Professional Documents
Culture Documents
Sandesh
Sandesh
ESTIMATING PROCESS
ESTIMATING USING
HAND HELD DEVICES
The process of estimating is part art, part science. The estimator generally follows certain
steps in developing the estimate
– Break the project into cost centers
– Estimate the quantities required for cost centers that represent physical end items
(e.g. cubic yards of earth, linear feet of pipe etc). For physical systems this
procedure is commonly called quantity take off.
– Price out the quantities determined in step 2 using historical data, vendor quotations,
supplier catalogs and other pricing information. The pricing may be base on a price
per unit (unit cost) basis or a lump sum (one job) basis. Price developments for
physical work items may require an analysis of the production rates to be achieved
based on resource analysis. If this is used, the estimator must:
Assume a work team composition to include number of workers and equipment
used
On the basis of team composition, estimates on an hourly production rate are
based on the technology used
Make an estimate of the efficiency to be achieved on this job
Calculate the effective unit price
– Calculate the total price for each cost center
The estimator usually summarizes the values for each cost center on a summary sheet
such as that shown in Figure 13-3.
Figure 13-3 Typical Estimating
Summary
DEFINITIONS OF COST CENTERS
The subdivisions into which the project is divided for detail cost estimation
purposes are variously referred to as:
– Estimating accounts
– Line items
– Cost Accounts
– Work Packages
As described in Chapter 6, the team “work package” has become current over
the past 20 years and is commonly used to indicate a subdivision of the project
that is used for both cost control and scheduling (i.e. control time)
When both cost and time control systems are combined into an integrated
project management system, work packages are controlled to determine cost vs.
estimate and time vs. schedule
The subdividing of the project into work packages results in the definition of a
work breakdown structure (WBS)
A work package is a well defined scope of work that usually terminates in a
deliverable product. Each work package may vary in size but must be a
measurable and controllable unit of work to be performed. It also must be
identifiable in a numerical accounting system in order to permit capture of both
budget and actual performance information. A work package is a cost center.
QUANTITY TAKEOFF
The development of the quantities of work to be placed in appropriate units (e.g.
square feet, cubic yards, etc.) is referred to as the quantity takeoff (QTO) or
quantity surveying. The procedures employed by the estimator to calculate these
quantities should incorporate steps to minimize errors. Five of the most common
errors experienced during quantity takeoff are:
– Arithmetic: Errors in addition, subtraction and multiplication
– Transposition: Mistakes in copying or transferring figures, dimensions, etc.
– Errors of Omission: Overlooking items called for or required to accomplish the
work
– Poor Reference: Scaling drawings rather than using the dimensions
indicated
– Unrealistic waste or loss factors
The first step in quantity takeoff procedures is to identify the materials required by
each estimating account or work package
After that, relevant dimensions are recorded on a spreadsheet so that quantity
calculations in the required unit of measure can be made
Before the calculations for the QTO are performed, detailed working drawings are
sometimes required to clarify the contract drawings and specifications or the
chosen construction method (e.g. forming technique)
QUANTITY TAKEOFF CONT’D
Such a drawing for a small wall is given in fig. 13-4
From these drawings and details a checklist should be developed to
indicate all of the materials required for each work package
The actual calculations should be performed on a standard spreadsheet
to allow independent checks and self checks
All supporting documentation should be attached to the estimate to aid in
checking by other sources
A materials takeoff sheet for the small wall (fig. 13-4) is given in fig. 13-5
A summary or “recap sheet” should be made. This recap sheet should
consists of a listing by material type, of all materials required for the
entire work team or package
The listing should also include appropriate waste and loss factor
calculations. An example of a recap sheet is given in fig. 13-6
In practice, most companies use computerized databases and
spreadsheet programs to prepare final estimates
Figure 13-4 Small Wall Construction
(CMU = Concrete Masonry Unit)
Figure 13-5 Activity Material List
Figure 13-6 Construction Support
Material Recap Sheet
METHODS OF DETAILED COST
DETERMINATION
After quantities have been determined for accounts that are relevant to the project at hand,
the method by which costs will be assigned can be selected. The two methods of cost
determination most frequently used are:
– Unit pricing
– Resource enumeration
If the work, as defined by a given estimating account is fairly standard, the cost can be
calculated by simply taking dollar per unit cost from company records and applying this
cost with a qualitative correction factor to the quantity of work to be performed
For instance, if the project calls for 100 linear feet of pipe and historical data in the
company indicates that the pipe can be placed for $65 a linear foot to include labor and
materials, the direct cost calculation for the work would yield a value of $6500
Unit pricing values are available in many standard estimating references
The standard references normally give a nationally averaged price per unit. A multiplier is
used to adjust the national price to a particular area
Among the largest and best known of these services are:
– R.S. Means Company, Building Construction Cost Data
– F.R. Walker’s, The Building Estimator’s Reference Book
– The Richardson General Construction Estimating Standards
These references contain listings of cost line items similar to the cost account line items a
contractor would maintain
METHODS OF DETAILED COST
DETERMINATION CONT’D
The development of direct costs to include overhead and profit for a particular line
item using the R.S. Means system is shown in fig. 13-7
The line items specified in the R.S. Means Construction Cost Data are defined by
using the uniform construction index numerical delineators
The system assumes a given crew composition and production rate for each line
item
In the case illustrated a standard crew designated C-1 can construct 190 SFCA
(square foot contact area) of plywood column form per shift (daily output)
This underlines the fact that unit pricing data must make some assumption
regarding the resource group (i.e. crew, equipment fleet, etc.) and the production
rate being used
That is, although unit pricing data are presented in dollars-per-unit format, the cost
of the resources group and rate of production achieved must be considered
The dollars-per-unit value is calculated as follows
Cost of resources per unit time $/hour
= = $/unit
Production rate of resource unit/hour
METHODS OF DETAILED COST
DETERMINATION CONT’D
• Combining this installation cost with the materials cost per unit of $2.60
yields a bare unit cost for materials and installation of $6.80
• The overhead and profit (O&P) charges associated with labor (as
considered in the Means system) are:
- Fringe benefits (included in bare costs)
- Workmen’s compensation
- Average fixed overhead
- Subcontractor overhead
- Subcontractor profit
• In order to adjust the bare costs of installation to include
subcontractor’s O&P, the appropriate craft values for the members of
the craft are located and applied. For the carpenters the total correction
is 59.7% or $15.05/hr.
• Therefore, the carpenter’s rate is to include O&P at $40.25/hr.
Simililarly, the labor rate is adjusted to $31.60/hr to include O&P
Figure 13-7 Line Item Cost
Development using R.S. Means Data
METHODS OF DETAILED COST
DETERMINATION CONT’D
Clearly the numerator (cost of resources per unit time) of the unit-
cost ratio will vary significantly over time as the costs of labor and
machines vary
The costs of all components of the construction process have risen
sharply over the past 20 years. This is shown dramatically in the
ENR Construction and Building Costs indexes shown in chapter 2
In order to factor out the inflationary escalation inherent in resource
costs, some contractors maintain the ratio of man-hours or
resource hours required rather then dollars per unit. This
establishes a company data-base tied to resource hours required
rather than dollars per unit
Therefore, the contractor can retrieve a man-hour or resource-hour
(RH) per unit for each line item
The value is calculated as:
Resource hours per hour = RH/unit
Units per hour
PROBLEMS WITH UNIT-COST
METHOD CONT’D
In the unit pricing approach the resource costs and the production rates
are the aggregate value of resources and rate accumulated on a number
of jobs over the period of historical data collection
With the resource enumeration approach, the estimator specifies a
particular crew or resource group at a particular charge rate and a
particular production level for the specific work element being estimated
This should yield a much more precise cost-per-unit definition
The disadvantage with such a detailed level of cost definition is the fact
that it is time consuming
Therefore, resource enumeration estimating would be used only when:
– Items for which no unit cost data are available
– “Big ticket” items, which constitute a large percentage of the overall cost of
the job and for which such a precise cost analysis may lead to cost savings
– Extremely complex work for which unit-pricing deemed in adequate
Figure 13-9 Resource
Method of Estimating
Figure 13-10
Labor Resource
Enumeration
WORK PACKAGE OR
ASSEMBLY-BASED ESTIMATING