Professional Documents
Culture Documents
Projects
Peter Igbi, MNSE
What is a Project?
A series of tasks that need to be completed in order to reach a specific
outcome. It consists of a series of inputs and outputs required to
achieve a particular goal.
They range:
From simple to complex
Single discipline/individual to multiple
Greenfield to Brownfield
The Nigerian Project Delivery
Climate
“Why projects fail in Developing Countries”…PMI
• Cycle Time
Sensitivity
• Customer
Satisfaction • Front End Delivery
• Critical Success Factors definition
• Quality Separation • Risk Identification
• Cost Leadership • Project driver focus
• Contracting and Procurement
• Risk Management
• Technical
• Non-Technical
• Construction Management & Delivery
• Assurance and stage gates (Decision Control Framewor
Delivering projects – Importance of Standardized
Processes
• Deploy an integrated project delivery toolbox
• What needs to be done
• In what steps (intent focused)
• In what order (intent focused)
• Grow Leaders
• Develop critical skills
• Deploy the right people
Technical Risk Sources: Usually from technology that drives the process.
There is a
difference
between Risks
and Issues
Typical Problems in Project Delivery
Inaccurate/outdated Drawings
Integrity scope which could be covered by routine maintenance programs
added to the project
Obsolescence of equipment marked for replication
Unclear Standards strategy (for example carbon copy conflict vs new
standards and new DEPs)
Design constraints not understood or improperly defined
Tie-ins not properly identified
Recycles due to scope changes
Cost estimate basis is not robust
Schedule not resource loaded
Turn around not factored into the planning
Partner disagreement
Unclear business case
Under-resourced teams
Hence a successful and competitive
project is:
• Well Planned
• Well Resourced with a strong team
• Has a clear and effective communication structure
• Has good change control
• Has a clear and focused vision of what it aims to achieve
• Is adequately positioned to manage risks
CASE STUDY-1
Case 1: Mama Put!!
- Front End Considerations
- Success Factors Location, Demand, Types of Meals(diverse/specific), Optics
- Risk Identification Price escalations, hygiene, environment , Local Government regulations, competition
- Project Driver Profit
- Procurement
- Availability and cost
- Proximity to business
- Rent?
- Construction
- Wind direction
- Proximity to the Pot
- Sitting arrangement
- Washing of plates and customer turnover
- Quality Control
- Lessons Learnt from others
- Tasting and cooking skills
- Cash flow management
CASE STUDY-2
Case 2: Installation New Equipment in Brownfield Location
Understated
Understated Piping
Piping Lengths
Lengths Poor
Poor Relief
Relief System
System Removal
Removal Assessment
Assessment
Poor
Poor Site Survey/Stakeholder engagement
Site Survey/Stakeholder engagement System impact not exhaustively considered
Initial design resulted in excessive dP Stakeholders (PEQ) brought in late
Addendum
Addendum to to BDEP
BDEP required
required System rerating
System rerating and
and additional
additional scope
scope
Schedule delay, iterations with
Schedule delay, iterations with Engineering
Engineering Contractor
Contractor
Tie-in
Tie-in Challenges
Challenges Picked
Picked up
up Late
Late
Inaccurate
Inaccurate Pipeline
Pipeline Sizing
Sizing
Tie-in
Tie-in requirements not properly considered
requirements not properly considered in
in
original design In-unit
In-unit piping not resized to
piping not resized to match
match with
with increased
increased
flow
Delay
Delay in
in tie-in
tie-in Brownfiel flow
Velocity
Velocity in
in piping
piping above
above max.
max. as
as per
per DEP
DEP
Potential Production
Potential Production Impact
Impact
Scope
Scope change
change with
with associated
associated impacts
d Failures impacts
Standards
Standards Requirements
Requirements Not
Scope Change
Not Picked
Change (additional
Picked Up
Up Early
Early Execution Assumptions made without proper verification
Scope (additional isolation
isolation valves)
valves) Vessel
Vessel with
with design
design flaws
flaws delivered
delivered on
on site
site
Schedule Impact IPF workshop done in Execute phase
IPF workshop done in Execute phase
Additional Scope (Isolation valves, etc)
Brownfield Projects Are
• Within the physical boundaries of an existing asset
• The new facilities physically interact with existing facilities
• Typically the level of interaction increases as project size increases
• The physical proximity of new equipment to existing assets creates SIMOPs,
technical, process safety and construction safety interactions.
…Samuel Johnson