You are on page 1of 86

1 of 85 8.

1 Forms of project organization

Why a project organization?


1because the traditional form
1. Has no means of integrating different departments
2. Does not facilitate effective communication, coordination and
control of several departments
Alternative means of project organization
1. Line and staff organization
2. Divisional organization
3. Matrix organization

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
2 of 85 8.1 Forms of project organization

1. Line and staff organization


2 Project activities are done by people in each functional
departments
 A project coordinator is assigned to facilitate coordination of
line management in functional departments
 The coordinator is devoid of authority and responsibility of line
management
 he collects project-information, shares information, renders
advice, and provide assistance

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
3 of 85 8.1 Forms of project organization

2. Divisional organization
3 a separate division with its own functional departments is set
up to implement a project.
 The project manager has full line authority and total formal
control over the project.
 Facilitates planning and control, brings about better integration
of efforts, and strengthens commitment of project personnel.
 But it may entail inefficient use of resources-unnecessary
duplication of specialists

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
4 of 85 8.1 Forms of project organization

3. Matrix organization
4 Designed to achieve efficient use of resources and effective
realization of project objectives
 Project personnel are responsible to their functional supervisor
and project manager (dual responsibility)
 Violates the unity of command rule
 Implies greater organizational complexity and creates inherent
conflicts

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
5 of 85 8.2 Project Planning

Why a plan?
5 Used as a basis for organizing project activities and allocating
responsibilities to individuals
 A means of communication and coordination between all those
involved in the project
 Encourages people to look ahead
 Instills a sense of urgency and time consciousness
 Establishes the basis for monitoring and control

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
6 of 85 8.2 Project Planning

What do we plan?
6 The work
 Manpower and organization
 Financial resources
 Information system
Project objectives
Must help in answering the following questions
 What are the technical and performance objectives?
 What are the time and cost goals?
 To what extent should project work be sub-contracted? How many
contractors? The
Project Financing terms
and of contract?
Management-Project
Project Financing and Management-Project Management Thursday, January 23, 2020
Management
7 of 85 8.2 Project Planning

Tools of planning
7Bar chart(Ghant chart)

 A pictorial device in which activities are represented by a


horizontal bars on the time axis.
 Manpower requirement can be shown a number on the bar
Advantages Disadvantages
 simple to understand  cannot show interrelations
among activities in complex
projects
 used for manpower planning  physical limit to the chart
 used to show project progress  cannot easily cope with
Project Financing and Management-Project frequent changes/updating
Project Financing and Management-Project Management Thursday, January 23, 2020
Management
8 of 85 8.2 Project Planning

Tools of planning
8Bar chart

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
9 of 85 8.2 Project Planning

Tools of planning
9Bar chart

Advantages Disadvantages
 simple to understand  cannot show interrelations
among activities in complex
projects
 used for manpower planning  physical limit to the chart
 used to show project progress  cannot easily cope with
frequent changes/updating

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
10 of 85 8.2 Project Planning

Tools of planning
10
Network Techniques
 Activities, events and interrelationships are represented by a
network diagram
Advantages Disadvantages
 effectively handles  more complicated than bar charts
interrelationships
 identifies critical activities  do not define operational schedule
 can handle complex projects
 can be easily computerized
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
11 of 85 8.3 Project Control

Why control?
 ensures regular monitoring of performance
11

 motivates project personnel to strive for achieving project


objectives
Approaches
1. Variance analysis approach
2. Performance analysis

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
12 of 85 8.3 Project Control

1. Variance analysis approach


 Involves comparison of actual cost with budgeted cost
12
Example
Activity A Activity B
Budgeted cost in the period Br 95,000 15,000
Cumulative budget to date 450,000 155,000
Actual cost in the period 105,000 12,000
Cumulative actual cost to date 440,000 160,000
Variance for the period (10,000) 3,000
Cumulative variance to date 10,000 (5,000)
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
13 of 85 8.3 Project Control

1. Variance analysis approach


Limitations
13
 Is a backward looking
 Does not use data effectively to provide integrated control. It
doesn’t show value of work done.

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
14 of 85 8.3 Project Control

2. Performance analysis approach


Involves answering the following questions:
14
 Is the project on schedule, ahead of schedule or behind
schedule? If there is variation, where did it occur, why did it
occur, who is responsible, and what would be its implications?
 Has the cost of the project as per the budget, less than the
budget or more than the budget? If there is variation, where
did it occur, why did it occur, who is responsible, and what
would be its implications?
 What is the trend in performance? What would be the likely final
cost and completion date of the project and its components?
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
15 of 85 8.3 Project Control

2. Performance analysis approach


Method
15 of analysis
TERMS
 Budgeted Cost for Work Scheduled(BCWS). This includes budgets
for
 all work packages scheduled to be completed
 portion of work in progress scheduled to be completed
 Overheads for the period
 Budgeted Cost for Work Performed (BCWP). It comprises budget
for work completed, for work-in progress, and overhead budget.
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
16 of 85 8.3 Project Control

Method of analysis…

16 Actual Cost of Work Performed(ACWP)
 Budgeted Cost for Total Work (BCTW). Total budgeted cost for the
entire project
 Additional Cost for Completion (ACC)
Given the above terms performance is evaluated as follows:
Cost variance= BCWP-ACWP
Schedule variance in cost terms = BCWP-BCWS
Cost performance index= BCWP/ACWP
Schedule performance index= BCWP/BCWS
Estimated cost performance index = BCTW/(ACWP+ACC)
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
17 of 85 8.3 Project Control

Performance analysis approach(Example)


17
Consider the following project cost information

Budgeted Cost for Work Scheduled(BCWS) Br 4.5mill


Budgeted Cost for Work Performed (BCWP) 3.9mill
Actual Cost of Work Performed(ACWP) 4.1mill
Budgeted Cost for Total Work (BCTW) 8mill
Additional Cost for Completion (ACC) 4.4mill

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
18 of 85 8.3 Project Control

Performance analysis approach(Example)


Cost variance = Br 3.9mill – 4.1 mill
18
= -Br 0.2mill
Schedule variance = Br 3.9mill – 4.5mill
=-Br 0.6mill
Cost performance index = Br 3.9mill/Br 4.1mill
= 0.95
Schedule performance index =Br 3.9mill/Br 4.5mill
= 0.87
Estimates cost performance index = Br 8mill/(4.1mill+4.4mill)
= 0.94
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
19 of 85 8.4 Human aspects of Project Management

 the following aspects need to be carefully


19
handled to succeed in human relations:
 Authority
 Orientation
 Motivation
 Group functioning

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
20 of 85 8.4 Human aspects of Project Management

Authority
20
to exercise leadership and influence, a PM has to
explain logic and rationale for activities rather
than giving orders
 entertain the views and suggestions by others
 avoid unilateral imposition of decisions
 eschew dogmatic posture

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
21 of 85 8.4 Human aspects of Project Management

Authority…
21
His authority stems from his
 ability to develop a rapport with project personnel
 skill in resolving conflicts
 professional reputation and
 skills in communication and persuasion

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
22 of 85 8.4 Human aspects of Project Management

Orientation
 Strengthen managerial orientation of the
22

project rather than an engineering orientation.


Motivation
 The project manager should understand that
 humans are motivated by varieties of needs
 pressure is counterproductive
 people are motivated more when the goals are
Project Financing and but
challenging Management-Project
attainable Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
23 of 85 8.4 Human aspects of Project Management

Motivation…
 expectation of reward rather than fear of
23

punishment has greater impact on behavior

Group functioning
 a project may comprise a vertical, horizontal,
or mixed groups

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
24 of 85 8.4 Human aspects of Project Management

Group functioning…
 an effective group can be established through
24

the following steps:


 development of mutual trust
 Diminution of defensive behavior
 openness and candor in communication
 cooperation and supportive behavior
 resolution of differences by mutual
Project Financing and Management-Project
negotiation Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
25 of 85 8.5 Network scheduling

 A network diagram is used that shows activities


25

and events of the project and their logical


relationship
Example: ECSU uses the following activities as part of
applicant selection and admission process
1. Send letter of notification to regions to select
candidates
2. Set entrance exam
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
26 of 85 8.5 Network scheduling

Example…
26
3. Administer entrance exam
4. Announce the result
5. Registration
3
4
5
1

2
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
27 of 85 8.5 Network scheduling

Rules for Network Construction


1. Each activity has a preceding and succeeding event.
27
Activities are numerically denoted by pair of preceding
and succeeding events.
Example: Send notification (1-3)
Administer Exam (2-3)
2. Each event has a distinct number
3. No loops
4. No more than one activity can have the same
preceding and succeeding event
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
28 of 85 8.5 Network scheduling

No looping!

X
28

1 2

3 Dummy
Activity

1 2
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
29 of 85 8.5 Network scheduling

Time estimation
29
 Three times values are obtained
 Optimistic time-time if no complications arise
 Most likely time-takes into account normal
delays
 Pessimistic time-time required if unusual
complications arise
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
30 of 85 8.5 Network scheduling

Average Time
30

te = (to + 4tm + tp)/6


where
te = weighted arithmetic average time
to = optimistic time
tm = most likely time
tp = pessimistic time
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
31 of 85 8.5 Network scheduling

Example: Project A
31 2 5 8

3 7
1

4 6

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
32 of 85 8.5 Network scheduling

32
Event to tm tp Average
1-2 5 12 17 12
1-3 8 10 13 10
1-4 9 11 12 11
2-3 5 8 9 8
2-5 9 11 13 11
4-6 14 18 22 18
3-7 21 25 30 25
6-7 8 13 17 13
5-8 14 17 21 17
7-8 6 9 12 9
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
33 of 85 8.5 Network scheduling

Example: Project A
17
33 2 5 8
11

10 3 7
1
25
13
4 18 6

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
34 of 85 8.5 Network scheduling

Determining the Critical Path


34
STEPS
1. Calculate the Earliest Occurrence Time (EOT)
for each event
 Time at which the event can be completed at
the earliest. It is computed beginning from
event o and moving forward.

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
35 of 85 8.5 Network scheduling

EOT for activities in Project A


17
35 2 5 8
11

10 3 7
1
25
13
4 18 6

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
36 of 85 8.5 Network scheduling

Determining the Critical Path


36
STEPS
2. Calculate Latest occurrence time(LOT) for
each event
 the latest allowable time by which an event
can occur , given the time allowed for
completion of the project. Project
completion time is EOT of the last event.
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
37 of 85 8.5 Network scheduling

LOT for activities in Project A


17
37 12 2 5 8
11
37 54

10 3 7
1
25
20 45
0
13
4 18 6

14
Project Financing and Management-Project 32
Project Financing and Management-Project Management Thursday, January 23, 2020
Management
38 of 85 8.5 Network scheduling

Determining the Critical Path


38
STEPS
3. Calculate slack for each event
Slack = LOT - EOT

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
39 of 85 8.5 Network scheduling

EOT for activities in Project A


17
39 2 5 8
12 11
37 54

10 3 7
1
25
20 45
0
13
4 18 6

14
Project Financing and Management-Project 32
Project Financing and Management-Project Management Thursday, January 23, 2020
Management
40 of 85 8.5 Network scheduling

Slack
Event LOT EOT (LOT-EOT)
40
1 0 0 0
2 12 12 0
3 20 20 0
4 14 11 3
5 37 23 14
6 32 29 3

7 45 45 0
8 54 54 0
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
41 of 85 8.5 Network scheduling

Critical Path
17
41 2 5 8
12 11
37 54

10 3 7
1
25
20 45
0
13
4 18 6

14
Project Financing and Management-Project 32
Project Financing and Management-Project Management Thursday, January 23, 2020
Management
42 of 85 8.5 Network scheduling

PERT(Program Evaluation and review technique)


model
42
 considers uncertainty in project completion time
 uses the standard deviation as a measure of
variability
STEPS
1. determine SD of the duration of each activity in
the critical path
2. determine SD of total duration of the critical path
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
43 of 85 8.5 Network scheduling

SD of the duration of each activity is determined as


43
follows
σ = (tp-to)/6
Variance is obtained by squaring σ
SD of total duration of the critical path
sum of variance 1/2
of activity
= duration on the
critical path
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
44 of 85 8.5 Network scheduling

2
44 Event to tp σ σ
1-2 5 17 2 4
2-3 5 9 0.67 0.44
3-7 21 30 1.5 2.25
7-8 6 12 1 1
Sum 7.69

Standard deviation (critical path duration)


= 2.77 (SQRT of 7.69)
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
45 of 85 8.5 Network scheduling

Critical path duration (mean) is 54 days and


45
standard deviation is 2.77.
The critical path duration is assumed to
approximate a normal distribution, and hence
the probability that
Mean + 1SD is 68.2%
Mean + 2SD is 95.4%
Mean + 3SD is 99.8%
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
46 of 85 8.5 Network scheduling

Probability of completion by a specific date(D)


46
is determined by first calculating value of Z.
Z= (D-T)/σ
and obtaining cumulative probability upto Z by
looking at the probability distribution of standard
normal variable.

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
47 of 85 8.5 Network scheduling

47

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
48 of 85 8.5 Network scheduling

CPM (Critical Path Method)


 developed for projects that are relatively less-
48

risky.
 focuses on variations in activity times as a result
of resource assignment.
 the variations are planned and are within the
control of the project manager
 it aims at finding a schedule that minimizes total
cost
Project Financing and Management-Project
Project Financing and Management-Project Management Thursday, January 23, 2020
Management
49 of 85 8.5 Network scheduling

CPM…
49
Assumptions
1. Costs associated with the project are divided into
two categories as Direct costs and Indirect costs.
2. Activities can be expedited by crashing using
more resources
3. Crashing reduces time but increases direct costs
4. Indirect costs increase with project duration.
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
50 of 85 8.5 Network scheduling

STEPS
50
1. Obtain the critical path in the normal network and
determine project duration and direct cost
2. Examine cost-time slope of activities on the critical
path and crash activities with the smallest slope
3. Construct a new critical path, and determine
project duration and cost
4. Repeat steps (2) and (3) till activities on the critical
path are
Project crashed
Financing and Management-Project
Project Financing and Management-Project Management Thursday, January 23, 2020
Management
51 of 85 8.5 Network scheduling

Illustration: Consider the following information on a


project Time(weeks) Cost
51
Activity Normal Crash Normal Crash
1-2 5 2 Br 6,000 Br 9,000
2-4 6 3 7,000 10,000
1-3 4 2 1,000 2,000
3-4 7 4 4,000 8,000
4-7 9 5 6,000 9,200
3-5 12 3 16,000 19,600
4-6 10 6 15,000 18,000
6-7 7 4 4,000 4,900
7-9 6 4 3,000 4,200
5-9 12 7 4,000 8,500
Assume
Project theand
Financing indirect costs of the project are
Management-Project
Project Financing and Management-Project Management
Br 1,000 a week.
Thursday, January 23, 2020
Management
52 of 85 8.5 Network scheduling

Illustration…
Time Cost Cost to
52
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
1-3 4 2 1,000 2,000 500
3-4 7 4 4,000 8,000 1,333
4-7 9 5 6,000 9,200 800
3-5 12 3 16,000 19,600 400
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
5-9 12 7 4,000 8,500 900
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
53 of 85 8.5 Network scheduling

Illustration
53
6 9 26
2
4 7
5 6 34
10
1
6 9 34
4 3
5 12 28
12
26
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
54 of 85 8.5 Network scheduling

Illustration…
Time Cost Cost to
54
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
1-3 4 2 1,000 2,000 500
3-4 7 4 4,000 8,000 1,333
4-7 9 5 6,000 9,200 800
3-5 12 3 16,000 19,600 400
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
5-9 12 7 4,000 8,500 900
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
55 of 85 8.5 Network scheduling

Illustration…
55
CP 1 Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 34weeks Br 35,000

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
56 of 85 8.5 Network scheduling

Illustration…
CP2 Time Cost Cost to
56
Activity Normal Crash Normal Crash expedite
1-3 4 2 1,000 2,000 500
3-4 7 4 4,000 8,000 1,333
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 34weeks Br 27,000

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
57 of 85 8.5 Network scheduling

Illustration
57
6 9 26
2
4 7
5 4 6 31
10
1
6 9 31
4 3
5 12 28
12
26
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
58 of 85 8.5 Network scheduling

Illustration…
58
CP 1 Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 31weeks Br 35,900

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
59 of 85 8.5 Network scheduling

Illustration…
CP2 Time Cost Cost to
59
Activity Normal Crash Normal Crash expedite
1-3 4 2 1,000 2,000 500
3-4 7 4 4,000 8,000 1,333
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 31weeks Br 27,900

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
60 of 85 8.5 Network scheduling

Illustration
60
6 9 26
2
4 7
5 4 6 31
10
1
6 9 29
2 3
5 12 26
12
24
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
61 of 85 8.5 Network scheduling

Illustration…
61
CP 1 Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 31weeks Br 35,900

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
62 of 85 8.5 Network scheduling

Illustration…
Cost and duration after crashing Activity 7-9
62
CP 1 Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 29weeks Br 37,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
63 of 85 8.5 Network scheduling

Illustration
63
6 9 24
2
4 7
5 4 4 29
10
1
6 9 27
2 3
5 12 26
12
22
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
64 of 85 8.5 Network scheduling

Illustration…
Cost and duration after crashing Activity 7-9
64
CP 1 Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 29weeks Br 37,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
65 of 85 8.5 Network scheduling

Illustration…
Cost and duration after crashing Activity 7-9
65
CP 1 Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 25weeks Br 40,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
66 of 85 8.5 Network scheduling

Illustration
66
6 9 24
2
4 7
5 4 4 25
6
1
6 9 23
2 3
5 12 26
12
22
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
67 of 85 8.5 Network scheduling

Illustration…
CP2 Time Cost Cost to
67
Activity Normal Crash Normal Crash expedite
1-3 4 2 1,000 2,000 500
3-5 12 3 16,000 19,600 400
5-9 12 7 4,000 8,500 900
Total 26 weeks Br 22,000

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
68 of 85 8.5 Network scheduling

Illustration…
CP2 Time Cost Cost to
68
Activity Normal Crash Normal Crash expedite
1-3 4 2 1,000 2,000 500
3-5 12 3 16,000 19,600 400
5-9 12 7 4,000 8,500 900
Total 17 weeks Br 25,600

Cost and duration after crashing Activity 3-5

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
69 of 85 8.5 Network scheduling

Illustration
69
6 9 24
2
4 7
5 4 4 25
6
1
6 9 23
2 3
5 12 17
3
22
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
70 of 85 8.5 Network scheduling

Illustration…
70
Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 25weeks Br 40,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
71 of 85 8.5 Network scheduling

Illustration…
Cost and duration after crashing Activity 2-4
71
CP 1 Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 22weeks Br 43,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
72 of 85 8.5 Network scheduling

Illustration
72
3 9 21
2
4 7
5 4 4 22
6
1
6 9 23
2 3
5 12 17
3
22
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
73 of 85 8.5 Network scheduling

Illustration…
73
Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-3 4 2 1,000 2,000 500
3-4 7 4 4,000 8,000 1,333
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 23weeks Br 33,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
74 of 85 8.5 Network scheduling

Illustration…
Cost and duration after crashing Activity 3-4
74
Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-3 4 2 1,000 2,000 500
3-4 7 4 4,000 8,000 1,333
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 20 weeks Br 37,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
75 of 85 8.5 Network scheduling

Illustration
75
3 9 21
2
4 7
5 4 4 22
6
1
6 9 20
2 3
5 12 17
3
19
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
76 of 85 8.5 Network scheduling

Illustration…
76
Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 22weeks Br 40,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
77 of 85 8.5 Network scheduling

Illustration…
Cost and duration after crashing Activity 1-2
77
CP 1 Time Cost Cost to
Activity Normal Crash Normal Crash expedite
1-2 5 2 Br 6,000 Br 9,000 Br 1,000
2-4 6 3 7,000 10,000 1,000
4-6 10 6 15,000 18,000 750
6-7 7 4 4,000 4,900 300
7-9 6 4 3,000 4,200 600
Total 19 weeks Br 46,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
78 of 85 8.5 Network scheduling

Illustration
78
3 9 18
2
4 7
2 4 4 19
6
1
6 9 20
2 3
5 12 17
3
19
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
79 of 85 8.5 Network scheduling

Illustration…
79 Project cost and duration
Time Direct Cost Indirect
Activity (Crash) (Crash) cost Total cost
1-3 2 2,000
3-4 4 8,000 (20weeks x
4-6 6 18,000 Br 1,000
6-7 4 4,900 per week)
7-9 4 4,200
Total 20 weeks Br 37,100 Br 20,000 Br 57,100

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
80 of 85 8.6 Project closure

Administrative closure
80
 the process of documenting the results of a
project work to ensure that all of the
requirements and specifications have been met
 administrative closure should be performed at
completion of each phase of a project

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
81 of 85 8.6 Project closure

Issues to be addressed include:


81
 collection and archiving of all project
documents that includes final cost and schedule
data.
 Updating records and product specifications to
reflect what was actually achieved
Revising employee records to reflect newly
developed skills and anticipate future training
needs
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
82 of 85 8.6 Project closure

Issues to be addressed…
82
 Preparation of a final project report that summarizes
history of the project.

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
83 of 85 8.6 Project closure

Final lessons-learned review


83
 it includes evaluation of the strengths and weaknesses
of a project. Questions like ”what did we do right and
what did we do wrong? are answered.
 data from lessons- learned reviews should be viewed
as one of the most important resources that an
organization can acquire

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management
84 of 85 8.6 Project closure

Personnel issues in project closing


84
 the project manager must assure workers that their job is
secured despite completion of a project work
 in a project that has lasted for a prolonged period,
the project team becomes like a family to some individuals,
and losing that family can arouse considerable sadness.
 emotions of project people should be properly managed
because failure to do so may result in people not wanting
future project assignments.
Project Financing and Management-Project Thursday, January 23, 2020
Project Financing and Management-Project Management
Management
85 of 85

85

Project Financing and Management-Project Thursday, January 23, 2020


Project Financing and Management-Project Management
Management

You might also like