Professional Documents
Culture Documents
Project Risk Management
Project Risk Management
Project Management
Risk Risk
Monitoring Identification
Risk Risk
Handling Analysis
Risk Identification
Business risk
– Market risk
– Shifts in business strategy or senior management
Technical risk
– Design and development problems
– Testing and maintenance problems
– Technical uncertainty
Project risk
– Budget
– Schedule
– Personnel
– Requirements problems
Risk Factors: What the
Literature Says . . .
Technological newness
Application size
Application complexity
Task complexity
Project team expertise
Organizational environment
Magnitude of potential loss
Insufficient/inappropriate staffing
A 2 5 10 1
B 4 2 8 3
C 3 3 9 2
Risk Handling
Risk prevention
– Develop options to reduce the potential of the problem
occurring
Risk avoidance
– Accepting a lower risk (another solution) to avoid a high risk
Risk remedy
– Monitoring risk status and developing solutions to reduce
effect when risk becomes a problem
Risk assumption
– Decision to accept the risk should it occur
Risk reduction
– Obtaining additional information that will reduce risk (e.g.,
prototyping, incremental development)
Risk Monitoring
Should be done periodically
– (e.g., when certain milestones are reached, at the end
of project phases, at steering committee meetings,
etc.)
Useful to regularly assess and update project risk
exposure
Senior management should be involved in
monitoring and should be aware of exposures
Listen to the project group
Establishing Risk Referent
Levels
Risk referent levels can be set to define
regions of acceptable and unacceptable risks
Three typical risk referent levels
– Cost overrun
– Schedule slippage
– Performance criteria
Region in which
Example Projected project termination Referent level for
Schedule will occur cost/schedule
Overrun overruns