PIPE BURSTING
Manhole to Manhole
and
METHOD OF STATEMENT
1. Scope of Work
2. Planning
3 . S t a ge 1
a. Site Inspection
b . R e vi e w o f C C TV Re p o r t s
c. Manhole Inspection
d . S u b s u r f a c e Ut i l i t y E n g i n e e r i n g
4 . S t a ge 2
a. Material Selection
b . C o m mi s s i o n i n g o f H DP E
c . M a n h o l e t o Ma n h o l e B u r s t i n g
i . M a n h o l e I n ve r t U p s i z i n g
i i . V a c u u m E xc a va t i o n
d . T e mp o r a r y P u mp i n g
5 . S t a ge 3
a . L a t e r a l Co n n e c t i o n
b. Connection of Pipeline
c . C o m mi s s i o n i n g o f Re p l a c e me n t P i p e
d . D e c o m mi s s i o n i n g o f e xi s t i n g p i p e l i n e
a.Site Inspection
Visual site inspection are must for pipe bursting to ascertain the
actual site condition and constrains.
To review existing CCTV reports and record will determine the internal
severity condition of the propose bursting section of manhole to
Manhole and also to determine lateral positioning. Therefore Pre and
Post CCTV is must for any pipe bursting projects.
Prior to pipe bursting , All Debris such as dirt, sand, rocks, grease,
and other solid or semisolid material resulting from the cleaning
operation shall be removed at the downstream structure of the section
being cleaned.
c.Manhole Inspection
4.Stage 2
a.Material Selections
Designed for use with the Hammerhead and PB static and pneumatic
pipe bursting system, “Snaptight” is a proprietary jointed pipe using
push and pull method. A range of outside diameters from 150mm to
500mm is available. A full list of sizes is shown in the table below.
Completed work
The following works are to be completed before a request to connect
new pipes can be made:
c . M a n h ol e t o M a n h ol e Bur s t i ng
If the old pipe has collapsed PB Burst can be used to bore through
the collapse.
The new pipe push through using PB Steel Rod Pulling 75mm of 1m
length each ideally suitable where pipe upsizing isn't required, or
where the upsize is a small increase.
Method of Installation
• W inch placed into manhole 1
• W inch rods inserted into old pipe from manhole 1 and connected
to head in manhole 2.
• Head winched into old pipe, which is broken and displaced.
• New pipe is located in shield on rear of head and held in place
by simple tensioning device.
• Head is again winched forward. New pipes are snapped together
behind the head as it is winched forward.
• Above step is repeated until full length is in place.
During this modification works the existing manhole may need some
renewal of enlargement of manhole chambers to suit the new pipe
installations.
To Provide:-
5.Stage 3
Unknow n connection
The possibility is given that any replaced pipe has an unknown
connection to another pipe inside existing connection it is completely
mandatory that such connections are found and eliminated.
C o m pl e t e d w ork
The following works are to be completed before a request to
connect new pipes can be made:
b . C o n ne c t i on o f pi pe l i n e
After coordination with S.O and the Engineer the pipe can be
connected into the existing the new HDPE sewer system.
P r oc e dur e s
All lateral connection shall be notify by the SO’s representative
to the affected shop units, houses or business outlets. W ith this
inf orm ation the source of the temporary by pass shall be
organised.
Completed work
The following works are to be completed before a request to connect
new pipes can be made:
Pipes are to be laid in appropriate lengths of
generally not more than 3 meters.
Pipes are to be tested and inspected
House connections are to be installed including re -
orientation of the existing main line and shall be
tested and inspect.
Connection of pipeline
After coordination with RE and the SO, the pipe shall can be
connected into the existing trunk main or distribution main system.
The network shall than be used once to feed the house connections
through the new piping, on JPP’s supply day to the area, to make sure
that all plots are served properly.
Coordination
Coordination has to be made with IWK and the SO’s Enginee r as to
the work procedure. Also the date of expected decommissioning and
the exact location of the existing, to be decommissioned pipe are to
be fixed. Shop drawings are to be ready approved from the SO’s
Engineer.