Professional Documents
Culture Documents
Project Overview:
Plot Area 741.64 SQMT & FSI is 3, BUA 63,344 SFT, Height is 69.35meter
This project is super luxury apartments with spacious balcony and carpet area.
40 feet High Monumental Garden.
16feet High Grand Entrance Lobby
L1-L6 level Automated Tower Parking.
Transfer Girder above the L6 level and 15 Residential floors.
Fitness Centre of 250 SFT
2nd & 9th is Refuge Floors.
15 exclusive residences only.
One 4BHK flat of Carpet area 1944sft +140sft Deck per floor and Refuge Floors
have 3BHK flat of Carpet area 1358sft+139sft Deck each.
Maintenance free sustainable façade.
Roof Top Swimming Pool
ALL MAJOR ACTIVITIES
Soil Investigation:
Soil Investigation was done at earlier stage to obtain the soil properties and quality for
proposing the foundation method, load bearing capacity and obtain probable settlement of
structure. Shore Pile design was proposed and carried out.
Site Clearance:
Site Clearance Certificate is issued to start the work at site. It is part of enabling works
which involves clearing or demolition on existing structure in the land which needs to be
developed. Site is cleared to start the Construction.
ALL MAJOR ACTIVITIES
Quality Control tests are done like Cube testing of concrete, Steel testing, concrete blocks
and sieve analysis of aggregates for RCC.
All the finishing works are carried out with quality assurance.
Safety measures are carried out at the site during the execution for the labours. Safety
trainings are provided to the labours to educate them. Hygiene and cleanliness is
maintained at the site and doctor are visited at the site for health checkups.
Safety Shoes, Jacket etc are kept on site for the visitors.
Handover to Client
After the completion of all the works from contractors end , inspection is carried out.
Finally the project is handed over to the client for operational purpose.
PROJECT DURATION
Start Date 18/05/2017 Finish Date
03/1/2020 i.e. 32 months
Post OC Works Completion Date
12/03/2020
Project Manager
Quality &
Procurement MEP Civil Site Planning QS & Billing
Safety
Engineer Engineer Engineer Engineer Engineer
Engineer
Following are the Site Progress Photographs attached to support the above progress reports
SITE PHOTOS & PROGRESS
Raft Reinforcement
SITE PHOTOS & PROGRESS
Foundation
SITE PHOTOS & PROGRESS
SITE PHOTOS & PROGRESS
Girder Shuttering
& Reinforcement
SITE PHOTOS & PROGRESS
Garden Level-
Triple Height
SITE PHOTOS & PROGRESS
Tower Parking RCC
SITE PHOTOS & PROGRESS
Progress Photograph
SITE PHOTOS & PROGRESS
Side Elevation
SITE PHOTOS & PROGRESS
Artist Impression
THANK YOU