Schedule Calculations
Computer Support for Successful Project Management: Using MS
Project 2016 with Construction Projects by Ulhas M. Samant
Understanding Relevant Terms
Critical Path: Critical Path is the longest path through a project network. It, therefore determines the
Free Float: The amount of time an activity can be delayed without delaying the early start date of its
successor.
B C
3 weeks 8 weeks
E
A End
Start 5 weeks
3 weeks
D
6 weeks
3
Computation of Total Float
Duration
ES EF
Float
LS LF
4
Forward Pass and Backward Pass
6 6 14
3
B- 3 weeks C-8 weeks
6 6 14
3
0 3 14 19
Start A- 3 weeks E-5 weeks End
0 3 14 19
3 9
D-6 weeks
8
14
5
Critical Path & Slack in MSP