Professional Documents
Culture Documents
Reliability
through
PM Optimisation
Project Team:
Electrician
Planner
Mechanic
Operator
Reliability Engineer
Facilitator: Steve Turner 1
PMO2000™ www.reliabilityassurance.com
Why investigate the Residue Cell C’s
PMO2000™
How we went about it
PMO2000™
Opportunities identified
PMO2000™
Opportunities Identified…cont
PMO2000™
Outcome PM Optimisation Analysis
Delete
13%
Extend Interval
11%
New Task
Use As Is 7%
60%
Reduce Interval
9%
PMO2000™
Outcome PM Optimisation Analysis
Use As Is
13% Delete
19%
Reduce Interval
25%
Extend Interval
30%
New Task
13%
Analysis of Mechanical Changes
PMO2000™
Downtime Analysis-Mechanical
Monthly 5.17 2 3 12 36
Two
Weeks 2.25 1 2.25 26 59 1 8 26 208
PMO2000™
Downtime Schedule
10
Original
Total 32hrs
8
Revised
Downtime Hours
Total 30hrs
6
0
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
PMO2000™
Some interesting issues
PMO2000™
Some interesting issues….cont
PMO2000™
Other benefits...
PMO2000™
What needs to happen now
PMO2000™
Improved Reliability
through
PM Optimisation
Project Team:
• Electrician
• Planner
• Mechanic
• Operator
• Reliability Engineer
Facilitator: Steve Turner 18
PMO2000™ www.reliabilityassurance.com