Professional Documents
Culture Documents
Andy Pickles
of
GCG (Asia) Ltd.
Asia 1
Overview of Presentation
Presentation relates to deep excavation for major
infrastructure projects
• Interpretation of instrumentation
Asia 2
Risk in Design of Deep Excavations
• Soil stratigraphy
Asia 3
Uncertainty of Soil Stratigraphy
Variation of Continuity of Sand Layer
Asia 4
Uncertainty in Design Parameters - 1
Deep Excavation in Clay
0.000
0.040
0.080
0.120
0.160
0.200
0.240
0 20 40 60 80 100 120 140 160
4 4
FILL
0 0
-4 -4
-8 Soft CLAY -8
Reduced level (m)_
-16 -16
Bend Mom
40 75 Stiff CLAY Final exc 2800 kNm
-20 -20 5000 kNm
-24 -24
Clayey SAND
-28 -28
Asia 6
Construction Related Uncertainties -1
Performance of Grout Cut-off
CLAY
Asia 7
Construction Related Uncertainties - 2
• Ground settlement on wall installation
Asia 8
Instrumentation to deal with these risks
• All design approaches
Design parameters from previous experience
Determined from instrumentation results
Asia 9
Trigger Levels in Routine Design
• Trigger levels are used as part of the AAA system
Asia 10
Managing Risk and Obtaining Value
Asia 11
The Role of Instrumentation
• Routine design and construction 0% I
N
To verify an already conservative design C
R
• Observational approach
E
A
Use data to continually improve design S
Reduce construction costs I
N
Save construction time G
Asia 12
Typical Scope of Standard Instrumentation
Standard instrument 1 km cut and cover 1 km cut and cover
type with station in with station in
Singapore Hong Kong
Inclinometers in walls 120 50
Piezometers 50 120
(VW and standpipe)
Settlement points 800 500
Extensometers 10 15
Asia 13
Scope of Data Collection
• Typically 1000 to 2000 separate instruments
Asia 14
Typical cost of instrumentation
Cost of instrumentation and 1.5% to 2% of contract value
monitoring
Management cost (engineering 0.5% to 1% of contract value
support, meetings etc.)
Total cost 2% to 3% of contract value
Cost includes
• Instrumentation
• Monitoring teams (instrumentation and survey)
• Engineering support to coordinate work
• Development and maintenance of database
• Daily, weekly and monthly reporting with associated meeting costs
Asia 15
Cost of Instrumentation Routine Design
• Total cost for routine instrumentation of a deep excavation contract
is S$ 5 to 10 million
• Cost is of similar order to the original design costs (i.e. pay as much
to verify as to design)
Asia 16
How to Add Value to Instrumentation
• Adding value is reducing risk and reducing cost
Asia 17
Cost of Adding Value to Instrumentation
• Additional cost for proper interpretation of results and
associated report is S$ 0.1 million
Asia 18
Examples of Excessive Monitoring
Manual Settlement Readings
Jan 00 Nov 01
-5
-15
-120
Asia 19
Examples of Excessive Monitoring
Groundwater Level mPD 3 Manual Piezometer Readings
Tide Gauge
2
Groundwater Level mPD
1 Day Piezometer
0
Asia 21
Examples of Excessive Monitoring
Datalogged Piezometer Readings
Jan 00 Nov 01
-5
-15
2.5
-1.5
Asia 22
Monitoring Frequency, Value and Risk
• My experience approximately 50% of monitoring is
unnecessary.
Asia 23
Proposal for Increasing Value of Instrumentation
• Use of Observational Method can achieve substantial cost savings
and more importantly time savings (e.g. Powderham, Nicolson)
Asia 24
Comment on Interpretation of Instrumentation
The 4 Basic Steps
1. Baseline readings and background trends must be
established (daily rainfall, seasonal rainfall, tide,
temperature etc.)
Asia 25
Establish Baseline Trend
“X”
Movement of
Maximum
Viaduct Structure
Allowable “Y”
Water Alert = 10 mm
Drawdown Action = 15 mm
Is 1m Alarm = 20 mm
40 m
Asia 26
Establish Baseline Trend – 1
Movement of Bypass Pier Head
50
X-dir
Feb 01
40 mm
JunJuly
00 00 Oct 01
-30
20
Y-dir
18 mm
0
Asia 27
Establish Baseline Trend – 1
Movement of Bypass
50
X-dir
40 mm
JunJuly
00 00 July Oct
01 01
-30
20
Y-dir
18 mm
0
Asia 28
Establish Baseline Trend – 2
Variation of Groundwater Level
3
Groundwater Level mPD
Asia 31
Construction Records – Progress Summaries
Asia 32
Construction Records - Photographs
3 March 2002
Asia 33
Correlate Response to Construction Activities
Cause and Effect Plots
Jan 00 -5
Nov 01
Settlement (mm)
-120
50
Inclinometer (mm)
+2.5
Piezometer (mPD)
-1.5
Asia 34
Correlate Response to Construction Activities
and Baseline Trends
Tidal Response
Rainfall Control
+2 Start Dewatering
Groundwater Level mPD
Stop Dewatering
+1
Complete Dwall
-1
• Reduced costs and reduced risk (i.e. added value) can be obtained
by better use of instrumentation
Asia 36
End of Presentation
Thank you
Asia 37