You are on page 1of 21

CADANGAN MENDIRIKAN 1 BLOK BANGUNAN 34 TINGKAT YANG MENGANDUNGI:

(A) 6 TINGKAT PODIUM UNTUK TEMPAT LETAK KENDERAAN (TINGKAT 1 KE


TINGKAT 5) DAN KEMUDAHAN MASYARAKAT (TINGKAT 6); DAN (B) 1 BLOK
PANGSAPURI (227 UNIT) 29 TINGKAT (TINGKAT 6 KE TINGKAT 34); DAN (C) 1 BLOK
PANGSAPURI (229 UNIT) 29 TINGKAT (TINGKAT 6 KE TINGKAT 34) DI ATAS PLOT C
(LOT BARU: PT 210), SEBAHAGIAN DARIPADA PARSEL A1-4, TANAH TEBUSGUNA
JELUTONG, SEKSYEN 8, BANDAR GEORGETOWN, DAERAH TIMUR LAUT, PULAU
PINANG UNTUK TETUAN JARINGAN SIMFONI SDN BHD.

METHOD STATEMENT

PLUMBING

REV. 01

IJM CONSTRUCTION SDN BHD


(195650 H)

IJM CONSTRUCTION SDN BHD


IJMC/TLCPC/TS/M&E/MOS/ARP/11
METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

Table of Contents

1. Installation of PP-R Hot & Cold-Water Pipe

2. Installation of PVC Cold Water Pipe

3. Installation of uPVC Pipes

4. Testing & Commissioning for Hot & Cold-Water Pipe and uPVC Waste Pipe

5. Installation of Poly Tank

6. Installation of Underground Pipe

7. Installation of Underground Sewage Pipework

8. Installation of Cold-Water Pumps

9. Installation of Hydro Pneumatic Pump sets

EEU ENGINEERING SDN. BHD Page 1


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

1.0 INSTALLATION OF PP-R HOT & COLD-WATER PIPE

1.1 General

The PP-R pipes and fittings are joint with socket fusion.

1.2 Instruction for socket fusion

1.2.1 Preparation

a) Fix heating bushes – attached the heating bushes on the heating tool.
Maximum two set of bushes can be attached in the same time.

b) Check the temperature – Once the socket fusion machine is on, set the
temperature on the electronic display, which must range between 255°c and
265°c. To ensure correct temperature, frequent calibration is recommended.

c) Clean the heating tools – After checking the temperature, wipe the heater bush
with a clean cloth. This operation must be repeated after each welding.

d) Cut the pipe – Cut the pipe at right angle, if necessary, remove burrs from
inside. If necessary, cut deformed damaged pipe ends.

e) Clean pipe & fitting – Clean the fitting inside and the pipe outside (the presence
of dust, grease or other impurities can affect the fusion quality and lead to
leakages).

EEU ENGINEERING SDN. BHD Page 2


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

1.2 Instruction for socket fusion

1.2.2 Fusion

a) Mark the pipe – Mark the insertion depth on the pipe for (see table). The mark
must remain visible under heating and joining.

b) Heat pipe & fitting – Push the pipe and the fitting straight into the heating
bushes. Pull out pipe and fitting slowly and without twisting once the heating
time has elapsed.

c) Joint pipe & fitting – Push the pipe into the fittings so that the welding bead of
pipe and fitting touch together. During the jointing time, small adjustment in
the angle and alignment can be made. During the cooling time, any stress on
the joint must be avoided.

d) Fusion inspection – The outer fusion bead must be inspected. A double bead
must be uninterrupted all around the pipe circumference.

EEU ENGINEERING SDN. BHD Page 3


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

2.0 INSTALLATION OF PVC COLD WATER PIPE

2.1 General

The PVC pipes and fittings are joint with solvent cement.

2.2 Procedure for jointing of PVC pipes and fittings

a) Cut the pipe clean and square to the desired length


b) Remove internal and external burrs and remove swarf
c) Without scoring the pipe, mark the pipe a known distance from the end and clear
of the area to be abraded.

NOTE: This mark is used to check the pipe penetration into the socket after
complete of joint.

d) Lightly abrade the end of pipe to be joint.

e) Lightly abrade the inside of the socket of fittings.

f) Thoroughly clean the abraded surface of pipe and fittings with a clean rag
moistened with priming fluid (MEK Cleaner).

g) Using a clean brush, apply solvent cement into the surface of pipe end and inside
of socket, ensuring complete coverage evenly on the surface.

h) Immediately after application of cement, push the pipe fully home into the
fittings.

DO NOT twist, but continue to exert the pressure necessary to hold the pipe into the
fitting 10 ~ 30 second.

i) Wipe off excess cement.

EEU ENGINEERING SDN. BHD Page 4


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

2.3 Connection of PVC pipe to other materials

a) PVC pipe can be connected to other materials by threaded or flanged joints

b) Threaded joints

• Threaded joint is recommended for smaller size of joints, i.e., 15ø to


50ø

• Threaded fittings such as male threaded and female threaded are


available.

• Applied sufficient layer of PTFE sealing tape on the male threaded


fittings and screwed to the female fittings provided at other materials
of pipes.

• Tightened the male fittings with suitable size of pipe trench.

c) Flanged joint

There are 2 kinds of flanged joint, full faced PVC socket flange and PVC
socketed slab flanges of which to be installed with a loose metal backing rings.

• All flange joints shall have a rubber gasket.

• Pipe ends for flanging shall be cut square and the jointing method refer
to item 1.2

• Tightened the PVC flanged pipe to the flange provided at other


materials pipe with proper size of bolts, nuts and washers

EEU ENGINEERING SDN. BHD Page 5


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

3.0 INSTALLATION OF uPVC PIPES

3.1 Setting out

• Upon erection of formworks by the builder, the toilets area shall be set
out as per Architecture layout by the builder’s surveyor with assistance
of the sub-contractor’s representative.

• The position of outlet pipes to be provided with temporary boxing or


cast-in-situ socketed sleeves shall be marked on the formwork.

3.2 Provision of temporary opening and cast-in-situ socketed sleeve.

• Timber boxing shall provide temporary openings or uPVC pipe


sleeves at least one size larger than the actual pipe size to be installed.

Fix the timber boxing or uPVC pipe sleeve firmly on surface of the
formwork, and insert the opening with paper to prevent checking with
concrete.

The timber shall be removed before installation of pipe works and to


be casted-back after installation of sanitary piping.

• Cast-in-situ uPVC socketed sleeves are anti-water-seepage type and


shall be provided to received the sanitary fixtures outlet pipe or floor
drain/traps waste pipe

Nail the uPVC socketed sleeve firmly on surface of the formwork and
insert paper into the sleeve to prevent choking with concrete.

EEU ENGINEERING SDN. BHD Page 6


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

3.3 Installation of aboveground uPVC sanitary pipes

3.3.1 The openings or socketed sleeves provided shall be checked to ensure at the
correct positions.

3.3.2 Measure the pipe lengths and cut to the required measurement.

3.3.3 Clean the pipe end and socket to be jointed with cloth.

Chamfer the pipe end if necessary

3.3.4 Apply solvent cement onto the pipe end and inside of socket

3.3.5 Push home the pipe end into the socket and hold firm for 20 ~ 30 seconds.

3.3.6 Fixed the pipe at slab soffit to the required height with proper pipe hanger and
adjust the required gradient.

3.3.7 Clean excess solvent cement with cloth.

EEU ENGINEERING SDN. BHD Page 7


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

4.0 TESTING AND COMMISSIONG

a) General

All inspection and testing shall be recorded on the proper form and records
approved by QA/QC

b) Pressure Test

• All piping will be hydrostatically pressure tested to 1.5 times the


maximum working pressure of the system (except for sanitary piping
which shall be flow tested)

• The test duration shall be at least 20 min and visual inspection shall be
conducted to check for leakage

• Should the pressure in the piping show not visible drop in pressure, the
pressure shall be recorded and leave for 24 hours

• Pressure test shall be considered as passed if the pressure in the pipe


after 24 hours, remained the same or dropped not more than 5%,
provided there is no visible leakage found on the joints

• If the pressure drop was greater than 5% the pipe shall be inspected
and retested.

c) Flow test for soil and waste piping

• Water shall be poured into the piping from the highest end and check
the flow at the lowest end

• All joints’ pipes and fittings must be carefully check and ensure there
is no visible leakages

• Any joint with leak must be rectify and the system retest.

EEU ENGINEERING SDN. BHD Page 8


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

5.0 INSTALLATION OF POLY TANK

• Shop drawing to be submitted prior to the installation

• To provide the 2 number of MS C Channel as support for hard wood


and poly tank.

• Check quantity and inspect conditions of tank accessories

• Fixed the poly tank on top of the wood properly

• Connection of ABS pipe to the poly tank

• Fill up the poly tank with water (when the water supply available),
check the tank any leakage

5.1 INSTALLATION OF SANITARY APPLIANCE

• All Sanitary appliances will be as per the brand and model selected by
Veritas/IJM PD.

• The position of sanitary wares on fittings appliances shall be carefully


marked and drilled to manufacture’s details.

• Protection shall be taken to prevent damages and breakages to sanitary


wares and fittings

EEU ENGINEERING SDN. BHD Page 9


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

6.0 INSTALLATION OF UNDERGROUND PIPE

6.1 Electro Fusion Jointing

• In the electro fusion process a heating wire permanently mould into the
fitting gets heated by current at a low voltage. The surrounding material
around the wire gets melted and expands due to the warming. The melt
starts closing the gap between pipe and fitting, leading to a heat transition
to the pipe which also gets heated and melts in the welding zone. The pipe
material also expands.

• The increasing material expansion between pipe and fitting, which is


hindered by the cold zones outside the welding zone, leads to a build up a
welding pressure between pipe and fitting and a homogeneous welding
connection emerges.

• Thrust block at the pipe joint shall be provided and the details shall refer
to construction drawing.

6.2 Backfilling

6.2.1 As soon as practicable, after inspection by the engineer/authorized personnel for


the pipe that has been laid and completed, the trench shall be back filled with
selected earth in order to prevent pipes from snacking or floating.

6.2.2 The jointed joint holes may be left unrefilled until the joints have been inspected /
tested.

6.2.3 Material that excavated from the trench shall be use for backfilling provided it is
lump, which may prevent adequate consolidation.

EEU ENGINEERING SDN. BHD Page 10


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

6.3 Excess earth

6.3.1 After completion of backfilling, the excess earth shall be spread to level at site
or cart-away from site to approve dumping area.

6.4 Testing

6.4.1 To local authority requirement PBAPP.

EEU ENGINEERING SDN. BHD Page 11


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

7.0 INSTALLATION OF UNDERGROUND SEWAGE PIPEWORK

7.1 Setting out & excavation

7.1.1 The sub-contractor’s site personnel in liaison with the main-contractor’s surveyor
shall establish the alignment of the pipe trench.

7.1.2 The routes of pipelines shall be pegged out.

7.1.3 The trench shall be excavated to the depths intended

7.1.4 The bottom of the trench shall be graded so that the pipe invert slopes evenly
between the adjacent invert levels.

7.1.5 The trench shall be excavated to provide for the necessary working space

7.1.6 Where pipes are to be laid on a concrete bed, extra depth shall be excavated to
receive the concrete.

7.1.7 All trenches shall be vertical sides, except for depth exceeding 4.0m, the ground
above 4.0m level shall be removed to allow for working space of excavation.
This is because the maximum depth of excavation by excavator is app. 4~5.0m
only.

7.1.8 Trench shoring may be applied when excavation works are carried out at the
following conditions:

• Soft ground
• Structure close to excavation area
• High underground water level
• Depth and shape of excavation

7.1.9 The method of shoring subjected to earth condition

EEU ENGINEERING SDN. BHD Page 12


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

7.1.10 Widths of pipe trenches

Unless specially specified or due to site constraint. The trenches shall be


excavated to the widths given in table 7.1.10 below

Table 7.1.10 Widths of pipes trenches

External diameter of pipe Clear width of trench for backfill Maximum trench width
with selected earth or sand
150 ø and below O.D + 300mm 0.900M
200ø ~ 250ø O.D + 400mm 1.150M
300ø ~ 350ø O.D + 500mm 1.140M
400ø ~ 450ø O.D + 600mm 1,130M

7.1.11 Trench excavation shall be commenced and completed as soon as reasonably


practicable after the pipes have been laid and jointed joint holes may be left
unrefilled until the joints have been inspected / tested.

7.2 Bedding

Unless specially specified, the type of bedding shall be constructed in accordance


with construction drawings.

EEU ENGINEERING SDN. BHD Page 13


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

7.3 Laying and jointing of

Vitrified Clay Pipes

• The trench shall be bedded with concrete Grade 20 (ready mix) before laying
of pipe. Thickness of bedding are shown in table 7.3

Table 7.3
Pipe dia. 100ø 150ø 230ø 300ø
Min. bed thickness 150mm 150mm 150mm 150mm

• Lift and lowered the pipes into the trench carefully and place onto the
compacted crusher run bed.

• Clean the socket joints and spigot end of pipe

• Apply a little lubricant on inside of socket joint.

• Place the rubber ring onto the spigot end, aligned the pipes and push
home the spigot end to the socket

• For pipes diameter larger than 230ø, a pipes puller may be used for
jointing of pipes.

• Upon completion of pipe joints to the required distance, check


alignment and gradient of pipes and than haunched the pipe with
20mm crusher run.

• Back fill the trench with selected earth and compact with rammer in
approved layers. Repeat filling and compact until it reached the
required level.

EEU ENGINEERING SDN. BHD Page 14


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

7.4 Backfilling

7.4.1 As soon as practicable, after inspection by the engineer/authorized personnel for


the pipe that has been laid and completed, the trench shall be back filled with
selected earth in order to prevent pipes from snacking or floating.

7.4.2 The jointed joint holes may be left unrefilled until the joints have been inspected /
tested.

7.4.3 Material that excavated from the trench shall be use for backfilling provided it is
lump, which may prevent adequate consolidation.

7.4.4 The blanket must never be power-rammed but should be lamped by hand taking
care not to strike or miss-align the pipes.

7.4.5 Main backfill on the blanket should also be hand-rammed to a height of 7.0m
above top of the pipeline at least.

7.4.6 The blanket above 0.7m above the pipelines shall be compacted as specified layer
by rammer or roller not exceed 1.0 ton, until it reached the required level.

7.4.7 Excess earth

After completion of backfilling, the excess earth shall be spreaded to level at site
or cart-away from site to approve dumping area.

7.5 Testing

• Generally, the pipe works are inspected and tested in 2 stages 1.e. before
covered up and before handed over upon completion.

1st stage: Inspection and rectification for defect pipe works

Prior covered up the pipe works, inspection shall be carried out to locate any
defects in the pipe works and rectified as necessary.

2nd stage: CCTV testing & report as required for O.C. clearance by IWK/JPP.

EEU ENGINEERING SDN. BHD Page 15


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

8.0 INSTALLATION OF COLD-WATER PUMPS

8.1 Selection and Submittal

• The pumps models are selected as per specified flow rates and delivery head.

• Prior procurement of pump sets, the selected pump sets catalogue and
technical references shall be submitted for the Consulting Engineer’s
approval.

• Submit shop drawings for pumps and associated pipe works detail, including
size and location of R.C. pump plinths.

8.2 Installation of pump

• Construct the R.C pump plinths as per approved shop drawings, showing size
and location.

• Drill holes to suite pump base bolting position. And insert drop-in anchors
into the holes drilled on the R.C. plinth.

• Mount the pumps on the R.C pump plinths, insert a piece of approved anti-
vibration neoplane rubber in between pump base and the plinth, and the
tightened the bolts.

• Measure and connect the associated pipe work c/w valves fittings and
accessories all as per approved shop drawings.

8.3 Starter Panel and Wiring

• Starter panel and wiring and control wiring sensors.

• Starter panel and wiring shall be installed as per approved shop drawings.

• Control wiring sensing cable shall be completed from the storage tank c/w
sensing electrodes and connected to the control panel relay. Signals shall
incorporate low- and high-level alarm, pump start and stop relay signals.

• Suction tank control wiring sensing cable shall incorporate low and high
alarm, pump, restart relay signal and connected to the control panel relay.

EEU ENGINEERING SDN. BHD Page 16


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

8.3 Starter Panel and Wiring

• The pump set are ready for testing and commissioning provided the water,
power supply and all related plumbing works are completed.

Refer to Appendix MOS-CWS-1.3.1 and MOS-CWS-1.3.2 for illustration.

EEU ENGINEERING SDN. BHD Page 17


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

8.3 Starter Panel and Wiring

EEU ENGINEERING SDN. BHD Page 18


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

9.0 INSTALLATION OF HYDRO PNEUMATIC PUMPSETS

9.1 Selection and Submittal

• The pumps models are selected as per specified flow rates and delivery head.

• Prior procurement of pump sets, the selected pump sets catalogue and
technical references shall be submitted for the Consulting Engineer’s
approval. Submit shop drawings for pumps and associated pipe works detail,
including

9.2 Installation of Hydro Pneumatic pump sets

• The hydro pneumatic pump sets shall be factory assembly complete with all
necessary valves, fittings and accessories.

• The whole set of pumps, valves, fittings and accessories including the JKKP
approved pressure vessel are mounted on a common mild steel base and
deliver to site for installation.

(Should due to site constraint, the pump set and accessories shall be
assembled at site)

• Construct the R.C plinth as per approved size and location. Drill holes to
suite base frame bolting position for mounting of the pneumatic pump sets.
Insert drop-in anchors into the holes drilled on the R.C. plinth.

• Mount the pneumatic pump sets on the R.C plinth, insert anti-vibration
neoplane rubber (if necessary) in between the common base and R.C plinth,
and the tightened the bolts.

• Connect up the suction and delivery pipe works.

9.3 Starter panel & wiring

• Starter panel and wiring shall be installed as per approved shop drawings.

• Connect all cable wiring to the pump sets.

• The pump sets are ready for testing and commissioning provided the water,
power supply and all other related plumbing works are completed.

EEU ENGINEERING SDN. BHD Page 19


METHOD STATEMENT
SANITARY & PLUMBING WORKS
THE LIGHT CITY PLOT C – MEZZO

9.0 INSTALLATION OF HYDRO PNEUMATIC PUMPSETS

Refer to Appendix MOS-CWP-2.3.1 for illustration.

EEU ENGINEERING SDN. BHD Page 20

You might also like