Professional Documents
Culture Documents
Chapiter 2 Project Planning
Chapiter 2 Project Planning
Project planning
Project planning
Planning tools
Risk management plan • Identifying and setting up a plan for managing risks
• Identifying the material resources need and howto
Procurement plan acquire them
• Identifying stakeholders and planning to ensure their
Stakeholders mgt plan
support or reduce their negative impact
Project planning
The Work Break Down Structure (WBS) is a mean to organise work into tasks and subtasks
s/task1 s/task2
Project planning
Time estimation
3. Adjust accordin to the profile of the person in charge ( a new employee will make much
more time than an expert)
4. Leran from previous projects.
Time estimation
• Project duration is the sum of the duration its different actions
• Tasks durations must be estimated with a reasonable precision
Project scheduling
Project planning
3 E 4
Chaque tâche est suivie et précédée par une étape
X Y 6 9
5
A,2 2 C,4
4 E,1 5
1
B,3 3 D,2
Project planning
A,2 2 C,4
2
4 E,1 5
6 7
0
B,3 3 D,2
3
A,2 2 C,4
2 2
1 4 E,1 5
6 6 77
0 0
B,3 3 D,2
3 4
Duration
Activity Title Predecessor
(days)
A Plan the process 5
B Move in equipments 9 A
C Order materials 6 A
D Clean site 10 B
E Move in materials 2 C
F Set up on-site lightning 5 D
G Build on-site temporary facilities 6 B,E
H Excavate 8 F,G
Project planning
Float (slack time) : Delays that tasks can take without impacting
the overall project duration (without delaying the project).
A,2 2 C,4
2 2
4 E,1 5
6 6 77
0 0
B,3 3 D,2
3 4
Task float= End date of a task - task duration – start date of previous task
Activity End date Duration Start date of Float
previous task
Activities B and D can
A 2 2 0 0
start with a one day
B 4 3 0 1
delay without impacting
C 6 4 2 0 the overall project
D 6 2 3 1 duration
E 7 1 6 0
Project planning
A,2 2 C,4
2 2
4 E,1 5
6 6 77
0 0
B,3 3 D,2
3 4
Case study: In order to respond to the growing market needs and boost its market
shares, the CEO of an organisation performing in the production of milk, decided on
setting up a new production unit.
The project encompasses going through 9 main activities ranging from acquiring the
facility to equipement. The activities are listed below
C,3 9 9
D,4
6 6 16 16
A,6 E,1
F,7 I,4
9 9
B,2 20 20
0 0
H,3
G,2
6 15 8 17
PERT DIAGRAM: La duréeProject
du projet
planning
Float calculation
Activity Float
A 6-6-0 0
B 15-2-0 13
C 9-3-6 0
D 16-4-9 3
E 9-1-6 1
F 16-7-9 0
G 17-2-6 9
H 20-3-8 9
I 20-4-16 0
Critical path A C F I
Project planning
Project timeline
Project planning
A Gantt Chart is a timeline that is used as a project management tool to illustrate how
the project will run.
it shows
- individual tasks,
- their durations and
- the sequencing of these tasks
- the overall timeline of the project and
- the expected completion date.
Task A
Task B Activities
prroject
Task C
Task D
Task E
Time
Project planning
Each task is represented by an horizontal bar, showing the tasks begin and end
(task duration)
This chart allows to see in a glipmse
•Overlapping tasks
Resource planning
Project planning
.
Project planning
- Consider
- Technical requirements of the project
- Team competencies
- Availability of resources
- Critical resources
- Draw an OBS and a Responsibility Matrix
Project planning
Risk= An event that may occur during the life cycle of the project
and may impact negatively this project
Risk, in itself, isn’t bad, it’s the miscalculation of risk, or the non-
calculation of risk that’s bad
Communi
cation
Project planning
• Clients
Marketing and • Suppliers
commercial risks • Competitors’ offers
• Regulations
Legal risks • Contractual risk
• Dispute risks,….
• Escalation of prices
Financial risks • Poor cost estimation
• Earthquakes, windstorms,
Natural risks
sandtorms, …
• Electrical gazards
Safety risks • Height, ladders
• Extreme temperatures,, …
Environnemental • Hazard of pollution,
risks • Gaz emissions, ….…
Project planning
Risk matrix
Project planning
- Risk mitigation: Lessening the effect of threat. ex: Training employees – using
backups of info - late penalties in contracts - insurance
Identify the risks, their impact, their likelihood of appearance in a risk matrix and draw
a mitigating plan for each risk
On 14 April 1912 RMS Titanic sank with the loss of 1500 lives…
E J Smith