Professional Documents
Culture Documents
V5X Installation and Commissioning
V5X Installation and Commissioning
Kay
Technical Support Engineer
Preparation Drawing Review
Site Investigation
Installation
Technician
Pre-
Tools
commissioning
Commissioning
1. Drawing review
Two Ways
Manual check
Using software
Manual check
L1
L8 L9
L6 L7
f g h i j
L2
L4 L5
L3
a b c d e
Manual check
L1
L8 L9
L6 L7
f g h i j
L2
L4 L5
L3
a b c d e
Manual check
f g h i j
≤ 110m
L2 ≤ 30m
L4 L5
L3
a b c d e
Manual check
•For indoor auxiliary pipes > 10m long, check that pipe diameter has been increased
Sum of indoor unit Gas pipe Liquid pipe (mm) Branch joint kit
capacity indexes (A) (mm)
A < 166 Φ15.9 Φ9.53 FQZHN-01D
Equivalent length of all liquid pipes < 90m Equivalent length of all liquid pipes ≥ 90m
Total capacity of
outdoor units
Gas pipe (mm) Liquid pipe (mm) Branch joint kit Gas pipe (mm) Liquid pipe (mm) Branch joint kit
Plumb bob
Plumb line
Indoor unit installation
•Hangers should be full-thread, Φ10mm steel
•Use dual nuts
One row
Two rows
Outdoor unit installation
Three or
more rows
Outdoor unit installation
• Foundation can be steel or concrete
• Leave sufficient space for condensate drainage
• Foundation should be taller than deepest snowfall in local climate
Fixing bolts
Transverse Longitudinal
duct duct
OR
Outdoor unit installation
• Duct is needed when ventilation is poor or installation space is limited
• ① Remove the steel filter first (2 pieces)
• ② Then fix the duct using self-tapping screws (ST 3.9 x 12)
Transverse Longitudinal
duct duct
OR
Piping storage
• If piping is to be used soon, seal the openings with plugs or adhesive tapes
• If piping is to be stored for a long time, charge the piping with nitrogen at 0.2-0.5MPa
and seal the openings by brazing
Piping selection
Piping outer diameter Temper Minimum thickness
(mm) (mm)
Φ6.35 0.8
Φ9.53 0.8
O
Φ12.7 0.8
(annealed)
Φ15.9 1.0
Φ19.1 1.0
Φ22.2 1.2
Φ25.4 1.2
Φ28.6 1.3
Φ31.8 1/2H 1.5
Φ38.1 (half hard) 1.5
Φ41.3 1.5
Φ44.5 1.5
Φ54.0 1.8
Piping cutting
• Measure the exact pipe length
• Use pipe cutter to cut piping
• Use scraper to remove copper burrs
• Seal the opening before positioning the piping
Piping insulation
• Prevents condensation forming on piping
• Protects people from danger caused by high temperature refrigerant
• Reduces energy losses
Φ6.35 - 12.7 15
Φ15.9 - 38.1 20
Φ41.3 - 54.0 25
Piping insulation
• Use glue to connect two insulation segments together
• Use 5 cm PE tape to fix joint seams
Piping installation
• Spacing between refrigerant piping supports
Diameter (mm) ≤ 20 20 - 40 ≥ 40
• Determine spacings based on liquid pipe diameter where liquid and gas pipe hung together
Piping installation
• Use pipe expander to expand pipe ends when connecting two same-sized pipes together
• Use bender to bend pipes ≤ Φ19.1mm, use elbow when pipe ≥ Φ22.2 mm
Piping installation
• Lay the piping on the bearings and use clamps to fix
• Connect the sections of piping and fix using tape
• Seal the pipe opening after laying until brazing
Piping installation
• Using Midea branch joints is recommended, to ensure quality, compatibility with Midea units
and well-balanced refrigerant flow
Horizontally
Vertically
Piping installation
• To ensure smooth oil return all outdoor branch pipes must not be higher than the
refrigerant outlets
Piping installation
Oxide
Piping installation
• Flow nitrogen at around 0.02 - 0.03 MPa
Hand valve
Sealing tape Pressure hose
Nitrogen cylinder
Piping installation
To eliminate dust, moisture and other particles:
• Method :
1. Block all the pipe openings
2. Flush the pipe with nitrogen at 0.5 MPa
3. Use your hand to block one of the openings
4. When the pressure is too high to block,
remove your hand
5. Repeat steps 3 and 4 for each opening Dust
Moisture
6. After flushing, seal all the openings
Other
particles
Eliminate
Block for a few seconds Then release
Piping installation
• Pipe flushing sequence :1-2-3-4-5-6 working towards the outdoor units
• Seal other pipes while flushing one pipe
• Seal all the pipes once finished flushing
Nitrogen
②
⑥ ⑤ ④ ③ ①
Piping installation
• Use flaring tools to make flare openings free from cracks and scratches
• Connect the flared openings to the IDU connections, using dual wrenches to fasten the nuts
Drainage piping
• Select horizontal drainage piping according to IDU capacity
Capacity (L/h)
Nominal
PVC piping Remarks
diameter (mm) Slope 1:50 Slope 1:100
PVC25 25 39 27 Branch
PVC32 30 70 50 piping only
PVC40 40 125 88
Branch or
PVC50 50 247 175 main piping
PVC63 63 473 334
Drainage piping
• Select insulation size according to drain piping diameter
• Insulation should be > 10mm thick to avoid condensation forming
• Use clamp included with the IDU to fix the insulation and flexible tube at the unit
Drainage piping
• Slope of main drainage pipe should be > 1%
• Drainage pipe should be independent of other water pipes
• Air vents should face downwards to prevent dust entering
Vent
≥ 1% Condensate
pipe
Drainage piping
Lift pipes are required for units with built-in drainage pumps:
• Lift height up to 1000 mm from bottom of the unit
• Drainage piping should slope downwards from top of lift to main drainage pipe
Drainage piping
For units without drainage pumps:
• Direct drainage option: install U-shaped pipe
• Pump out option: install pump box SBH-04 or SBH-05
50mm
50mm
Plug
• IDU drainage pipe should be higher than main drainage pipe to avoid water backflow
• Support spacing is around 0.8 - 1.0m
• To avoid backflow, two horizontal drain pipes should not meet at the same level
• Check watertightness after completing drainage pipe installation
P,Q,E H1,H2, E
X, Y, E
Wiring connections
• Select indoor unit power wiring according to below table
• Select leakage protector based on 1.5 - 2.5 times total rated current
• Select manual switch based on max. running current
Leakage protector
and manual switch
3-Phase
380-415V
380-415V 100mA
4x10 mm2 (< 20m)
16HP 3Ph- 4x16 mm2 (< 50m) 1x10mm 2
40 35 0.1sec or
50/60Hz less
4x16 mm2 (< 20m)
18HP 1x16mm2 50 40
4x25 mm2 (< 50m)
Mount the
panel
Duct installation
• Ducting for duct units
Galvanized steel sheet
Polyurethane foam
Preparation
Installation
Pre-
Gastightness Test
commissioning
Joint Insulation
Commissioning
Vacuum Drying
Charging Refrigerant
3. Gastightness test
• The gas charged into the pipes must be nitrogen
• Test procedure should follow steps below
• After gastightness test, if vacuum drying is not to be done immediately, reduce the
system pressure down to 1.5MPa
Joint insulation
• After gastightness test, joint insulation can be applied
• Use additional insulation segments to fill the joint gaps
• Separately insulate the indoor unit liquid and gas pipe connectors
Vacuum drying
• To remove air and moisture from the piping system
• Use a vacuum pump with a displacement in excess of 4L/s
• Use a vacuum pump capable of maintaining a pressure of -0.1MPa (-14.5PSI)
Φ6.35 0.022
Φ9.53 0.057
Φ12.7 0.110
Φ15.9 0.170
Φ19.1 0.260
Φ22.2 0.360
Φ25.4 0.520
Φ28.6 0.680
Charging refrigerant
• Refrigerant charging procedure
Make sure the gastightness test, pipe insulation and vacuuming have been
finished
Charge liquid refrigerant to both sides, use a scale to measure the charged
weight
Upside down
Oil balance
valve
Preparation
Installation
Pre-
commissioning
Commissioning Setting ODU Switches
Setting IDU Addresses
Test Running
Handing Over
4. ODU switch setting
0 Master unit
ENC1 ENC3 S12 S3
1 Slave unit
S7 ENC2 S1
2 Slave unit
3 Slave unit
ENC4 S10
S4 S2 S5 S6
ODU switch setting
0 8HP
ENC1 ENC3 S12 S3
1 10HP
S7 ENC2 S1
2 12HP
3 14HP
ENC4 S10
4 16HP
S4 S2 S5 S6
5 18HP
6 20HP
7 22HP
≥8 Invalid
ODU switch setting
S4 S2 S5 S6
ENC3 A-F means 42-47 units
0 System 0
ENC1 ENC3 S12 S3
1 System 1
S7 ENC2 S1
2 System 2
3 System 3
ENC4 S10
4 System 4
S4 S2 S5 S6
5 System 5
6 System 6
7 System 7
≥8 Invalid
ODU switch setting
S1 S3 Switch
Function Description
Number
S4 S2 S5 S6
S5 Priority mode selection
RM05 controller
IDU address setting
• Manual address setting using RM12 remote controller
• Address setting range: 0 - 63
1. Press below three buttons at same time to enter address setting function
+ + 3 2
2. Press ON/OFF button to display above icon
3. Press up/down button select the address no. 5 4
4. Press the Fan Speed button to send address
1 1
5. Press the Mode button to check address
6. Exit the function by pressing the same three buttons as in step 1
1
IDU address setting
• Manual address setting using KJR-29B wired controller
• Address setting range: 0 - 63
3 1
Test running
• Power on ODUs and leave for at least 12 hours to preheat
• Power on IDUs and check for error codes
• Check if ODU displays correct no. of IDUs Installation
Inspection Report
• For installation inspection guidelines refer to embedded Word document
Reference
No. of IDUs
Check button
Test running
• Complete the commissioning report after test running
Heating Mode
• Set 30⁰C, high fan speed, heating mode for all IDUs
• During running, check for any abnormal noise or leakage from
IDUs or ODUs
• After running for 1hr, check system operating parameters
Test running
• Cooling mode reference parameters
Conditions
Outdoor 35⁰C DB Outdoor 43⁰C DB
Indoor 27/19⁰C DB/WB Indoor 32/23⁰C DB/WB
High pressure (MPa) 2.8 - 3.0 3.4 - 3.8
Win - Win
Q&A
Questions?
Thank you