Professional Documents
Culture Documents
MANAGEMENT
Ilija Stojanović, Ph.D., PMP
WBS -example
Cost estimation tools and techniques
• Analogous estimates: use the actual cost of a previous, similar project as the basis for estimating
the cost of the current project
• Bottom-up estimates: involve estimating individual work items or activities and summing them
to get a project total
9
Activity Optimistic Pessimistic Most likely Three point estimation
A Excavate
Excercize:
• Try at home: Beta Distribution (from the traditional PERT technique).
Triangular Distribution
tE = (tO + 4tM + tP) /6
tE = (tO + tM + tP) / 3
• Tangible costs or benefits are those costs or benefits
that an organization can easily measure in dollars or
otgher currency
Types of costs • Direct costs are costs that can be directly related to
and benefits producing the products and services of the project
Management
Management reserves
reserves
(unknown
(unknown risks)
risks)
500 USD
500 USD
COST
COST BASELINE
BASELINE PM
8250
8250 USD
USD
Contingency
Contingency reserves
reserves
(known
(known risks)
risks)
750
750 USD
USD
Cost
Cost of
of the
the project
project
7500
7500 USD
USD
CA
CA 11 CA
CA 22
4500
4500 USD
USD 3000
3000 USD
USD
WP
WP 11 WP
WP 22 WP
WP 33
1500
1500 USD
USD 3000
3000 USD
USD 3000
3000 USD
USD
Activity
Activity 11 Activity
Activity 22 Activity
Activity 33 Activity
Activity 44 Activity
Activity 55
500
500 USD
USD 1000
1000 USD
USD 3000
3000 USD
USD 1000
1000 USD
USD 2000
2000 USD
USD
Cost baseline
• EVM is a project performance measurement technique that
integrates scope, time, and cost data
Earned • The planned value (PV), formerly called the budgeted cost of
work scheduled (BCWS), also called the budget, is that portion
Value of the approved total cost estimate planned to be spent on an
activity during a given period
Managemen
t (EVM) • Actual cost (AC), formerly called actual cost of work performed
(ACWP), is the total of direct and indirect costs incurred in
accomplishing work on an activity during a given period
• EV>PV
• AC>PV
• AC>EV
Example 2
• EV>PV
• AC<PV
Example 3
• EV<PV
• EC<PV
Monitoring your
project using
Earned Value
Management
Example
• You are managing a software project with an initial budget estimate of 2 million USD.
During interim cost and schedule performance analysis, you figured out that:
• You should have spent $500,000 till now based on your initial plans and 1,000 man/days of
schedule activities
• You spent $600,000 till now and completed 1,100 man/days of schedule activities which
should have cost $450,000 based on your initial plans.
• You re-estimated the budget required for the remaining work to be done as $1,500,000.
• BAC (Budget at Completion)= 2 million USD ("initial budget estimate of 2 million USD" referred in the
scenario)
• PV (Planned Value) = $500,000 for cost related EVM calculations, ("You should have spent $500,000 till
now based on your initial plans)
• PV=1,000 man/days for schedule related EVM calculations ("You should have spent 1,000 man/days of
schedule activities" )
• AC (Actual Cost) = $600,000 ("You spent $600,000 till now" referred in the scenario)
• EV (Earned Value)= 1,100 man/days for schedule related EVM calculations,
• EV = $450,000 for cost related EVM calculations.
("completed 1100 man/days of schedule activities which should have cost $450,000 based on your initial
plans" referred in the scenario)
• ETC (Estimate to Complete) = $1.5 million USD ("You re-estimated the budget required for the remaining
work to be done as 1,500,000." referred in the scenario)
Earned Value Formulas
• BAC (Budget at Completion)= 2 million USD ("initial budget estimate of 2 million USD" referred in the
scenario)
• PV (Planned Value) = $500,000 for cost related EVM calculations, ("You should have spent $500,000
till now based on your initial plans)
• PV=1,000 man/days for schedule related EVM calculations ("You should have spent 1,000 man/days
of schedule activities" )
• AC (Actual Cost) = $600,000 ("You spent $600,000 till now" referred in the scenario)
• EV (Earned Value)= 1,100 man/days for schedule related EVM calculations,
• EV = $450,000 for cost related EVM calculations.
("completed 1100 man/days of schedule activities which should have cost $450,000 based on your initial
plans" referred in the scenario)
• ETC (Estimate to Complete) = $1.5 million USD ("You re-estimated the budget required for the
remaining work to be done as 1,500,000." referred in the scenario)
• EV>PV
• AC>PV
• AC>EV