Professional Documents
Culture Documents
05 Fin 502 Investment Decision Rules
05 Fin 502 Investment Decision Rules
T
CFt
NPV I 0
1 RRR
t
t 1
NPV 0 TAKE
Clear Timing
Decision Differences
Introduction to Financial Valuation 3
XYZ Corp: NPV Example
– $110,000
$14,000 $14,000 $14,000 $14,000
$100,000
é æ öù
1 1 1
NPV = -$110, 000 + $14, 000 ê çç1- ÷ ú + $100, 000
êë 0.1 è (1+ 0.1)10 ÷øúû (1+ 0.1)
10
= $14, 578
PV
Profitability Index (PI ) =
I0
Take project if PI > 1. Why?
PV
>1 Þ PV > I 0 Þ
I0
PV - I 0 > 0 Þ
NPV > 0
Introduction to Financial Valuation 5
PI Example
220 110
PI A 1.10 PI B 1.10
200 100
220
PI A 1.07
205
Introduction to Financial Valuation 6
Internal Rate of Return (IRR)
T
CFt
NPV = -I 0 + å =0
(1+ IRR)
t
t=1
$90,000
NPV
$60,000
$30,000
$0
14,578
0 0.04 0.08 0.12 0.16
-$30,000
RRR
In general, the IRR rule works for a stand-alone project if all of the project’s
negative cash flows precede its positive cash flows.
The IRR rule may disagree with the NPV rule and thus be incorrect. Situations
where the IRR rule and NPV rule may be in conflict:
o Scale
o Unconventional cash flows
o Multiple IRRs
o Nonexistent IRR
RRR = 10% NPV(A) > NPV(B) and when RRR = 20% NPV(A) < NPV(B)
IRR(A) < IRR(B) projects have different scales, cannot compare IRR directly
Incremental IRR = IRR of the difference in cash flows between A and B, IRR
of switching from B to A
Incremental IRR = 15.66% > 10% accept A (its larger scale is sufficient to
make up for lower IRR).
$6,000
$4,000
Incremental IRR = 15.66%
$3,000
NPV
$2,000
$1,000
$0
0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0%
($1,000)
($2,000)
($3,000)
RRR
Introduction to Financial Valuation 12
Incremental IRR
A B C D E
RRR 10% 10% 11% 10% 10%
NPV $842,857 $1,028,571 $781,818 $9,091 $28,531
IRR 29.67% 28.00% 32.50% 15.00% 15.00%
Investment (C0) -300,000 -400,000 -400,000 -200,000 -200,000
C1 80,000 100,000 130,000 230,000 0
C2 perpetuity perpetuity perpetuity 0 0
C3 0 304,175
g 3% 3% 0% 0% 0%
Problem of scale.
Problem of cash flow timing.
Problem of risk.
Consider a mining project with the following cash flows. The initial outlay
is C0 = – $60, year 1 CF is C1 = + $155. In year 2, there are additional costs
due to environmentalist lobby groups, C2 = – $100. IRR= ?
0.10
-0.05
-0.10
-0.15
-0.20
-0.25
RRR
Multiple IRRs! For RRR < 25% and RRR >33.3%, the NPV is negative
and the project should be rejected
Introduction to Financial Valuation 15
IRR and Unconventional Cash Flows (4)
0 1 2
Consider the following cash flows
+ 1,000 – 3,000 2,500
3, 000 2, 500
NPV at 10%: 338, 84 = 1, 000 - +
1.1 1.12
This project has no IRR!
450
400
350
NPV
300
250
200
150
100
50 RRR
0
5%
115%
80%
100%
105%
110%
120%
125%
130%
135%
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
60%
65%
70%
75%
85%
90%
95%
IRR Rule. Selecting the project with the highest IRR may lead to mistakes. If
certain instances occur, projects IRRs cannot be meaningfully compared.
Scale problems (similar to the problem with PI). Would you rather have 20%
on $5 or 10% on $20?
If a project’s size is doubled, its NPV will double. Not the case with IRR .
IRR rule cannot be used to compare projects of different scales.
Timing Problems: when projects have the same scale, the IRR may lead you
to rank them incorrectly due to difference in the timing of the cash flows.
The IRR that is attractive for a safe project need not be attractive for a much
riskier project.
Introduction to Financial Valuation 17
Projects With Different Lives
é 1 æ 1 öù
Machine A; PV = -10, 000 - 3, 000 ´ ê ç1- 3 ÷ú
= -17, 460.55
ë 0.10 è 1.10 øû
é 1 æ 1 öù
Machine B; PV = -9, 000 - 4, 000 ´ ê ç1- 5 ÷ú
= -24,163.47
ë 0.10 è 1.10 øû
Projects PV I0 NPV = PI =
($ thousands) ($ thousands) PV − I0 PV/I0
A 144 90 54 1.6
B 70 50 20 1.4
C 100 50 50 2