You are on page 1of 41

Physical Acoustics Ltd VPAC -

Quantification of Through Valve Gas &


Liquid Losses

Physical
. Acoustics Limited © 2009 1
Overview
 VPAC – Valve leak detection system and technology package.
5131 – is the hardware component made by Physical Acoustics.

 Physical Acoustics developed VPAC with BP and Shell (since


1982). PAL manufacture the hardware and sell package under
licence.

 Identification of leaking/passing valves is important for safety and to


minimise losses.

 Physical Acoustics Ltd, based in Cambridge, provides


- VPAC systems
- Operator training (on and offshore)
- Valve testing services with trained VPAC engineers
- System maintenance, repairs and spare parts
- Consultancy and advice on use and testing strategy

Physical
. Acoustics Limited © 2009 2
Principles Of AE Leak Detection

 Acoustic Emission (AE) is Structure Borne Noise.

 AE May Be Generated By:


- Propagating Cracks
- Spalling Corrosion Product
- Turbulent Flow

 VPAC detects leak “hiss” caused by turbulent


flow, which is measured in dB (AE)

Physical
. Acoustics Limited © 2009 3
Acoustic Emission Generation
Open Valve Sensor & VPAC
(laminar flow)

If a valve is open there will be laminar flow that generates little or no noise.

Physical
. Acoustics Limited © 2009 4
Acoustic Emission Generation
Tight Valve Sensor & VPAC
(little noise)

A tight valve makes very little noise.

Physical
. Acoustics Limited © 2009 5
Acoustic Emission Generation
Turbulent Flow Sensor & VPAC
(significant noise)

A passing valve creates turbulent flow and hence acoustic noise. The AE
is transmitted into the valve body and can be detected with the 5131.

Physical
. Acoustics Limited © 2009 6
VPAC / 5131
DEVELOPMENT

Physical
. Acoustics Limited © 2009 7
B.P. and Shell Development
Program
 1982 - BP evaluation of technologies for valve leak
detection/quantification.
 1984 - BP concentrated on AE technology for laboratory
testing and field trials.
 1984 -1990 BP extensive field trials and database
development.
 1991 - BP/PAL specification of new instrument.
 1994 - BP license technology to PAL.
 1997 - BP & Shell develop liquid & gas ESD/large diameter
valve correlations.
 Physical Acoustics sells and supports VPAC worldwide.

Physical
. Acoustics Limited © 2009 8
Database Development
 Identify leaking valves using AE monitor

 Remove leaking valves from service

 Re-test valves in lab. using flow-meter and acoustic


monitor to develop database

 1984-1990 800 valves, up to 18”, plug, gate, ball, globe,


PSV, PCV, and others

 Develop graphical and numeric correlation from the


database

Physical
. Acoustics Limited © 2009 9
Physical
. Acoustics Limited © 2009 10
VPAC - Field Experience
 5-10% of valves suffer
through-valve leakage.

 1-2% of these passing


valves are responsible for
75% of total losses.

 Leaks can exceed 1000


litres/minute

 Leaks down to <1 litre/min


detectable
Physical
. Acoustics Limited © 2009 11
VPAC - Field Uses

 Maintenance planning – identify leaking valves prior


to shut down.
(Safety Issues).

 Reduces losses to atmosphere through vent pipes.


(Environmental Issues).

 Reduce loss to flare (even if there is a gas recovery


system savings can be made).
(Reducing Costs).

Physical
. Acoustics Limited © 2009 12
VPAC - Field Uses

 Trouble shooting – tracing leaks and sources of cross


contamination.

 Re-qualifying PSV’s after operation.

 ESD’s testing (save 6-12 hrs production).

Physical
. Acoustics Limited © 2009 13
Some VPAC Customers
 Shell Exploration and Production UK, OneGas, Shell
Sweden, Shell Denmark, Shell U.K. Oil
 Sapref, Natref, StatoilHydro, HPCL
 BP, SRC, Nerefco, Petrofac
 Gulf Oil, Total, NAM, OK, Noretyl, Neste Oil
 Lindsey Oil, Natref, ConocoPhillips, Indian Oil
 Phillips Petroleum, Irish refining, BPCL
 British Gas, BSP, Saudi Aramco (Multiple Sites)
 TAKREER, PDO, ChevronTexaco, Occidental, Ras
Gas, Shell Brunei, Oman LNG ………………

Physical
. Acoustics Limited © 2009 14
“1993 VOC losses AU$9m [~US$12m], cut to half (14,342
tonnes) by end 1995, by end 1996 cut to 4821 tonnes.”
(28,684 tons per annum to 4821 tons per annum)

Physical
. Acoustics Limited © 2009 15
Overview of Shell VPAC Project
 PAL have recently supplied Shell and One Gas with 18 VPAC systems as
part of the UpGrade Project

PAL have trained on the Shell Anasuria, Brent B and C, Dunlin, Eider,
Gannet, Nelson, North Cormorant, Shearwater and Tern platforms.

PAL also have trained and provide VPAC testing services at Shell St
Fergus.

PAL have also trained on the OneGas East AWG-1C, F3-FB-1, K8-FA-1,
K15-FA-1, K15-FB-1, L2-FA-1, L5-FA-1, L9-FF-1 and L13-FC-1 platforms

 PAL are about to start VPAC training campaign in the southern UK north
sea for OneGas West

In total PAL have trained about 400 offshore personnel in VPAC testing

Physical
. Acoustics Limited © 2009 16
VPAC SYSTEM

Physical
. Acoustics Limited © 2009 17
VPAC – 5131 System

 Portable unit (2kg)


 I.S. Sealed unit
 Battery charger
 2 x HF sensor
 Case
 Wave guide
 User manuals
 Leak rate
calculation excel
Physical
. Acoustics Limited © 2009 18
Using VPAC
 To turn on, press Enter.
 Wait until Auto Ranging completed.
 Make measurements.

Stored Memory Point (1-300) Current Measured Value

1 13 50

Stored Value At Memory Point


 Record dB value in excel work sheet against valve I.D. along with
differential pressure.
 Hold down M button for a few seconds to power down (or system
has auto switch off in 2mins).
 Enter record into excel SW table for permanent records.

Physical
. Acoustics Limited © 2009 19
Testing Process
 Ensure the valve is closed.

 Valve must be subject to differential pressure 0.5 bar


gases, 3 bar liquids (these are minimum pressures as flow
must be turbulent).

 Clean away loose rust and scale.

 Hold sensor on valve body using grease as acoustic


couplant.

 Let measurement stabilise - take reading.

 Take upstream and downstream readings to check valve


is source.

Physical
. Acoustics Limited © 2009 20
Measurement Positions Valves <24”

Note it is good practise to make several


Physical
. Acoustics Limited © 2009 measurement per valve 21
Measurement Positions Valves over 24”
• Make a measurement
approximately every
300mm across the body
of the valve and flanges

• Use the highest VPAC


reading the loss control
equation

Physical
. Acoustics Limited © 2009 22
Plant Noise
• <10% of plant valves may have noise from other site
processes and you will experience it.

• VPAC measurements upstream and down stream ensure


that VPAC reading at valve is leak and not false.

• Valve reading must be 6dB+ than upstream/down stream


reading to be used in the leak rate equation.

• No compensation is required in the spread sheet - use peak


VPAC reading from valve

Physical
. Acoustics Limited © 2009 23
Noise Measurement Positions
Ideally noise check measurements are 0.5 -1m from valve

0.5 -1m 0.5 -1m

Noise check point

ONLY USE VALVE MEASUREMENT IN LEAK CALCULATION


Physical
. Acoustics Limited © 2009 24
Plant Noise – Example Results

Up stream Valve Down stream Result


13dB 13dB 13dB No leak
19dB 52dB 19dB Leak
62dB 72dB 23dB Leak
71dB 52dB 52dB Noise

Remember – there is no need to compensate for up/down stream


readings if measurement at valve is 6dB bigger.
Physical
. Acoustics Limited © 2009 25
5131 Menu Functions

 For normal operation use as delivered.

 There are option changes that can be


made – But these have no benefit to
testing.

 No Need to Change Settings!

Physical
. Acoustics Limited © 2009 26
VPAC LOSS CALCULATION
SPREADSHEETS

Physical
. Acoustics Limited © 2009 27
Spreadsheet Calculation of Losses
4 leak rate equations
- Gases <18 Inch
- Liquid <18 Inch
- Gas ESD, large
valves 18< and soft
seat valves
- Liquid ESD, large
valves 18< and soft
seat valves

Physical
. Acoustics Limited © 2009 28
Using Estimation Software

 Simple Excel format.


 Calculations built In.
 Make sure correct spreadsheet is used GAS,
LIQUID, ESD.
 During Measurement Note:
- Valve ID -5131 Reading
- Inlet Valve Size -Valve Type
- Differential Pressure - Product

Physical
. Acoustics Limited © 2009 29
Which Spreadsheet?

There are four pages in the Shell platform specific


Excel spreadsheet – make sure you use the
correct one.
 VPAC Gas – Gas up to 10” diameter
 VPAC Liquid – Liquid up to 10” diameter
 VPAC Gas – Gas over 10” diameter
 VPAC Liquid – Liquid over 10” diameter

Physical
. Acoustics Limited © 2009 30
Other Considerations

 Safety
 Intrinsic Safety
 Operating temperatures and use of wave guides
 Trouble shooting
 Lagging / Insulation
 Online monitoring

Physical
. Acoustics Limited © 2009 31
Safety
 Consider if you need to raise a permit to carry out VPAC testing.

 Always carry VPAC system in the case with sensors pre-connected


and stored in the front pouch. This will protect the system and stop it
catching on plant and scaffold etc.

 Climb ladders with 2 hands with the case over your shoulder.

 If using the wave guide fit it in a leather sheath – if not needed leave it
behind.

 Never put the wave guide in your pocket as it could spear your leg or
fall out.

 Wash our hands and wipe down sensors/cable to remove grease.

Physical
. Acoustics Limited © 2009 32
Intrinsic Safety
 The unit is IS certified as long as its not tampered
with.

 This unit Cannot be user serviced.

 If unit malfunctions contact PAL. Do not open the


casing, this will invalidate the IS certification.

 Remember to connect and disconnect the sensor


only in a safe, gas free environment

Physical
. Acoustics Limited © 2009 33
Surface Temperatures

 Probe will operate at temperatures up to


1250C (not continuous contact).

 Above this temperature use a waveguide.

 But there will be a loss of signal through


waveguide – small leaks will not be
detectable.

Physical
. Acoustics Limited © 2009 34
Waveguide Correction

 When you find a leaking valve – note reading.

 Retest using waveguide – note reading.

 Make a note of difference, this gives


correction for waveguide.

 However, the readings will be unreliable and cannot be used to


estimate leak rates, they can only be used as a guide.

Physical
. Acoustics Limited © 2009 35
Lagging & Insulation
 Hot valves may well have lagging or jackets on
them.

 Customer must consider any preparation of


lagged valves in advance of test

 Never modify or cut off lagging without


permission - it may have trace element heating
underneath

 Jackets must be put back on post test and


sealed properly
Physical
. Acoustics Limited © 2009 36
Troubleshooting

 If the 5131 is used correctly faults are not common.

 Most common is probe damage due to impact damage


or at connector due to heavy handed connection /
disconnection.

 If damaged probe reads (in air) 16+dB or 6-11dB


replace probe and retest with sensor clasped in your
hand (this shields it from electric noise).

 If problem is not resolved call PAL who can advise.

Physical
. Acoustics Limited © 2009 37
VPAC Permanent Leak Sensor System
 There are many situations when intermittent
surveys are undesirable and ‘Real Time ‘ leak
monitoring is required.
 To achieve this we supply a sensor and amplifier
unit which has an industry standard 4-20 mA
output.
 This provides an intrinsically safe solution for leak
detection in hazardous environments. 1276 zener
Barrier – 1278 galvanic barrier.

Physical
. Acoustics Limited © 2009 38
VPAC ONLINE IS Sub System

4-20 MA
output to
DCS or
turnkey
system

Physical
. Acoustics Limited © 2009 39
What next - Hands On!

Physical
. Acoustics Limited © 2009 40
VPAC Training Course

Thank you for your attention.

Do you have any questions?

Physical
. Acoustics Limited © 2009 41

You might also like