REPLACEMENT OF HYDRANT AND FOAM PIPELINE AT

LBT @ LBT1 AND LBT2 BRIDGE CONNECTION AT WHARF, WESTPORTS MALAYSIA SDN. BHD.

MANPOWER & MANHOURS LIST FOR REPLACEMENT OF HYDRANT PIPELINE AT DBT2 WHARF PROJECT

Manpower ManHours
Total
No MANPOWER PLAN Total Manpower daily 1st month 2nd month 3rd month 4th month 5th month 6th month
Weeks
1 Site Engineer 1 8 48 208 208 208 208 208
3 Site Supervisor 1 8 48 208 208 208 208 208
4 Fitter 2 16 96 416 416 416 416 416
5 Welder 1 8 208 208 208 208 208
6 Helper 4 32 832 832 832 832 832

Notes
1. working day is 6 days (Monday to Saturday) 26days per month
2. manpower allocated for this project is 8 people max. Unless got other requirement, will be decide later