1. SCOPE
The scope of this procedure covers the activities involved in laying High
Density Polyethylene (HDPE) Pipes to ensure that the works and
materials conform to the requirements specified in the Contract (IFC)
Drawings, approved Shop Drawings and Project Specifications.
2. FIELD OF APPLICATION
Intended usage of HDPE Pipes is for the Storm Drainage System of the
Hospital.
3. REFERENCES
4. MATERIAL SUBMITTAL
5. PROCEDURE
5.1 Ensure that the materials to be used are the same materials that
had been approved. Manufacturer’s recommendation regarding
handling and storage should be strictly followed.
5.2 The route of the pipeline shall be surveyed and set out accurately,
its trench width and depth set precisely in accordance with IFC
Drawings, which will indicate the limits to which mat foundation
reinforcing bars shall be placed. The trench shall be blocked out
prior to concreting the mat foundation.
F-P.810/1-0
J&P Document number:
M ET H O D CP 300(a)-QCP-009
S T AT E M E N T
J&P (O) Ltd. /
Page: 3 of 4
J&P–AVAX S.A. J.V.
5.4 Before placing the sand bedding, the bottom of the trench shall be
cleaned of all trash and construction debris that may possibly
cause damage to the pipe. It shall be placed at a minimum
thickness of 150mm beneath the pipe.
5.5 Jointing of pipe shall be done beside the trench before lowering
them to the prepared bed. All joints shall be fusion-welded type
(Butt Fusion or Electrofusion) in accordance with manufacturer’s
recommendation.
5.8 When work ceases on any pipeline, the unfinished end of the
pipeline shall be covered.
5.9 Pipeline shall be pressure tested after they are jointed and before
any pipe surround filling commence. Testing shall be by Air Test
and shall be in accordance with QCS Section 20 Part 7.4.4.
5.10 Sand shall be used for pipe surround and for the first 300mm
above the top of the pipe. It shall be placed in layers not
exceeding 150mm compacted thickness, thoroughly rammed with
suitably shaped rammer working alternately on either side of the
pipe.
F-P.810/1-0
J&P Document number:
M ET H O D CP 300(a)-QCP-009
S T AT E M E N T
J&P (O) Ltd. /
Page: 4 of 4
J&P–AVAX S.A. J.V.
5.11 Sand-Cement Stabilized Fill shall be used for the remainder of the
fill, compacted on layers not exceeding 250 mm unconsolidated
thickness to 95% of the maximum dry density. Backfilling and
compaction shall terminate at the bottom of basement slab on
grade.
Compaction test on fills shall be carried out at the rate of 1 test for
each layer of backfill for every 50 m of pipeline trench.
5.12 Where PVC warning tape is specified, it shall be laid between 100
mm to 300 mm above the pipe.
6. REVISIONS
F-P.810/1-0