Professional Documents
Culture Documents
Project Planning
Project Planning
Project Planning
Duration
4
5
3
3
2
Precedence
A
A
B, C
Activities Table
Events :
(vertices)
C
T
(Time reqd. for activity)
Duration
4
5
3
3
2
Precedence
A
A
B, C
Project
Start
B
E
Project
End
Project
Start
C
Project
End
E
Design bracket
Build bracket B
Build panel
C
Drill holes in panel
A
C
A
C
A
A
D
A,C
B
D
Project
Start
B
5
3 C
D
3
E
2
Project
End
A
4
Project
Start
B
5
3 C
D
3
E
2
Project
End
0
Project
Start
A
4
B
5
3 C
7
D
3
E
2
Project
End
9
0
0
Project
Start
A
4
B
5
4
4
3 C
7
7
D
3
E
2
Project
End
9
9
0
0
Project
Start
A
4
B
5
4
4
3 C
7
7
D
3
E
2
Project
End
9
9
This project cannot be completed in less than 9 weeks given the expected duration of the activities.
However, activities B & D could be delayed or extended by up to 2 weeks each without affecting the
minimum project completion time. This is termed float or slack time.
0
0
Project
Start
A
4
B
5
4
4
3 C
7
7
D
3
Project
End
E
2
9
9
Example
Activity
A 3
B 3
C 4
D 1
E 3
F 2
G 2
H 4
I
1
J 3
K 5
Duration
A
C
B, D
A, B, D
C, F
G
C
E, G
F, H, I
Precedence
Example
B
A
Project
Start
E
J
F
G
D
C
I
Project
End
Example
Activity
Duration
Earliest
Start
Latest
Start
Float
13
10
10
13
10
16
14
14
Duration
TM
TS
TL
TEST
Earliest
Start
Latest
Start
Float
3.0
0.5
0.5
3.0
3.5
0.5
10
4.83
1.67
4.83
4.83
3.33
6.50
14.84
8.34
2.67
6.50
6.5
2.17
9.17
9.17
4.17
11.34
11.34
1.17
4.83
14.34
9.51
3.17
11.34
18.17
6.83
12
5.83
15.51
15.51
PERT/CPM
The critical path has now become C-D-F-G-H-K
with a total estimated time of 21.3 days
(i.e. 15.51 + 5.83)
The std. deviation along the critical path is the
square root of the sum of the individual
variances:
CP = C2 + D2 + F2 + G2 + H2 + K2
which for this data is 2.36 days