REPORTS
Inventory Report
MB52
Inventory as on Date for project and O&M
MB5B
Quantity of Material Received or Issued from store within a
period.
ME2J
Supply progress of any PO related for entire project
This is to be used if information is required for all the PO
pertaining to a project or an element of a project
Supply Progress
For a project or an Element
Variant: PROJ_PROG
Input Field:
Project: SAP Project Name like TR-200811.
WBS Element: SAP WBS like TR-200811-02-02-01
Item Category: “D” for Service PO other wise blank
Account assignment category: “Q” for regular project material.
Delivery date: for items whose delivery falls within this period
Material group: it is to filled if one particular type of PO is to be
searched like PO for conductor supply or PO for vehicle.
Supply Progress
ME2N
Supply progress of any PO related to project or O&M
Provides item wise information about qty yet to be delivered
and qty yet to be billed along with total qty.
Supply Progress
For supply PO
Variant: SUPPLY_PROG
Input Field:
Purchase Documet: SAP PO no. can be one or more or range as
per requirement.
Purchasing Group: PO related to C&M group for ex. C00 is
SR-II RHQ -1
Plant: to check out substation wise purchase order. Mainly used
for O&M PO.
Supply Progress
ME2S
Progress of any Service PO related to project or O&M
Provides item wise information about qty yet to be delivered
and qty yet to be billed along with total qty.
Supply Progress
For Service PO
Variant: SER_PROG
Input Field:
Purchase Documet: SAP PO no. can be one or more or range as
per requirement.
Purchasing Group: PO related to C&M group for ex. C00 is
SR-II RHQ -1
Plant: to check out substation wise purchase order. Mainly used
for O&M PO.
Similarly ME2J can be used monitoring all PO pertaining
of one project
PO Analysis
ME80FN
Can be used for viewing PO BOQ, delivering schedule
monitoring as well as PO history analysis (Like GR,
Cancelled GR, invoice cleared by Finance line item wise)
Service Consumption Report
ML84
Can be used to find out cost incurred in a particular service
for a particular station in a given period, for example vehicle
cost for a station.
PROJECT COST
CJI3
Total expense of a Project or an Element on accrual basis
PROJECT COST
For PROJECT
Variant: PROJ_COST
Input Field:
Project: SAP Project Name like TR-200811.
WBS Element: SAP WBS like TR-200811-02-02-01
Posting Date: Period for which the data is required.
Payment Details
ZMATPAY
PO Wise actual Payment, Retention and Tax details.
HR Reports
ZHR_EMP_MASTER_DATA - Employee Master data details
ZHR_EMP_SUP - Employee List along with their Reporting
Officer
ZHR_BIO_DATA - One Page Bio Data of Employees including
his Basic Details, Qualification & Experience History.
PT_QTA10 - Leave Balance (EL, HPL, SAL etc) of Employees
as on date.
ZHR_TIME_ABSENCE - Report regarding the Leave
Availed/Tour Data of the employees in a certain period
ZHR_EMP_CLAIM_REPORT - Consolidated report regarding
the Claims i.e. Contingent, Medical etc., Leave Encashment &
Advances etc. paid through ESS in a certain period
WBS Element Report
CN43N
Details of WBS ,Description, Profit centre, Region , Status
of WBS for a given Project
WBS Element Report
For a project
Variant: PROJ_WBS
Input Field:
Project: SAP Project Name like TR-200811.
Output :
ZPSL2R1
Shows month wise planned erection activities as per
approved L-2
Erection L-2 View
Input Field:
Project: SAP Project Name like TR-201202.
WBS Element: SAP WBS like TR-201202-01-01-01
Output :
Package wise monthly planned erection activities as per L-2
Supply L-2 View
ZMM_INSP03
Shows month wise planned supply as per approved L-2
Supply L-2 View
Input Field:
Purchase Document : SAP PO Number
Material :SAP Material Number
Delivery/Inspection date : Dates if required
Output :
PO wise monthly planned supply Quantity as per approved L-2
MONTHWISE ERECTION PROGRESS
REPORT
ZPSR_ACTUAL_REPORT
Month wise erection Progress
MONTHWISE ERECTION PROGRESS
REPORT
Input Field:
Project: SAP Project Name like TR-201202.
WBS Element: SAP WBS like TR-201202-01-01-01
Start Date & End Date : If specific period progress is required
Output :
Package wise monthly erection progress
SUPPLY PROGRESS REPORT
ZPSSUPPLY
Progress of Supply of Material project/WBS/PO Wise
SUPPLY PROGRESS REPORT
Input Field:
Project: SAP Project Name like TR-201202.
WBS Element: SAP WBS like TR-201202-01-01-01
Purchasing Document : SAP PO Number
Month & Year : month & year for progress is required
Output :
PO Wise Scheduled V/s Actual Material supply Status
Balanced Quantity of Material
Last Inspected/Total Inspected Quantity
Physical Progress of Pkg
ZPSL2_SERVICE
Cumulative progress V/s L-2 plan & Current month
progress, erection activities of Transmission Line &
Substation e.g. Tower Foundation, Erection & Stringing &
No. of Gangs deployed
PACKAGE PHYSICAL PROGRESS
For PROJECT
Variant: cmg
Input Field:
Project: SAP Project Name like TR-200811.
WBS Element: SAP WBS like TR-200811-02-02-02
Output :
CUMULATIVE PLANNED Vs Actual Progress
Current month planned vs Actual Progress
No. of Gangs
Vendor detail
Physical Progress of Project
ZPSREPORT
Cumulative progress V/s L-2 plan & Last 03 month progress
of erection activities of Transmission Line / Substation e.g.
Tower Foundation, Erection & Stringing.
PROJECT PHYSICAL PROGRESS
For PROJECT
Variant: PROG_TL
Input Field:
Project: SAP Project Name like TR-200811.
WBS Element: SAP WBS like TR-200811-02-02
Region : S1,S2,N1etc.
Vendor
Output :
Planned vs actual progress, balance, Target, Year wise progress
Click Print option and view PDF Report
DIVERSION REPORT
ZMM_DIVREP
Details of the diversion of material from one package to
other package.
DIVERSION REPORT
Input Field:
Project: SAP Project Name like TR-200811.
WBS Element: SAP WBS like TR-200811-02-02-01
Material : Material number as per SAP
Date Range : Start & end date during which diversion happened
DETAILED & SUMMARY L3 REPORT for TL
ZPSL3R
Progress of Transmission line location wise (L-3) &
Visual Chart
DETAILED & SUMMARY L3 REPORT of TL
Summary Report
Input Field:
Project: SAP Project Name like TR-201103.
WBS Element: SAP WBS like TR-201103-04-04-01-04
Various other parameters such as Tower Location number,
Tower Type, Foundation Type, Crossing, Forest etc.
Output :
Summary report of Foundation, Tower Erection, Stringing
Pictorial representation of location wise Progress
DETAILED & SUMMARY L3 REPORT
Detailed Report
Input Field:
Project: SAP Project Name like TR-201103.
WBS Element: SAP WBS like TR-201103-04-04-01-04
Various other parameters such as Tower Location number,
Tower Type, Foundation Type, Crossing, Forest etc.
Output :
Detailed report of Foundation, TE, Stringing location wise
Creation of Visual Chart
Section Report (Page Chart) of TL
ZPSSECTION_REPORT
Shows Section wise Progress of Trans Line for stringing
Planning
Section Report (Page Chart) of TL
Input Field:
Project: SAP Project Name like TR-201103.
WBS Element: SAP WBS like TR-201103-04-04-01-04
Output :
Section Wise Package wise monthly planned erection activities
as per L-2