CINNOTECH CORPORATION

Presentation to SMB - Procurement


July 08, 2019
Brief Company Profile
• Registered with SEC / Office Address: 35th Floor, Eco Tower Building, BGC
• Some background - from RV Technologies to CINNOTECH Corporation
• Business model – design, supply & installation/commissioning of analytical
process instruments, remote monitoring & control for process/packaging
equipment
• Applications - air and water quality monitoring and treatment, food &
beverages, power & energy, petrochemical, refineries, cement & mining,
etc.
• Acquire and provide leading European technologies in the Philippines thru
Strategic Partnerships
Our Partners - Waste Water Solutions
Summary of discussion with Davao Brewery Packaging Department

1) Confirm availability of power supply going to the new "Hermis" Tunnel Pasteurizer 440 Volts (three phase) 60 Hz.
Kindly provide details of the location where "Hermis" Motor Control Center cabinets will be placed including actual
position where the HMI control cabinet will be located. It would help if a layout can be provided with final location of
these cabinets that clearly shows physical dimensions/measurements of the floor area (for cable estimation,
equipment footing, etc.).

2) Copy of the existing floor layout of Line 2 that includes the position/concrete footing of the old pasteurizer to be
replaced; this would help us plan for the dismantling of the old pasteurizer and for installing the new "Hermis"
pasteurizer.

3) We would also like to have an estimate of the piping layout (length & DN size of the pipe if possible) of the
"coolant" coming from San Miguel's refrigeration plant, that will be needed by the "Hermis" tunnel pasteurizer in
order to operate the heat exchanger.

4) Lastly, a copy of the scope of work for this project that states the parameters that need to be met by the new tunnel
pasteurizer as required by your Brewing Technical Group.

Note: Hermis mentioned that at least six months lead time is needed to fulfill the order in case this project is awarded to
them
Tunnel Pasteurizer - San Miguel Brewery Davao Plant Last Quarter 2019 First Quarter 2020
Jul-Aug Sep-Oct Nov-Dec Jan-Feb Mar-Apr Apr-May
Details of Tasks - New Tunnel Pasteurizer Installation
a) Awarding of Contract by San Miguel Beer
1. Pre-bidding (Invitation of Bidders) & Bidding Submission
2. Awarding of P.O. & Contract Signing
b) Engineering Discussion/Clarification
1. Polishing of Specifications (revisions, etc.)
2. Coordination of delivery of equipment
c) Schedule of Delivery
1. Tracking of production of equipment (delays, final shipping date, etc.)
2. Total no. crates/containers & final inventory
3. Actual Delivery to site/customs processing
e) Commissioning of New Tunnel Pasteurizer
a) Dismantling of old Pasteurizer (2 weeks)
b) Actual installation & commissioning of new pasteurizer
d) Final - Production Run