Week Sales MA(3) Forecast Error Absolute Square Percentage Error
1 39
2 44
3 40
4 45 41 4 4 16 8.88888888888889
5 38 43 -5 5 25 -13.157894736842
6 43 41 2 2 4 4.65116279069768
7 39 42 -3 3 9 -7.6923076923077
8 38 40 -2 2 4 -5.2631578947368
Sum -4 16 58 -12.5733086443
MFE
MAD
MSE
MAPE
MPE
Absolute Week Actual Sales MA(3) F/E Absolute Square A/P/E
1 39
2 44
3 40
8.888889 4 45 41 4 4 16 8.8888889
13.15789 5 38 43 -5 5 25 13.157895
4.651163 6 43 41 2 2 4 4.6511628
7.692308 7 39 42 -3 3 9 7.6923077
5.263158 8 38 40 -2 2 4 5.2631579
39.65341 Sum -4 16 58 39.653412
Mean Forecast Error -0.8
-0.8 Mean Absoture Error 3.2
3.2 Mean Square Error 11.6
11.6 Mean Absotute Percentage Error 7.9306824
7.930682 Mean Percentage Error -2.514662
-2.514662
P/E
8.8888889
-13.15789
4.6511628
-7.692308
-5.263158
-12.57331 0
Week Sales MA FE ABS SQR ABS/P/E P/E
1 39
2 44
3 40
4 45 41 4 4 16 8.888889 8.888889
5 38 43 -5 5 25 13.15789 -13.15789
6 43 41 2 2 4 4.651163 4.651163
7 39 42 -3 3 9 7.692308 -7.692308
8 38 40 -2 2 4 5.263158 -5.263158
SUM -4 16 58 39.65341 -12.57331
Weights: 0.4,0.3,0.2,0.1(Rece
Week Sales WMA(4)
1 39
2 44
3 40
4 45
5 38 42.7
6 43 41.1
7 39 41.6
8 38 40.6 Week Sales WM/A
1 39
2 44
3 40
4 45
5 38 42.7
6 43 41.1
7 39 41.6
8 38 40.6
Weights: 0.4,0.3,0.2,0.1(Recent)
Week Sales
1 39
2 44
3 40
4 45
5 38 42.7
6 43 41.1
7 39 41.6
8 38 40.6
Weights: 0.4,0.3,0.2,0.1(Recent)
Week Sales Forecast
1 39 39
2 44 39
3 40 40
4 45 40 a=0.2
5 38 41 a*At+(1-a)Ft)
6 43 40.4
7 39 40.92
8 38 40.536
Week Sales Forecast
1 39 39
2 44 39
3 40 40
4 45 40
5 38 41
6 43 40.4
7 39 40.92
8 38 40.536
Week Sales Forecast
1 39 39.000
2 44 39.000
3 40 40.000
4 45 40.000
5 38 41.000
6 43 40.400
7 39 40.920
8 38 40.536
a=0.2
a*At+(1-a)Ft)
a 0.2
b 0.2 level=a*at+(1-a)*Lt-1+Tt-1
Trend=B*(Lt-Lt-1)+(1-B)*T1
Period Actual Level Trend Forecast Error
1 155
2 180 180 25 Period
3 260 216 27.2 205 55 1
4 560 306.56 39.872 243.2 316.8 2
5 160 309.1456 32.41472 346.432 -186.432 3
6 185 310.2483 26.1523072 341.5603 -156.5603 4
5
6
level=a*at+(1-a)*Lt-1+Tt-1
Trend=B*(Lt-Lt-1)+(1-B)*T1-t
Actual Level Trend Forecast
155
180 180 25
260 216 27.2 205
560 306.56 39.872 243.2
160 309.1456 32.41472 346.432
185 310.2483 26.15231 341.5603
Period Actual Level Trend Forecast
1 155
2 180 180 25
3 260 216 27.2 205
4 560 306.56 39.872 243.2
5 160 309.1456 32.41472 346.432
6 185 310.2483 26.15231 341.5603
a 0.2
b 0.2
level=a*at+(1-a)*Lt-1+Tt-1
Trend=B*(Lt-Lt-1)+(1-B)*T1-t