You are on page 1of 27

Sparkwest Steel

Industries
Limited

Capacity Requirement Planning

SSIL Planning Department 1


Sparkwest Steel
Industries
Limited

Defining Capacity
• Capacity is the amount of work that can be done in
a period of time
• It is usually stated in standard hours of work
• It must be determined at plant, department, and
work center levels.

SSIL Planning Department 2


Sparkwest Steel
Industries
Limited

Capacity Planning Process


• Determine the capacity available
• Translate the released and planned orders into
capacity required
• Sum up capacities required for each work center
• Resolve differences between available capacity
and required capacity

SSIL Planning Department 3


Sparkwest Steel
Industries
Limited
Determining Capacity Available
• Capacity available is the capability of a system or
resource to produce a quantity of output in a
particular time period.
• Available (theoretical) capacity can be calculated
or measured
• To calculate available capacity, one needs to know
– Available time
– Utilization
– Efficiency
SSIL Planning Department 4
Sparkwest Steel
Industries
Limited

Capacity Measurements

• Theoretical capacity
• Demonstrated capacity
• Calculated capacity

SSIL Planning Department 5


Sparkwest Steel
Industries
Limited

Utilization and Efficiency

Actual Hours Charged


Utilization =
Scheduled Available Hours

Standard Hours Earned


Efficiency =
Actual Hours Charged

SSIL Planning Department 6


Sparkwest Steel
Industries
Limited

Rated Capacity

Rated Capacity = Available time x Utilization x Efficiency

SSIL Planning Department 7


Sparkwest Steel
Industries
Limited
Load Sources
• Open Orders
• MRP - Planned Order Releases
• Other Sources
– Rework
– Excess scrap
– Quality problems

SSIL Planning Department 8


Routing Data

• Operation identification code


• Operation description
• Planned work center
• Standard setup time
• Standard run time per unit
• Tooling requirements

MGT 651 - IV DR. OZATALAY 9


Lead-Time Elements
• Queue
– time waiting before operation begins
• Setup
– time getting ready for operation
• Run
– time performing operation
• Wait
– time waiting after operation ends
• Move
– time physically moving between operations

MGT 651 - IV DR. OZATALAY 10


Adjustments to Capacity or Load
• Increasing Capacity
– Add extra shifts
– Schedule overtime or weekends
– Add equipment and/or personnel
• Reducing Load
– Subcontract work to outside suppliers
– Reduce lot sizes
– Hold work in production control
– Reduce the MPS
• Reducing Capacity
– Eliminate shifts or reduce length of shifts worked
– Reassign personnel temporarily

MGT 651 - IV DR. OZATALAY 11


Continued
• Increasing Load
– Make items normally purchased or subcontracted
– Release orders early
– Increase lot sizes
– Increase the MPS
• Redistributing the Load
– Use alternate work centers
– Use alternate routings
– Adjust operation start dates forward or backward in time
– Revise the MPS

MGT 651 - IV DR. OZATALAY 12


Production Activity Control

MGT 651 - IV DR. OZATALAY 13


Objectives of PAC

• Execute the MPS and MRP


• Optimize use of resources
• Minimize work in process
• Maintain customer service

MGT 651 - IV DR. OZATALAY 14


PAC Functions
• Plan
– Ensure resources available
– Schedule start and completion dates
• Execute
– Gather relevant shop order information
– Release shop orders
• Control
– Establish and maintain order priority
– Track actual performance
– Monitor and control WIP, lead times, and queues
– Report work center performance

MGT 651 - IV DR. OZATALAY 15


Data Requirements

• What and how many to produce?


• When parts are needed?
• What operations are needed?
• How much time operations will take?
• How much capacity is available at each work
center?

MGT 651 - IV DR. OZATALAY 16


Scheduling

• Objectives
– Meet delivery dates
– Effectively use manufacturing resources
• Involves
– Establishing start and finish dates for each operation
needed to complete an order

MGT 651 - IV DR. OZATALAY 17


Scheduling and Loading Techniques

• Forward scheduling:
– Activity starts as soon as the order is received .regardless of due
date
• Backward scheduling
– Activities are scheduled back from the due date
• Infinite loading
– Assumes capacity is infinite at any work center
• Finite loading
– Assumes there is a definite limit to capacity at any work center

MGT 651 - IV DR. OZATALAY 18


Bottlenecks Management

• Bottlenecks control the throughput of all products


processed by them
• Work centers feeding bottlenecks should be scheduled at
the rate the bottlenecks can process
• A time buffer inventory should be established before the
bottleneck
• Work centers fed by the bottleneck have their throughput
controlled by the bottleneck

MGT 651 - IV DR. OZATALAY 19


Input/Output Analysis

MGT 651 - IV DR. OZATALAY 20


Input, Output, Queue, and Capacity

Input Input Input

Queue

Capacity

MGT 651 - IV DR. OZATALAY 21


Actual Output Less Than Planned Output

Input Input Input

Not enough input?


Queue
Queues and lead
times increase

Capacity Insufficient Capacity?

MGT 651 - IV DR. OZATALAY 22


Actual Input Less Than Planned Output

Input Input Input

Feeding work centers


Queue
behind schedule

Work released late


May run out of work
Capacity Late orders
MGT 651 - IV DR. OZATALAY 23
Actual Output Greater Than Planned Output

Input Input Input

Queue

Excess Capacity
May run out of work
Capacity

MGT 651 - IV DR. OZATALAY 24


Actual Input Greater Than Planned Input

Input Input Input

Queue Feeding work centers


ahead of schedule

Work released early


Capacity
Queues and lead times
MGT 651 - IV DR. OZATALAY will increase 25
Actual Output Less than Actual Input

Input Input Input

Queue
Preceding work centers
Queues and lead times increase ahead

Not enough capacity? Capacity Releases early

MGT 651 - IV DR. OZATALAY 26


Actual Output greater Than Actual Input

Input Input Input

Queue Feeding centers behind

Releases late
May run out of work
Idle capacity
Capacity
Late orders
MGT 651 - IV DR. OZATALAY 27

You might also like