the overall economy of the state. There are two
DISCOMs in Telangana – TSSPDCL that supplies power to the districts of Hyderabad,
Rangareddy, Mahbubnagar, Nalgonda and Medak, and TSNPDCL that supplies to
Warangal, Karimnagar, Khammam, Nizamabad and Adilabad. Telangana has A vast
solar potential with average solar insolationofnearly5.5kWh/m2for more than 300
sunshine days. Government of Telangana (GoTS), intends to make use of the positive
environment in solar market and the push given by GoI for substantially harnessing
the solar potential in the state of Telangana.
The report presents detailed project report for feasibility study and detailed techno-
economic assessment of solar PV rooftop power plant in STPP area. Various buildings
suitable for installation of rooftop solar PV power plant were identified in the campus
for this. Chapter2 covers details of site survey such as assessment and selection of
suitable space for PV plant installation, assessment of available loads and resource
assessment. Chapter 3 presents the comparison of various solar PV technologies and
selection of appropriate technology based on the local conditions. Performance evaluation
is given for the selected technology for grid interactive system without any storage
system. Chapter 4 presents the basic engineering of the proposed solar PV power plant
covering actually out and technical specifications of PV power plant and estimation of
annual energy generation by the proposed system. Chapter 5 presents the detailed
techno-commercial study elaborating financial analysis, operation and maintenance
requirement. The conclusion recommendations of the report are presented in Chapter 6.
Central Policy for Grid Connected Solar Rooftop System MNRE is providing
“Achievement
linkedincentivestoGovernmentDepartmentsfortheinstallationofSolarRooftopSystems
in the Government Buildings having the vacant rooftops. Following steps need to be
taken to implement the Achievement linked incentives.
1. The government will undertake assessment of rooftop area and surplus area of all
Government/ PSU buildings and premises and collate data on RTS potential (10
sq.mareafor1kWpRTS)as also on present level of electricity consumption, average
tariff being paid.
2. Based on the RTS potential, present electricity consumption and average
tariff, financial savings would be assessed
3. The Government will confirm their willing ness to participate in this scheme based
in their RTS potential and possible savings and intimate MNRE and/ or State Nodal
Agency regarding preferred model and methodology for its RTS project
4. MNRE/Sate nodal Agency will assess RTS potential and set target capacity for RTS
potential projects of those entities who agree (as and when they agree) to participate in
the programme and are willing to seek incentive. Year-wise target will be finalized.
5. The target, if not completed, shall be rolled over to the next year and will be added in the
next year’s targets in consultation with the entities.
In case the Government Department opt for the CAPEX mode of the installation of
the System:
The cost/tariff of the project should be firmed up through a transparent bidding process.
The maximum incentive for S.No.1in the above table, will be limited to 25% of the
benchmark cost or the cost arrived through competitive bidding process, whichever
is lower, for general category States/UT sand 60% of the benchmark cost or the cost
arrived through competitive bidding process, whichever is lower, for special
category States/U'I's/ Islands. Similarly, for S. No. 2 above, it will be limited to 15%
for general category States/ UTs and36% for special category States/UTs/
Islands.ForS.No.3above,itwillbelimitedto10%forgeneralcategoryStates/U'I's and
24% for special category States/U'I's/ Islands.
IncasetheGovernmentDepartmentoptfortheRESCOmodeoftheinstallationof the
System:
In this case, thedevelopers areselected through atariff-based reverse bidding. The
incentiveamountwillbeupto25%ofthebenchmarkcostasmentionedinthetable above
for general category States/U'I's, The benefit of the incentives should be
passedontothecustomerintheformofreducedtariffbyfactoringincentive.In case
ofspecialcategoryStates/U'I's/Islandstheapplicableincentiveswillbeupto60%of the
bench mark cost.
2.Methodologyadoptedtodetermineactualpotential on
identified buildings in
STPP area, Telangana.
Feasible System
RooftopAr FeasibleSolar Size
S ea for Plant without obtained
l Location Zone SPV (in Shadow fromHeli Remark
sq. m) Analysis(inkW os cope
N
p) (kWp)
o
1 U#1&2 TG Rooftop EZ 259 22 9
2
3
3.Technology selection
Solar photovoltaicconversionisthedirectconversionofsunlightinto.Photovoltaicdevices are
rugged and simple in design requiring very little maintenance and their biggest advantage
being their construction as stand-alone systems togive outputs frommicro to
mega.Hence,theyareusedforpowersource,waterpumping,remotebuildings,solar home systems,
communications,satellitesandspacevehiclesandforevenmegawatt-scalepower plants.
Aphotovoltaicpowergenerationsystemconsistsofmultiplecomponentslikesolarcells,
mechanical and electrical connections, mountings, and means of regulating and/or modifying
the electrical output .These systems are rated in peak kilo (kWp), which is an Amount of
electrical power that asystemisexpectedtodeliverunderstandardtest conditions, when the sun
is directly overhead on a clear day.
Agridconnectedsystemisconnectedtoalargeindependentgridwhichinmostcasesisthe public
electricity grid and feeds power into the grid. They vary in size from a few kWp for residential
purpose to solar power plants up to tens of GWp. This is aformofdecentralized electricity
generation.
Thinfilmsdonothavethecostadvantageintermsofinitialinvestmentcostsover the
crystalline solar cells – importantfromboth equity and debtperspectives.
ThereturnonequityishigherforcrystallinePVascomparedtothinfilmtechnology
important from both equity and debt perspectives.
Projectsbasedoncrystallinetechnologywillhavelowertechnologyriskascompared to thin
film technology.
Evaluated over the entire project lifetime of25 years, i.e. in longer term,
crystallinetechnology scores significantly higher than thin film technology. Moreover,
projectsbased on crystalline technologies can probably continue generating beyond 25
years,making them more attractive.
Apart from other factors, crystal line technologiesrequirelesslandperMW
compared to thin film technologies.
Power output from any kind of solar cell decreases with increase in temperature. It
isreported that temperature coefficient of thin film modules is lower (-0.3%/oC)
ascomparedtocrystalline(-0.4%/oC).Hence,itisclaimedthattheyaremoresuitable for hot
climate and hence will give more generation for the equivalent capacities
ofpowerprojects.However,inIndianstateslikeDelhi,Gujarat,andRajasthanalso
havewinterwhichisfavourableforcreatinglessNOCT. Therefore,low output in
summerwillbecompensatedbyhigheroutputinwinter,forcrystallinePV technology.
Basedontheaboveconsiderations,itisconcludedthatcrystallinePVtechnologiesperform
significantly better than thin film technologies in our assessment.
4.Basic engineeringofsolarpowergenerationsystem
4.1 Layout ofsolarPV powerplant
The plant design was carried out and a detail estimation of nominal capacity of Solar PV
plant,sizingofdifferentcomponentssuchasSolarPVpanel,inverteretc.withtheirrequired technical
specifications were done. The schematic of solar PV power plant is shown in Figure 1.
PowerConditioning
Unit (PCU) Supply of PCU, comprising of inverter, charge controller, visualdisplay and necessary
protections. The inverter shallbebi-
directional,haveintegratedPVchargercontrollerandratedforcontinuousoperationatfullload.It
shall have solar priority grid charging and automatic re-start after over load triggered
shutdown. The PCU shall have provision for PCU by-pass arrangement soastocater load
directly through grid, incase of PCU failure .There shall also be emergency stop switch on the
front panel of PCU. The PCU shall also have web enable data Logger with all required
hardware, software for performance monitoring including supply of SIM, IP address and
GSM Modem.
Thedataloggershallhavefeaturesforsimultaneousmonitoringandrecordingofvariousparametersofdiffer
ent sub-
Detailed Project Report for Installation of Grid-Connected Solar Rooftop Power generating plants for STPP
1
9
Detailed Project Report for Installation of Grid-Connected Solar Rooftop Power generating plants for STPP
Detailed Project Report for Installation of Grid-Connected Solar Rooftop Power generating plants for STPP
Detailed Project Report for Installation of Grid-Connected Solar Rooftop Power generating plants for STPP