Professional Documents
Culture Documents
Corrosion
Coating
Cathodic protection
Cathodic protection criteria
CP Project
Overview of CP equipment
Safety / hazards
Routine testing / inspection
Routine maintenance
General trouble shooting
1
What Is Corrosion
In general, Degradation of materials through environmental
interaction.
Metals are put into high energy state during extraction from
ores & again want to be in low energy state which is their
oxides.
2
Corrosion in Metals
Corrosion Cell
( Due to different soil Resistivity, Oxygen concentration,
Dissimilar Metal )
Anode – Positively Charged
Cathode – Negatively Charged
Electrolyte – Soil
– Structure / Pipe
3
Detection of Corrosion Metals
If we place a metal in the soil, we can
measure the voltage between them using a
reference cell. ( Also Inside the A/G Water
Tanks )
For Mild Steel ( Rusted ) –0.2 to –0.5V
For Mild Steel ( New ) –0.5 to –0.8V
Remote Vs Close Interval Survey
Soil Resistivity, Line Current Survey
4
Mitigation of Corrosion
Coating of Metal Surface
– Coating will break the contact between metal &
Soil.
– Then there will not any path for the corrosion
current to flow.
– There are some limitations for coatings such as
damage during installation, coating deformation
etc
5
Cathodic Protection
In normal situation in U/G metal, current will flow
to soil from metal.
CP is the system which will make the U/G metal
to receive the current from the soil.
This is exactly opposite to the corrosion current
flow.
Thus the corrosion rate will be reduced.
If CP is used for coated metals, required current
will be considerably less.
6
Types of Cathodic Protection
Impressed Current Cathodic Protection
– DC power source is used
– Can be applied to Large Surface Area & long duration.
– Surface & Deep Well Ground Bed
Galvanic Cathodic Protection
– This is also called Sacrificial CP System.
– Can be used for Small Surface Area only & Shorter
duration.
– Anode will be active metals such as Magnesium, Al etc
7
8
Transformer Rectifiers
9
Surface Anode Ground Beds
10
11
Applications
External Protection for Underground pipelines,
Above Ground Storage Tank Bottom etc
External Protection of offshore Structures etc.
Concrete Reinforcement Protection.
External protection of Oil & Gas Well Casings.
Internal Protection of pipelines & Storage Tanks
etc. (Non Hazardous, Conductive product)
Above Ground Pipeline Crossings below roads
etc.
12
Criteria for CP
-850mV with CP applied
100 mV Polarization
Net Current required – Bare or Uncoated &
critical places to measure Close Potential
(E&I Log, CPET for well casings)
Over Protection ( More than –1200mV )
13
Cathodic Protection Potentials
14
100 mV Potential Criteria
1400 1400
Polarized Potential Polarized Potential
1200 1200
1000 1000
> 100 mV
Potential (-mV)
Potential (-mV)
800 800
> 100 mV
600 Instant On 600
Instant Off
400 400
200 200
0 0
Time
Time
15
Current Density
( At 300 C, 25% Increase in Every 100 C )
Bare Surfaces
Coated Surface
17
ANODE JUNCTION BOX
POSITIVE CABLE
CONNECTION TO 10” SURFACE
NEGATIVE CABLE
ANODES
CONNECTION TO CASING
WELLHEAD
WATER LEVEL
5M
WELL CASING
10 ANODES
25 M
20 ANODES
51 M
CP Current
19
20
21
Typical Stray Current
Cathodically Protected
Section of Foreign Pipeline
Foreign Pipeline
Accelerated Corrosion
on Foreign Pipeline
Rectifier
Protected Pipeline
22
Potential Testing of Foreign
Structures
Use multimeter with 100 megohm input
impedance
Measurements taken with current cycled
on and off
Project criteria: +50 mV shift with
current applied
23
Interference Vs. Potential
Values
Negative potentials shifts on a foreign structure
with system “ON” indicates areas where the
current is collecting on the structure to the soil.
(No problem)
25
ADCO CP Project
26
Basic Design Philosophy
Protect 1 or 2 well clusters per CP system
Standardized system capacity at 15 amp / casing
(plus 5 amp for flow line)
20 year design life
Integrated system (no insulating devices)
Deep and surface groundbeds (50 amp max)
Ground beds positioned remote (150 m from
wellhead)
Use rectifier and solar power supplies
Extend 415 VAC power up to 500 meters
Use exiting CP equipment where possible
27
Limitations Of Cathodic
Protection In Oil & Gas Wells
Cathodic protection can only be applied to the external
surfaces of the conductor and outer casing.
28
Electrical Isolation
Integrated system selected
Casings and flow lines electrically continuous
Minimizes interference and balancing problems
Eliminates maintenance and current leakage
problems across insulators
29
CP Current Requirement
NACE RP0186 criteria: net flow of current to the
casing eliminates anodic areas
Data analysis:
Corrosion potential evaluation tool (CPET)
E-log I testing
Current density calculations
Current attenuation modeling
FEED recommended 15 amps per casing
5 amp allowed for flow lines
30
Corrosion Potential
Evaluation Tool (CPET)
Logging
Recommended in the FEED for project
Typically conducted during well work overs
Only way to determine down hole anodic and
cathodic areas on a casing (interference)
Tool includes 4 sets of 3 electrodes which make
contact with the casing
Potentials are measured between electrodes to
determine magnitude and direction of CP current
flow
Shah field is good candidate for CPET logging
31
CPET Tool and Logs
32
E-log-i Testing
-1,000
CASING SEGMENT DEPTH (FEET)
-2,000
-3,000
-4,000
-5,000
-6,000
-7,000
-8,000
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0 16.0
CURRENT (DC AMPERES)
-1,000
CASING SEGMENT DEPTH (FEET)
-2,000
-3,000
-4,000
-5,000
-6,000
-7,000
-8,000
0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2.00
9-5/8” casing
15 amp total current
35
Groundbed Details
Deep and surface groundbeds used
Located 150 to 200 meters from wellhead
20 year design life
25 or 50 amp rating
10 or 20 anodes per ground bed
Titanium / MMO anodes
Individual anode lead wires
Coke breeze backfill
Design circuit resistance: 0.25 - 0.60 ohm
36
Preferred Groundbed Location
-ANODE TO BE LOCATED 180 +/- 90
FROM FLOWLINE.
-ANODE TO BE POSTION 75M FROM
UNDERGROUND METALLIC OPTIMUM GROUNDBED
STRUCTURES LOCATION
S.
TR
0M
20
.
MT RS
15 0
.
FLOWLINE
90 MIN
90
37
Determining Borehole Depths
Drill Stem Resistance (ohms)
14.00
Megger
12.00
10.00
8.00
Resistance(ohms)
6.00
4.00
2.00
Drill Rig Wellhead 0.00
3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60
Depth (m)
40
41
Deep Anode Groundbed
Details
200 mm diameter borehole
30 to 100 meter depth
6 meter surface casing
Anodes installed in water
MMO anodes
Coke breeze backfill
25 mm dia vent pipe
Centralizers
42
Cross Section Of Deep Anode
Groundbed
43
Titanium / MMO Anodes
44
Coke Breeze Backfill
Used for surface and deep
anodes
98% carbon content
Small particle size
Lowers anode to earth
resistance
Promotes uniform current
discharge from anodes
45
Anode / Vent Pipe Loading
Anode
Centralizer
Tremmy Pipe
Vent Pipe
46
Deep Anode Installation Rig
Coke breeze mixing tank
Tremmy tube
“A” frame for lowering
anode assemblies
47
Coke Breeze Pumping Operation
Coke breeze mixed in slurry
Pumped from the bottom up
thru flexible PE pipe
48
Power Supplies
• Use existing power supplies when possible
50
Solar Power Supplies
52
Storage Batteries
Lead acid type
1680 amp-hr capacity
5 day autonomy
Housed in stainless steel
enclosure
53
Negative Connection To Well
Bracket for cable connection
Removed during work overs
54
Special Tools
Multimeter (digital high input impedance)
Cu/cuso4 reference electrode
Clamp on ammeter
Current interrupter
Variable resistor for dummy load
PC with software for data loggers
Test reel and test leads
55
Project CP Criteria
Primary
– 15 ampere per well casing per feed recommendations
Secondary
– 100 mV polarization shift
56
Assessment Of CP Current
To Casing
It = total current output of
power supply
Current to casing = it - is
57
Commissioning Activities
Pre-commissioning check list
Power supplies energize per manufacturers
recommendations
Set power supplies at desired current output
Allow casing and flow lines to polarize
Re-test after 24 hours (polarization shift)
Download data loggers
Investigate and mitigate interference
58
General Safety
The CP equipment presents various hazards that
can cause injury to personnel
59
PPE And Safety Equipment
Helmet
Eye protection
Steel tip boots
Rubber gloves (recommended by battery
manufacturer
60
Safety Hazards
Batteries present spark, burn and acid hazards
62
Testing
63
Routine Testing
Solar power supplies
Transformer rectifier power supplies
Adjustment of the DC output
Measure current to casings (dual sites)
Measure anode output currents
Remote on / off potential of well casing
Potential of flow line
Current measurement through flow lines
Down loading of date loggers (every 60 days)
64
AC Input Measurement Of
Rectifier
AC power measurements must
be done by qualified personnel
65
DC Current Output Of
Rectifier
DC current output of panel ammeter
can be verified by using:
Clamp on ammeter
Panel shunt
66
DC Voltage Output of
Rectifiers
Accuracy of the panel volt
meter can be determined
using a multimeter
67
Measure and Balance CP Current To Well Casings
(Dual Sites)
68
Tap Adjustment Of Rectifier
Fixed voltage type
Manual tap adjustments (25)
Course (A-E) and fine (1-5) tap for
each phase
Taps must be the same for each phase
Correct Tap increments of 4% - DC voltage
rating
1.2 volt for 30 volt units
2.4 volt for 60 volt units
Shock hazard – power off while
making adjustments
Wrong 69
General Components Solar
Power Supplies for CP
Solar Panels
Batteries
Controller
– Charge controller
– CP controller
70
Electronic Components Of
Solar Controller
MSRx array switch PCB assembly (input
power)
71
Solar Power Alarm Settings
Controller has 12 individual alarms
Regulator Fault (RF) will occur if any alarm is
activated
Low, high and load disconnect voltages are set
per manufacturer recommendation
Controller senses battery voltage and temperature
The CP alarm will be activated below a preset
current value
72
Controller Alarm LED’s
High voltage
Low voltage
Charge fault
Regulator fault
CP alarm
Fire alarm
Low voltage disconnect
74
Normal Operating Display
75
Shunt Ratings
76
Shunt Rating / Conversions
EQUIPMENT SHUNT RATING CONVERSION
60 V / 50 A Rectifier 60 amp / 50 mV 1 mV = 1.2 amp
30 V / 25 A Rectifier 30 amp / 50 mV 1 mV = 0.6 amp
Solar input array 100 amp / 60 mV 1 mV = 1.66 amp
Solar load 60 amp / 60 mV 1 mV = 1 amp
Anode Junction Box .01 ohm 10 mV = 1 amp
Current Control Box 50 amp / 50 mV 1 mV = 1 amp
77
Anode Current Measurements
Individual anode lead wires
terminated in anode j-box
78
Flowline Current Measurements
79
Interrupting Current Output of
Rectifier
Rectifier includes relay & contact to
interrupt DC output
Separate current interrupter required
Terminal strip on front panel allows
access to relay contacts
80
Sample Interference Test
Data
P/S Potential (mV)
Test Location Results
On Off Change
Foreign Pipeline 150 m
- 990 - 980 -10 No interference
from Groundbed
Flowline of well -1120 -1010 - 110 No interference
Earthing electrode
located 40 m from -550 -550 0 No interference
ground bed
Shallow water well
located 50 m from -640 -650 + 10 Little Interference
ground bed
81
Set-up and Down Loading of
Data Loggers
Rectifiers and solar power supplies provided with data
loggers
Specification requires that voltage and current be
monitored on regular basis
60 day storage required
Software for data loggers installed on ADCO pc’s
82
Data Logger on Rectifiers
83
Rectifier Data Logger Connection
84
Set-up of Rectifier Data Logger
85
Data Logger Set-up Window
(General)
Name: well no.
Password: N/A.
Company: ADCO.
Site address: power source
(cluster / RDS / ETC).
Description: CP configuration.
Communication type: (unique
no. Per next slide).
86
Communication Type Codes
(Unique 5 Digit No.)
First digit - area
– 1 = Sahil
– 2 = Asab
– 3 = shah
– 4 = Bab
– 5 = Buhasa
Second digit – well type
– 1 = water
– 2 = oil
– 3 = gas
– 4 = observation
Digits 3-5 – well number (123)
87
Data Logger Set-up Window
(Channel Tab)
89
Data Logger Set-up Window
(Recording Tab)
Sample Intervals: 1 / hour
Duration: Indefinite
Start Date: Actual (future)
Time: Actual
Type: “On”
Title: “One Hour Recordings”
Enable Channels: Tick 2 & 3
90
Down Loading Data Logger
(Status and Tools Window)
The relevant T/R is selected
from the “Site Selection”
91
Down Loading Data Logger
(Auto Report Window)
Click “options” button
opens Auto Reporting
Options Window
Memory: Transfer or
Transfer & Clear as desired
92
Generating Report
Choose “reports” file from CRM folder
Enter file name of report desired
– *.LAH for low average high report
– *.CSV for one hour recording report
Select and open file for desired site
Select “de-limited” for original data type
Tick “comma” as delimiter
Select “finish” to generate excel report
93
Sample Rectifier Data Logger
Report
RMU SYSTEM (by RCS)
SITE REPORT CUMULATIVE Title: , Interrupter: Idle, Type: On, Start: Scheduled, Transfer Time:
07/23/04 13:19
SITE NAME: Bb-123
COMMUNICATION No.: 6 Date Time , TS, S. Rate, 1(V DC), 2(V DC), 3(A DC),
COMPANY: ADCO
ADDRESS: Cluster 21 07/21/04 10:00:00, Y, 1 Hour(s), , 5.8800, 9.7980, ,
DESCRIPTION: , , , ,
94
Down Loading of Solar Power
Data Logger
Hardware connection is from lap-top com-port
via RS232 connector
Opening the BP-download software a window
will request site and operator name
Clicking the “download historical data” tab will
start the data transfer. The download data
window will open automatically after transfer
completion
95
Solar Power Data Logger
Connection
96
Download Menu
97
Sample Readout of Solar
Power Data Logger
Site: Bu191 Operator: Anis Downloaded: 29-Jul-2004 at 09:30
H
CP RC DI LV LV AY AY L F R C B T
yyyy-mm-dd hh:mm Mode BV Temp AI LI CP I V
V V S A D 1 2 C A F P S S
A
CP Interrupt
2004-07-29 9:25
Timer Stop
CP Interrupt
2004-07-29 9:21
Timer Start
98
Maintenance
99
Routine Maintenance
Visually inspect accessible equipment and make
repairs as necessary.
101
Problem of TR System
The problem of a AC powered CP system can be
into the following basic areas:
– AC power to rectifier
– DC output of power supply
– External CP cables
– Anode junction box
– Groundbed
– Structure
102
AC Power Problem
Check voltage of input
terminal of rectifier
If no voltage present,
problem is with the AC
power source
103
No DC Voltage
Use portable meter to confirm AC
power to rectifier
Use portable meter to confirm no
DC voltage
If AC exists but no DC voltage
present, problem lays within
rectifier
Check circuit breaker
Check DC fuses
Carry out T/R trouble shooting
procedures
104
DC Voltage But No DC
Current From T/R
Usually a problem with the
external DC circuit
Use dummy load to confirm
fault is external of T/R
Check negative connection at
wellhead
Check positive connection at
Anode J-Box
Conduct continuity test of
DC cables
105
Dummy Load Across Power
Supply
A portable resistor can be
used to simulate the external
CP load
106
Internal Transformer Rectifier
Problems
107
Isolate Problem Of Solar
System
The problem of a solar CP system can be isolated
into the following basic areas:
– Solar panels
– Controller
– Batteries
– External CP cables
– Anode junction box
– Groundbed
– Structure
108
Solar Panels
Minimum panel voltage is
17 volts
Two panels in series, 7/6
panel pairs in parallel form
two separate circuits
Current of individual panels
can be measured by short
circuit with amp.-Meter
109
General Problems With Solar
Controllers
Check for burned components
Check internal and external electrical
connections
Check fuses and breakers
Consult the manufacturers O & M manual
110
Solar Power Supply Schematic
ADCO - MSRx 2 SHU NTPCB
ASSEMBLY 40 0 912
19
J1
2 9
J1
TB1
24
O
P
/
12V
6 7
12 13
J3 J1
J1 J2
ASSEMBLY 400 848 ASSEMBLY 400 849
J1
J4 J2
TB1
J7 J6
J3
O
P
/
1
2V
J5
V
B
ATT H
G
I HV L
OWV C
HRG R
EG C
P R
EF
SE NS OR1
N
I P
U T
S
ENSE A
LARM A
LARM F
AULT F
AULT F
AULT C
ELL
22 23 20 21 14
1
MSRx FUSEPCB
ASSEMBLY 40 09 16
17
16
18 8
4 5 15 3
10 11
E1 E2 F2 E3
S
ENSE
112
Problems With Charge
Controller
Over charging
– Faulty control PCB
– Failure of sub-array switch PCB
– Faulty internal / external wiring
– Excessive charge voltage
Under charging
– Extended period of poor weather
– Faulty control PCB
– Faulty internal / external wiring
– Failure of sub-array switch PCB
– Excessive load consumption
113
Problems With CP Controller
No output
– Tripped breaker
– Faulty controller PCB
– Failure of power PCB
– Load disconnected due to low battery voltage
– Faulty internal / external wiring
No control of output
– Faulty controller PCB
– Short circuit of power board
– In correct control mode selection
114
Batteries
115
Anode With Low Output
Check cable connections in anode junction box
116
Open DC Output Circuit
Check negative cable connections at wellhead.
Check positive cable connection at anode junction
box
Conduct continuity test of negative and
positive cables
Install temporary above ground cable
Use cable locator to determine the position of
the break
117
High Circuit Resistance
Review operating history of systems to
establish trend
Check positive cable connection and anode lead
wires in anode junction box
Check negative cable connection to wellhead
Measure the output of each anode
Confirm integrity of DC cables
Follow NACE standards for RP0572-2001 for
watering ground bed
118