Professional Documents
Culture Documents
Project Management
Project Plan
Information gathering
Constraints
Alternative analysis
Project objectives
Problem Statement
Project
Project Start
Completion
Goal Goal Goal Goal
1 2 3 4
• It is the sum of the cost budget for all the activities in the
baseline( original) plan of the project at any specific future
point in time.
• It is budgeted (planned) cost as per the project plan for a part
of the project to be completed in a given time frame
• For example , the BCWS for all the activities in a product
development project till day is from commencement is say Rs
2.0 Lakhs.
• Budgeted Cost of Work Scheduled (BCWS) is also referred
to as Planned Value
Budgeted cost of work scheduled(BCWS)
Formula
• Planned Value = (Planned % Complete) X
(BAC)
• BAC is the budget at completion.
Example
TOTAL $7,000
%
Start
ID Task End Date Budget Complet
date
e
Build
100 Feb. 10 Feb. 20 $4,000 75%
Fence
200 Lay Sod Feb. 12 Feb. 25 $3,000 10%
TOTAL $7,000
Solution
• Step 2: Determine Earned Value (EV)
• Task 100 is 75% complete, therefore EV = 75% x $4,000
= $3,000.
• Task 200 is 10% complete, therefore EV = 10% x $3,000
= $300.
• Next we will add a column called EV.
%
ID Task Start date End Date Budget EV
Complete
Build
100 Feb. 10 Feb. 20 $4,000 75% $3,000
Fence
TOTAL $7,000
Solution
• Step 3: Determine Actual Cost (AC).
• Again, since this is not a real project we will have to
assume that Task 100 has an actual cost of $2,500, and
Task 200 has an actual cost of $400.
• Now we will add a column called AC.
TOTAL $7,000
Solution
• Step 4: Determine Cost Performance Index (CPI)
• CPI = EV / AC.
%
Start End
ID Task Budget Comple EV AC CPI
date Date
te
Build
100 Feb. 10 Feb. 20 $4,000 75% $3,000 $2,500 1.20
Fence
200 Lay Sod Feb. 12 Feb. 25 $3,000 10% $300 $400 0.75
Formula
SPI = EV / PV
Where:
•SPI = Schedule Performance Index
•EV = Earned Value (dollars, euros, etc.)
•PV = Planned Value (dollars, euros, etc.)
Interpretation of Results
• If SPI is less than 1, the task is behind schedule.
• If SPI is 1, the task is on schedule
• If SPI is greater than 1, the task is ahead of schedule.
• For example,
• SPI = 0 means the project work has not started.
• SPI = 0.5 means the project has performed half the
work it was supposed to at this point.
• SPI = 1.0 means the project is on schedule.
• SPI = 2.0 means the project has performed twice the
work it was supposed to at this point.
Example
• Let’s say we have a project with two tasks, building a fence
and laying sod. The initial schedule baseline is:
TOTAL $7,000
Solution
• Step 2: Determine Planned Value (PV).
• Task 100 should be 50% complete, given the start and end
dates of Feb. 10 and Feb. 20, respectively. Therefore PV =
50% x $4,000 = $2,000.
• Task 200 should be 3 out of 13 days complete, which is
23%. Therefore, PV = 23% x $3,000 = $690.
%
ID Task Start date End Date Budget PV
Complete
Build
100 Feb. 10 Feb. 20 $4,000 75% $2,000
Fence
200 Lay Sod Feb. 12 Feb. 25 $3,000 10% $690