Professional Documents
Culture Documents
PERT-CPM
Sample Problem
A project consists of the following activities and estimated times as shown below.
a. Construct a network diagram
b. Determine the project completion time and critical path
Activity I. Predecessor Optimistic Time Most Probable Pessimistic Time Expected Time
(To) Time (Tm) (Tp) (Te)
A - 5 6 18 8
B A 8 8 19 10
C A,B 3 5 12 6
D B,C 6 9 14 9
E D 3 4 10 5
F E 3 3 9 4
B 10 7 3 3,000
C 6 2 4 6,000
D 9 6 3 1.000
E 5 3 2 6,000
F 4 1 3 2,000
Path n=0 1 2 3 4 5
A-B-D-E-F 36 35 34 33 32 31
A-B-C-D-E-F 42 41 40 39 38 37
A-C-D-E-F 32 31 30 29 28 27
Activity Crashed D D D F F
The activity to crash in day 1 is D because it has the lowest cost to crash. It can also be crashed for 3 days
so it is still the lowest activity to crash for day 2 and 3. Deduct one day from the base time (n=0) whenever
the activity to crashed is among the activities in the path.