Tel: 03 – 8082 3339 H/P: 012 – 601 6008 Fax: 03 – 8082 3339
Date: 30/10/2023
Tender Clarification
We would like to clarify few matters regarding to your tender submission that we had
received for the abovementioned project.
1 Are you fully read and understand the job scope recommended and able to YES
comply all the requirement?
A: Yes we fully understand and comply to the job scope which was given to
us
2 Do you aware that this project to be completed within 6 months without any YES
extension of time and variance order.
A: Yes we are aware that we have to complete this job within 6 month time
period without the EOT due to ship docking at the wharf area. We hope
Westport can provide us with the proper docking schedule for us to plan
and execute our job.
3 Do you aware that this project will be carried out according to operational YES
schedule, where contractor to prepare necessary manpower and completion to
be on time?
4 Do you have done any other similar project which is done recently? Please YES
provide necessary supporting document and referral letters from the clients.
A: Yes we have done many other projects in this fire fighting industry. Our
organization is proper company certified by the BOMBA, MOF, Cidb, TNB
and Telekom for fire fighting jobs. We have attached our track record for
your perusal.
5 Do you have skilled manpower, tools, equipment, machineries and materials YES
supply sufficiency to complete this project within the timeline given? Supporting
documents require.
6 Based on your study, what is the actual power and man-hours required to YES
complete this entire project within given timeframe. Please proved manpower and
man-hours calculation in simple table format.
A: Yes, 90% of the materials being used for this project will be locally
manufactured and supplied locally. However there might be few items which
might need to be imported from overseas which would be taking time an
approximately 2-8 weeks maximum.
8 You are requested to provide simple method of statement and projection plan for YES
the entire project completion. Please attached your supporting documents.
A: Yes we have attached a proper method of statement for the above tender.
Please refer to the attachment in the email.
If the contract awarded to your company, what is the facilities, supports do you YES
9 feel needed form our end to ensure project completion timely without
compromise quality of works.