Professional Documents
Culture Documents
Introduction
Key Terms
Pre-Commissioning Activities
11 September 2019 2
Key Terms
• The freedom from set of conditions with the potential
for leading to injury to persons, damage to property
SAFETY
or work interruption which affect the attainment of
project objectives.
11 September 2019 3
Key Terms
• An assembly of systems which together form a
distinct operating section, and is a part of the
plant. Unit is a part of the plant which can be
UNIT operated independently due to availability of
surge between units and / or which produces a
distinct end / intermediate product.
• The plant / unit / system is considered
mechanically complete when all the construction
work is completed in accordance with the
MECHANICAL drawings, specifications, guidelines, codes and
COMPLETION regulations; all equipments and machines
erected and aligned; all instruments installed and
pipelines hooked-up; all testing and inspection
activities completed.
• A listing of deviations from piping and
instrumentation diagram and the requirement of
CHECKLIST safety, start-up, operation and maintenance. For
Licensed units responsibility of check listing is
limited to as per P & ID.
11 September 2019 4
Key Terms
11 September 2019 5
WHY DO WE REQUIRE OPERATION SAFETY??
DAMAGE
SAFE
TO
SAFETY LIFE,
LIFE,
CHEMICAL
AS PROPERTY
PROPERTY
AND PHYSICAL
A AND
AND
HAZARDS
BARRIER ECO-SYSTEM
ECO-SYSTEM
11 September 2019 6
WHY DO WE REQUIRE OPERATION SAFETY??
11 September 2019 7
SAN JUANICO DISASTER PEMEX, MEXICO, 1984
BEFORE AFTER
11 September 2019 8
LPG FIRE AT VALERO, MCKEE REFINERY, 2007
11 September 2019 9
JAIPUR FIRE ACCIDENT , 2009
• 11 Dead
• Loss of ~ Rs.280 Crores
11 September 2019 10
EXPLOSION IN VENEZUELA'S LARGEST OIL REFINERY ON
25-08-2012
11 September 2019 11
WHY DO WE REQUIRE OPERATION SAFETY??
When Safety fails (such as: Seveso, Bhopal, Piper Alpha, Toulouse,
Buncefield, Texas City, etc.) Consequences of one incident alone bear the
potential to cause significant problems/losses:
Multiple casualties
Environmental Damage
Legal
11 September 2019 12
CAUSES OF ACCIDENTS IN OIL INDUSTRY
1%
Sabotage & Arson
5%
Design
5%
Natural Hazards
11 %
Process Upsets
12 %
Unknown
22 %
Operator Error 44 %
Mechanical
0 10 20 30 40 50
Source : Harry J. Toups LSU Department of Chemical Engineering ,SACHE 2003 Workshop
11 September 2019 13
FORMAT SYSTEM
The following formats (Format-I, II, III, IV and V) to be used during pre-
commissioning and Commissioning activities.
11 September 2019 14
ACTIVITIES DURING PRE-COMMISSIONING
Pre commissioning activities are activities performed in order to make the
plant / unit / system ready for commissioning after the plant/unit/system are
mechanically completed. These activities include, but not limited to the
following,
11 September 2019 15
ACTIVITIES DURING PRE-COMMISSIONING
11 September 2019 16
ACTIVITIES DURING PRE-COMMISSIONING
• Water run / dry run for process system to check the functioning of
controlling systems
11 September 2019 17
HAZARDS DURING PRE-COMMISSIONING
11 September 2019 18
HAZARDS DURING PRE-COMMISSIONING
STEAM BLOWING OF LINES (LP,HP,VHP)
• Steam will heat up the lines and equipment, which can cause metal burns.
• Steam blowing is also associated with high levels of noise which may
harm the ears.
• Condensate if fall on the person or direct hitting with steam can cause
severe burn injury.
• If steam blowing is going on in closed area like blower shed, compressor
shed etc. ,it can cause poor visibility & in turn can cause slip & fall
incidents.
• Normally superheated steam beam cannot be seen (only noise & heat can
be sensed),it can also cause burn injury.
11 September 2019 19
HAZARDS DURING PRE-COMMISSIONING
STEAMING OUT OF LINES, VESSELS, COLUMNS
• Failure of equipment or fittings / tubes which could lead to eye & hand
injuries and environmental contamination.
CATALYST LOADING
11 September 2019 21
HAZARDOUS MATERIALS
Hazardous materials are substances capable of posing a risk to personal
health and safety. Hazardous materials/substances could generally be
classified as follows:-
Sensitizers (Formaldehyde)
Sensitizers are chemicals which after repeated exposures can cause an allergic-
type reaction.
11 September 2019 22
HAZARDOUS MATERIALS
Irritants (Chlorine, Alkalis, Some solvents)
An irritant is a non-corrosive chemical that causes a reversible inflammatory effect on
living tissue by chemical action on contact.
Asphyxiants (CO,N2,CO2)
Chemicals/gases which can cause suffocation by restricting the uptake of oxygen or
by respiratory paralysis or by diluting/displace oxygen below levels needed by the
body
The best way to protect your health and safety is to know about each of the
chemicals being handled, or worked with, MSDS can be used for the same & must be
displayed wherever practicable
11 September 2019 23
GENERAL SITE SAFETY PROCEDURE
• Barricade with tapes or polypropylene 5mm dia ropes . These ropes shall have
placards indicating NO ENTRY.
• Substation just before energizing will be put under guard with entry register
• Switch yard will be chain link fenced with gate kept under lock and key.
11 September 2019 24
GENERAL SITE SAFETY PROCEDURE
SITE SECURITY
• Controlling vehicles, men and material into site restricted areas inside the plant
premises
• Specific ID cards or Markings for the purpose of entry into restricted area to men
and vehicles / equipments, if required by Commissioning In-charge
• Prevent the presence of any unauthorized ignition source
11 September 2019 25
GENERAL SITE SAFETY PROCEDURE
First Aid boxes are to be maintained as per EIL HSE specifications. Close liasioning
with client First Aid center / local Hospitals for major injury/illness cases to be
maintained. Alertness and quickness shall be maintained all time.
EMERGENCY COMMUNICATION
Banners and signs will be displayed on site to warn or inform people of hazards and
hazard zones, or to prescribe the use of certain personal protective equipment or to
prohibit certain activities. The following are possible but not Limited:-
11 September 2019 27
SPECIFIC SAFETY PROCEDURE
CIVIL WORK:
• All the underground systems like OWS, CBD, SS (Storm Sewer System) shall
be ready & blocked at OSBL to avoid Hydrocarbon backing from commissioned
plant.
• SS system can be hooked up with the outside system prior to start the pre-
commissioning activities like flushing or dewatering pump can also be used for
emptying out the SS pit.
• A plan shall be made for safe hooking up of Underground system with OSBL
after completing the all hot work.
• Fire proofing shall be completed to vessels, piping and structures as per the
drawing
11 September 2019 28
SPECIFIC SAFETY PROCEDURE
CLEANING OF PIPING (UTILITY & PROCESS )
Water Flushing: The flushing is carried out prior to leak testing. All the lines which
are to be air blown followed by water flushing shall be checked by site engineer at
the beginning and during operation.
11 September 2019 29
SPECIFIC SAFETY PROCEDURE
CLEANING OF PIPING (UTILITY & PROCESS )
Air Blowing/Card Board Blasting): In cases where water is not desirable in the
piping system (e.g. instrument /plant air), flushing by pressurized air shall be
carried out.
11 September 2019 30
SPECIFIC SAFETY PROCEDURE
CLEANING OF PIPING (UTILITY & PROCESS )
Steam Blowing/Target Blowing( Steam Lines, Turbines)
11 September 2019 31
SPECIFIC SAFETY PROCEDURE
CLEANING OF PIPING (UTILITY & PROCESS )
Chemical Cleaning, Degreasing, Alkali Boil out Operation (Compressor,
Steam Generators, WHB)
• Valid Work Permit is available at site and followed meticulously
• Specialized & trained Team is deployed for steam blowing operation
• Portion of Pipelines to be chemically cleaned is positively isolated from the rest.
• Incoming/ Outgoing or Inlet / Outlet valves to pipes / equipment are closed and
tagged “DO NOT OPERATE”
• After neutralizing, drain and arrangements for disposing off the cleaning agent
has been identified (as per the client’s instructions.)
• Safety shower eyebath fountain is available / provided/ commissioned.
Alternatively, arrangement s for showering with water, flushing eyes with water
is available at site.
• MSDS is available at job location
• PPE’s like Hand gloves, apron, goggles, helmet are provided to operation team
and are being used.
• Contingency Plan is prepared and informed to all employees.
11 September 2019 32
SPECIFIC SAFETY PROCEDURE
STATIC EQUIPMENT ( I.E.TANK, VESSEL,COLUMN REACTOR, ETC)
Cleaning:
• Gas test shall be done for Oxygen (%), Toxic gases (ppm), Flammable gases
(LEL) prior to entry and same to be monitored on regular intervals.
• Ensure positive blinding/isolation on all pipe line connections
• Communicate work hazards and precautionary measures to concern employees
through daily Tool Box talks, HSE Induction training.
• Deploy trained confined space attendant outside the vessel who shall maintain
the entry & exit register.
• Use of only flameproof portable lamps (24Volts) protected with glass & wire
mess inside confined space
• Provide adequate exhaust / ventilation
• Provide fire extinguisher near vessel. Also wherever required, keep ready fire
water hose as standby arrangement.
• Use of good quality of electrical cables. No joints shall be allowed.
11 September 2019 33
SPECIFIC SAFETY PROCEDURE
STATIC EQUIPMENT ( I.E.TANK, VESSEL,COLUMN REACTOR, ETC)
Catalyst Loading:
11 September 2019 34
SPECIFIC SAFETY PROCEDURE
ROTARY EQUIPMENT (I.E. PUMP, MOTOR, COMPRESSORS & TURBINES.)
Motor:
All the motors shall be tested under no load condition for its smooth functioning. Prior
to that following checks shall be carried out
• Double Earthing
• Secured with foundation.
• Flame proof motor/ Non-flame proof
• Authorized and trained person is on the job.
• Marking on the switches for “ON” & “OFF”, Emergency Shutdown.
• Communication system is in place
• Barricading of area with sign board.
• Covered with guard
11 September 2019 35
SPECIFIC SAFETY PROCEDURE
ROTARY EQUIPMENT (I.E. PUMP, MOTOR, COMPRESSORS & TURBINES.)
Pump:
Following checks shall be performed prior to commission the pump
• Double Earthing
• Coupling Guard is in place
• Marking for direction of rotation
• Free movement of the shaft
• Oil cup provided
• Calibrated pressure gauge at discharge end
• NRV at the suction
• On-off valve / control valve at both the end (Suction & Discharge)
• Provision of Earthing jumpers at pump & pipeline joints
• No leakage from mechanical seal.
11 September 2019 36
HAZARDOUS PROPERTIES OF CHEMICALS
HYDROGEN SULPHIDE(H2S)
• It is a toxic, flammable, and colourless gas. It has an offensive odour similar to that
of rotten eggs.
• Its auto ignition temperature is 260 deg. C and has a wide explosion range (i.e.,
LEL = 4.4 % & UEL = 46 %).
• At the concentrations above 100 ppm, sense of smell is lost.
• Vapour density is 1.2 times more than that of air.
• Hydrogen sulphide reacts violently with metal oxides in the presence of oxygen.
11 September 2019 38
HAZARDOUS PROPERTIES OF CHEMICALS
Symptoms of exposure
a) Very acute
b) Acute poisoning
11 September 2019 40
HAZARDOUS PROPERTIES OF CHEMICALS
HYDROGEN
11 September 2019 41
HAZARDOUS PROPERTIES OF CHEMICALS
LIQUIFIED GASES (LPG)
11 September 2019 42
HAZARDOUS PROPERTIES OF CHEMICALS
NAPHTHA AND OTHER HEAVIER HYDROCARBONS
• The major hazards from these types of hydrocarbons are fire and radiation.
• Any spillage or loss of containment of heavier hydrocarbons may create a highly
flammable pool of liquid around the source of release.
S. No Properties Values
1 Flammable Range (%v/v) 0.8 - 5
2 Auto ignition temperature (°C) 228
3 Heat of combustion (Kcal//Kg) 10,100 10100
4 Normal Boiling point (°C) 130
5 Flash point (°C) -21.7 to 42
11 September 2019 43
HAZARDOUS PROPERTIES OF CHEMICALS
BENZENE (NHT Feed, CCR , Benzene Recovery Unit , Py. Gas HDT, BTX Units)
11 September 2019 44
HAZARDOUS PROPERTIES OF CHEMICALS
TOLUENE (CCR , DFCU,BTX Units)
11 September 2019 45
HAZARDOUS PROPERTIES OF CHEMICALS
AMMONIA (SWS)
The hazard associated with ammonia is both toxic and flammable hazards. Toxic
hazards being more pronounced. Vapors of ammonia may cause severe eye or throat
irritation and permanent injury may result. Contact with the liquid freezes skin and
produces a caustic burn.
11 September 2019 46
SAFETY DURING COMMISSIONING
1. PRE START UP SAFETY AUDIT / REVIEW:
PSSR to be carried out before the plant goes into commissioning stage and all
critical points should be liquidated before feed cut-in. The Pre-startup Safety review
(PSSR) shall be conducted by a review team which will include as a minimum the
following participants
• HSE Engineer
• Process Manager/Engineer
• POSD Engineer
• Representative of owner
• Representative of Licensor – on the basis of contractual agreement
• Any external agency (e.g. third party inspection) if required by owner.
11 September 2019 47
SAFETY DURING COMMISSIONING
PRE STARTUP SAFETY REVIEW CHECKLIST
The review shall check various aspects of the plant. Typical List of Aspects for
PSSR are as follows:
11 September 2019 48
SAFETY DURING COMMISSIONING
• Safety Signs
• Hazardous area classification conformity
• Emergency Shutdown System
• Process Safety Devices,
• Process Safety Information and operating procedure
• Operator Safety Training
• Emergency Planning and response
• Critical tests and checks
• Safe Work Practices
• Maintenance training and mechanical integrity
• Emergency exists availability
• Availability of PPE at site
2.Clear demarcation and signposts shall be made to ensure and demarcate the live
areas of commissioning and the construction areas.
11 September 2019 49
SAFETY DURING COMMISSIONING
3. It shall be ensured that no longer construction work can be carried out in the
commissioning area without Client’s work permit.
4. It shall be ensured that all relevant statutory certificates are obtained and properly
maintained (e. g IBR, OISD, LPA, etc) before start of the commissioning activities.
11 September 2019 50
SAFETY DURING COMMISSIONING
General Safety Instructions for Commissioning
• Smoking is strictly prohibited in the operating plant except in smoking booths.
• To obtain necessary safety permit before start of any repair maintenance work.
• Safety Induction is Mandatory for all.
• Operation of machine / equipment by authorized personnel only.
• Use of PPE to comply with.
• Use of only flameproof portable lamps (24Volts) inside tanks / confined locations.
• Follow proper safety instructions according to the chemical's material safety data
sheet (MSDS) supplied by the manufacturer / supplier.
• Use of camera only on authorization.
• Keep plant area clean and free of junk.
• Entry of automotive vehicles in the process area is restricted.
11 September 2019 51
SAFETY DURING MAINTENANCE
It is strongly recommended that detailed maintenance procedures be written down for
maintenance work on each piece of major equipment or processing system. These
should take into account all possible hazards and should include at least the
following general rules:
11 September 2019 52
SAFETY DURING MAINTENANCE
Preparation for Maintenance
Permits
• No maintenance work should be started until a work permit has been signed and
issued by an authorized person indicating that the area to be worked in has been
properly prepared and tested in accordance with standing maintenance
instructions.
•
• Special permits are issued for each work category (hot works, excavations,
electrical works, vessel entry, etc.), with all special requirements for personnel and
plant protection clearly stated. Such permits should be issued for a specific period,
(e.g. to cover one operating shift), and only renewed after full re-inspection of
working area.
11 September 2019 53
GOOD HOUSEKEEPING
• Paper, wood, waste, and other refuse must be deposited in refuse containers.
• Keep process area, control room and other areas clean and orderly.
• Oil soaked rags and waste may ignite spontaneously; they must, therefore, be
discharged into steel containers specially marked and located for this purpose.
• Access to ladders, stairways, fire escapes, fire extinguishers, steam hoses, water
hoses and hydrants must be free of obstruction.
• Drum, cans and funnels used to dispense lube oil must be cleaned after use and
returned to their proper place.
11 September 2019 54
GOOD HOUSEKEEPING
• Tools, bolts, nuts, lengths of pipe, flanges, etc. must never be left lying on
platforms or walkways.
• Fire fighting equipment is for fire fighting only. Never use it for utility purposes nor
remove it from proper locations.
• Hang hose on rack when not in use. If hose is to be used for extended periods,
string it above walkways to eliminate tripping hazards.
• Never allow any water (rain) accumulation over crossover/ transition or refractory
lined Ducting.
11 September 2019 55
QUERIES
11 September 2019 56
Thank You !
11 September 2019 57