IT SMP Roadmap
IT SMP Roadmap
Cindi Locker
IT Service Mgmt. Program Mgr.
Progressive Insurance
Greater Cleveland LIG: 06/21/2007
1
Presentation Objective
Provide practical, descriptive guidance on an
approach to:
Empower internal, process owners, managers
and process experts to develop and obtain
approval to a implement an ITSM Roadmap
recommending
incremental (quick win / quick hit) change across all
(11) ITIL disciplines concurrently
2
Agenda
Roles / Responsibilities & Rules
Management Framework
Guiding Principles
Assessment
Goal
Method
Timeline of Accomplishments
Approach
Results
Levels of Process Maturity
Opportunities
Implementation
Goal
Recommendation
Phase 1 Deliverables
Where Are We Now 3
Roles & Responsibilities
Management Framework
Training
4
Guiding Principles
ITIL: We will use ITIL as a guide as we develop our Service Management Program. Our goal is
to follow their recommendations. We will try to keep deviations to a minimum.
Pace: We will manage culture change, increasing and changing demands of the business, and
maintain momentum through the execution of quick win, quick hit projects, at a steady pace
meeting committed dates.
Resources: We will release and empower the necessary and appropriate existing staff on a full
or part time basis to design new processes and procedures in accordance with the Roadmap.
Organizational Independence: We see our roles as providing the guide rails in which
organizations can move independently yet still honor the concept of being virtually the same.
Simplification: We will leverage industry best practices and solutions where possible. (Never
start with a blank page, avoid the trap of thinking we have unique needs.) We will look to retire
existing processes were applicable to meet an overall goal of administrative simplification.
5
Guiding Principles – Continued
Data (Integrated & Quality): We will promote the correlation of data across Service
Management modules/disciplines. We will build systems and processes that insure data quality.
Systems of Record: We will enforce no duplication or creation of redundant data and recognize
one source of information for official reporting. If there are deficiencies in that source, we will work
to correct the problem.
Team Work: We hold ourselves accountable to widespread sharing of all information, best
practices, and opportunities in support of our common goal of continuous improvement.
Enterprise Solutions: We will invent and build IT wide solutions and responsibly communicate
those decisions.
Temporary Solutions: Temporary solutions are acceptable. However, all or portions of the
temporary solution may need to be redone when an enterprise approach is implemented through
the Service Management Program. Although the temporary solution is not preferred, it would
solidify the areas requirements as they would have actual experience with their approach.
6
Assessment
Goal
An Objective ‘Look in the Mirror’
Factual Audit / Investigation
Strengths (What We Do)
Realistic Conclusion
Current Level of Process Maturity
7
Assessment
Method
Individual ITSM
• 11 ITSM Processes Process
Assessments
• 29 People
11 Teams
10 Leads
3 – 7 Per Team
• ‘Standard’ Assessment Guides
Questions Evaluating Existence of IT SMP Roadmap
1. 1.0 Prerequisites of Sequential Tasks
2. 1.5 Management Intent
3. 2.0 Process Maturity Integrate and
Determine
4. 2.5 Internal Integration Sequence Summarize and
5. 3.0 Process Output of Report Results
Assessment
6. 3.5 Process Quality Results
7. 4.0 Management Information
8. 4.5 External Integration
9. 5.0 Customer Interface
• ‘Standard’ Assessment Report Template
8
Assessment
Timeline of Accomplishments
53 Calendar Days / 37 work days
Review
Glossary of Terms
Service Management / Reference / ITIL Glossary
Read
Applicable ITIL Process Book (Service Support or Service Delivery)
IT Service Management an Introduction Based on ITIL
ITIL Planning to Implement Service Management
Chapter 6, Section 6.1 – Critical Success Factors and Key Performance
Indicators
Understand
Terminology
Relationships & Dependencies Other Service Management Processes
10
Assessment
Approach
Round 1: Broaden ITIL Knowledge/Draft Input (Cont)
Deliverable
Assessment Drafts / Each Team Member 11
Assessment
Approach
Round 2: Integrate Input / Author Report
Team Leads
1st Schedule Meeting(s) With All Team Members Present
Integrate Input
Utilize Standard Assessment Guide
2nd Author Assessment Report
Utilize Standard Report Format
3rd Schedule Meeting(s) With All Team Members Present
ID What Needs to Improve
Set a Time Limit for Debate / Lead Makes the Call
Group Opportunities Based on Dependencies
Prioritize Groups of Opportunities for Improvement (Project) Initiatives
Create ‘Process’ Roadmap
Deliverables
Assessment Report
Individual Process Roadmap 12
Assessment
Approach
Round 2: Assessment Report (example)
Process Overview
Findings
Level 1.0:
Strengths [What We Do]
Opportunities [What We Can Do Better]
Level 1.5: Management Intent
Level 2.0: Process Capability
Level 2.5: Internal Integration
Level 3.0: Process Output Products
Level 3.5: Process Quality
Level 4.0: Management Reporting
Level 4.5: External Integration
Level 5.0: Customer Interface
Summary
Current Overall Maturity Level & #
What Needs to Be Improved
What Could be Improved
13
Assessment
Approach
Round 3: Develop Service Delivery & Support Roadmaps
Deliverable
(1) Service Delivery Roadmap
(1) Service Support Roadmap
14
Assessment
Approach
Round 4: Develop IT SMP Roadmap
Integrate
Service Delivery & Service Support Roadmaps
Deliverable
IT SMP Roadmap
15
Assessment
Approach
Round 5: Approve IT SMP Roadmap
Modify As Needed
Based on Business Priorities & Resource Availability
Approve
Socialize Throughout IT
Deliverable
Approved IT SMP Roadmap
16
Results
Levels of Process Maturity
ITSM Process Maturity – Based on 10/2005 Assessment
Each level of maturity considers the following elements: Vision & Steering, Process Initial: Process recognition, limited
People, Technology & Culture. management activity; org places
[Diagram source: itSMF Planning to Implement Service Management ‘a companion to the IT Infrastructure Library pocket guide] no importance, resources or focus.
(Ad hoc or chaotic)
17
Time
Results
Opportunities
Opportunities by Criticality
High – High – Medium Low Totals
Main Sub*
SERVICE DELIVERY
Availability Management 16 6 24 12 52
Capacity Management 9 2 14 4 27
Financial Management for IT Services 5 3 18 1 24
IT Service Continuity Management 12 7 16 5 33
Service Level Management 15 5 34 6 55
Sub Total 57 23 106 28
SERVICE SUPPORT
Change Management 14 3 26 24 64
Configuration Management 8 2 15 0 23
Incident Management 26 2 23 13 62
Problem Management 12 10 20 19 51
Release Management 5 2 10 12 27
Service Desk 13 0 37 8 58
Sub Total 78 19 131 76
TOTAL (*Sub' Opportunities excluded from totals) 135 42 237 104 476
18
Implementation
Goal
Introduce Change in Phases.
Quick Wins / Quick Hits
Provide Immediate Benefits
Tactical Efforts With Specific Goals
Completed in Short Intervals (3-6 mths)
Phase 1
Demonstrate Management Commitment
Establish Process Ownership
Build ITSM Foundation / Prerequisites
Lay the Groundwork for Integration
Introduce Aspects of Common Process
Establish End State Visions
Accomplish Collaborative Approach
Begin Transformation of IT
19
Implementation
Recommendation
Focus on all 11 ITSM processes concurrently
High Criticality Opportunities Only
(3) 6-Month Phases
Tactical Efforts, Specific Goals
Short Term Implementation Projects Within Each ITSM Process
Availability Management
Establish standards / guidelines for availability requirements.
Capacity Management
Establish Capacity Management Process Plans for Desktop &
Servers.
Develop a performance management process for Telecom,
Server & Client Support Groups.
Financial Management
Define criteria & performance targets for Accounting, Budgeting &
Charging measurements & improvements.
Develop a continuous Vs deadline driven budgetary process. 21
Implementation
Phase 1 Deliverables – Service Delivery
23
Implementation
Phase 1 Deliverables – Service Support
Change Management
Improve prioritization & categorization of business &
technical requests and impact – tied to the business.
Redefine Change Advisory Board (CAB) membership,
roles and responsibilities.
Conduct CAB meetings that include groups interested in
application and business areas.
Redefine scope of request for change (change record
release management).
24
Implementation
Phase 1 Deliverables – Service Support
Configuration Management
Define Configuration Management (CM) requirements.
Inventory data sources and tools.
Plan to resolve CM issues related to platforms, applications and process
owners.
Incident Management
Rollout and ensure compliance to the Virtual Incident Management
(VIM) and Knowledge Management (KM) processes across IT.
Provide access to KM for Service Desk.
Develop a data mart and core set of IT management reports.
Appoint ‘new’ Process Owner and Analyst positions to ensure continual
improvement, as well as, management of VIM Process training.
Establish Operating Level Agreement (OLAs) between Service Desk and
Technicians for escalation.
25
Implementation
Phase 1 Deliverables – Service Support
Problem Management
Develop a central repository and standards for classification for root
cause and recording data.
Define IT Management reporting requirements.
Implement standard enterprise-wide Problem Management activities.
Release Management
Define a repository and templates for enterprise-wide standards and
policies.
Implement a formal Software Change Management (SCM) Process.
Service Desk
Develop IT Management reporting focused on reducing call volume.
Establish formal IT Service Support process for new applications.
26
Where Are We Now
Resources Redirected to Non-Discretionary Tasks Due To
Major Compliance Initiatives
SOX – Sarbanes Oxley
PCI – Payment Card Industry
Opening of our 2nd / Remote Data Center
Opening and Migration of a New Print / Mail Facility
27