Professional Documents
Culture Documents
Lecture-20
2
Definition
3
Uses of Caisson
• To reach the hard bearing stratum for transferring the load
coming on supports for bridge piers and building columns.
• To serve as an impervious core wall of earth dams, when
placed adjacent to each other.
4
Uses of Caisson
• To provide an access to a deep shaft or a tunnel.
• To provide an enclosure below water level for installing
machinery, pump, etc.
5
Difference between Cofferdam & Caisson
• Cofferdam is a temporary structure while caisson is a part of a
permanent structure.
• At places where cofferdams can not be dewatered successfully
caisson is used.
• In cases where, cofferdam becomes uneconomical when plan
area is small compared to depth of water.
6
Reasons for adoption of caisson:
• Depth of water
• Nature of soil to be penetrated
• Permeability of soil below foundation level
7
Material Used for Construction:
1. Cast-iron
2. Reinforced cement concrete
3. Steel
4. Timber
8
Suitability of Cast-iron
• Suitable for caissons of open well type.
• Cost is more compared to R.C.C or Steel.
• Unsuitable for pneumatic caisson, because of chances of failure
due to compressed air.
9
Suitability of R.C.C.
• Suitable for caisson shoes.
• Material is having heavy weight & difficult to handle.
10
Suitability of steel
• It is found to be most suitable material
• Usually in the form of a double skin of steel plates
• The hollow space is filled with cement concrete
11
Suitability of Timber
• Required at early stages of construction
• Now a days practically not adopted because of its weight &
chances of fire
12
Classification of Caisson
CAISSON
13
Box Caisson
PLAN
Filling
A B
Sand carpet
Concrete Placed by
Tremie
Section On A-B
14
Box Caisson
• Box is open at top & closed at bottom
• May be built by R.C.C or steel
15
Construction of Box Caisson
1) A level bearing surface is prepared by means of dredging or
divers
2) The caisson is constructed on shore, launched and floated to the
site of work
3) The box is then filled with suitable material to effect further
sinking , if necessary.
4) The top is then sealed & further foundation work is started above
the water surface.
16
Conditions favorable for construction of Box Caisson
17
Points for Box Caisson
• Bottom of box caisson is a part of permanent structure
• Successfully used for construction of quay walls in series.
18
WELLS Twin Octagonal
Twin Hexagonal
Rectangular
CIRCULAR Twin Circular
Double-D
19
WELLS
• A well is open at top as well as bottom
20
Advantages of circular well
• The ratio of sinking effort to skin friction is maximum, because
of min. perimeter
21
Advantages of circular well cont…
Cutting Edge
If soft material covers the site, it is
necessary to remove as much of it as
possible before placing the caisson
23
Scaffolding Towers
WELL
Joists
Rails
Staining
25
Procedure adopted for Construction of
Single well
26
Multiple wells or Monoliths
30m
Construction of Monoliths
45m
15m
18 m wide door
28m
Centre line of Bridge
27
Sequence of dredging in a Monolith
1 4 1
3 5 3
2 5 2
4 6 4
2 5 2
3 5 3
1 4 1
28
Construction Procedure
1. Suitable site is selected
2. Area of the dry dock should be kept bigger then the monolith
3. Door should be provided with sufficient width to take out
monolith.
4. Monolith height should be such that it will remain half
submerged.
29
Construction Procedure
5. Dredging then stars as per the sequence shown in fig.
6.After dredging to required depth, the whole monolith is
gradually sunk uniformly up to required level
7. The bottom is sealed by concrete and wells are filled with
concrete and cap is provided at the top to finish construction
30
Advantages of monoliths
• All the work is done above water & hence reduction in cost.
• There is no theoretical limit for the depth up to which a monolith
can be sunk
• The unskilled labour can be employed for the construction of
monoliths
31
Disadvantages of monoliths
• Foundation level is not available for inspection
• The rate of sinking can not be estimated
• Monolith may have moderate amount of tilting
• Less strength of concrete
32
Use of Monoliths
• Widely used for foundation work of bridge piers, quay walls etc
• Use of monoliths is justified for depth of water which will be
unsuitable for the cofferdam or prohibit the use of pneumatic
caisson
33
Cylinders Staging
Cylinder
River Bed
Pile Cap
Piles
34
Two cylinders with bracing Cylinders used
for bridge piers
Bracing
HWL
LWL
Cylinder Cylinder
River Bed
Bearing Surface
35
Construction procedure
• Cylinder is brought to site & kept in vertical position before
sinking starts
• Cylinders are usually taken in lengths of 2 to 3 m
• Metal cylinders ….
• After removing the material from inside of the cylinder, the
space is filled with concrete for the full height.
36
Advantages of Cylinders
• Obstruction to the water flow is less
• Quantity of excavation is small
• Simple construction
• Cheap in cost
• Do not require expensive and complicated lifting devices
37
Disadvantages of cylinders
• Difficult to sink them vertically in running water
• Load bearing capacity is less due to small dia.
• More chances of tilting
• Thickness is less, hence not suitable for high bridges
• Require additional loading for sinking ( self wt. is less)
38
PNEUMATIC CAISSON
39
Hoisting Rope Or cable
Air for
Man Lock
Compressor
Water surface
Wall Of Caisson
Air Lock
Muck Bucket
Working Chamber
41
Air pressure
• p = wh
42
Air pressure
• The limiting air pressure under which a man can work is @ 343
KN/m2
• So, maximum depth of water up to which a pneumatic caisson
can be adopted from health point of view is 343/9.81 = 35 m
• The pneumatic caisson can be used for the depths of water
ranging from 12 to 35 m.
43
Advantages of pneumatic caisson
• Inspection of work
• Concreting of foundation
• Easy removal of obstruction
• Checking of verticality of caisson
• Reliable quality of work
44
Disadvantages of Pneumatic caisson
• Extreme care is required to provide suitable health controls for
labors.
• It requires high degree of skill in operation.
• Cost of construction is high.
• The depth of penetration is limited below water level.
(35m max.)
45
Caisson sickness
• Compressed air sickness
• Symptoms-
- dizziness
- double vision
- headache
- trouble to speaking
- pain in legs etc.
46
Precautions to avoid caisson sickness
48
Thank You
49