Professional Documents
Culture Documents
1
Introduction:
Evaluation and Award are most important but often
controversial matters
Bid is a price and conditions at which a bidder intend to
buy at any given time
Bidder main target is to maximize the profit while
remaining lowest among other competitors and
minimize the risk .
Type of bidding – ICB, NCB, SSB (Single Source)
Tender and bid are used in the same meaning
Continue… 2
Types of Biddings:
Single Stage– Single Envelope
Single Stage– Two Envelopes
Two Stage – Single Envelope
Two Stage – Two Envelopes
4
Parameters:
Presentation limited to procurement of goods and works
Process commences upon receipt of bids
Process to end after Award
PEC documents:
Standard Procedure for Evaluation
Instructions to Bidders for Civil Works Documents
Instructions to Bidders for E&M Works Documents
Instructions to Bidders for Smaller Works Documents
PPRA Rules 2004
Construction bye-laws
5
Priority of Documents
for Evaluation :
Provisions stated in the Bidding Documents
In absence – relevant provision in PEC Act, bye-laws,
procedure
Bidding Documents can not be prepared in contradiction to
statute laws & relevant PEC framework bidding documents
and bye-laws
Priority of PEC Documents:
Act
Relevant Bye-laws
Continue… 6
Framework Bidding Documents
Procedure (Guidelines)
7
General
Principles :
Evaluation shall be based on explicit provisions in the
Bidding Documents
In case deficient, ambiguous provisions; PEC
documents and International Practices to follow
(FIDIC)
Three bids requirement is a convention and an
inference from Section 42 of PPRA Rules 2004
Members of Committee for adjudication of evaluation
must be engineers
Continue… 8
Instructions to users of PEC documents are of legal
value as rules
Besides required knowledge, evaluators must have
moral integrity, impartiality and should work on good
faith
Non-transparent evaluation and award results:
Lack of interest by bidders at large
Foreign bidders hesitate to invest
Less competition increased cost, more time for project
completion
9
Area of Disputed
Opinion :
Substantial responsiveness
Arithmetic corrections
Price Adjustments of acceptable deviations (Loadings)
Long list of unresolved issues/ queries
Pre-award negotiations/ clarifications
Domestic Preference
Conditional acceptance (LOCA, LOA)
Award to Lowest Bidder
10
Getting Ready for
Evaluation :
Evaluation team comprising relevant professionals
Preferably team members should be from among those
preparing Bidding Documents
Necessary checklists, formats specific to the Bidding
Documents are ready
Bid opening materials received:
Copies of bids verified with originals
Signed statements of the bid opening committee
members ( Attendance sheet, Valid Bid Security etc.)
Instructions to proceed with evaluation with schedule
ISO-9001Process and Quality Plan for evaluation 11
Conformance to Bidder Requirements
(Commercial):
Sr. Clause no. of Description Specified Bidder A Bidder B Bidder C
No. “Instructions Requirement (1) (2) (3)
to Bidders"
1 2.1 Prequalification of Whether the Bidder is C C C
Bidders pre-qualified
2 2.1 Eligibility of Bidders - Registered with PEC C1 C1 NC1
C: Conformance NC: Non Conformance S: Submitted NS: Not submitted NA: Not applicable
12
Example of Note Against Table:
Bidder A
C1:As required under the provisions of Sub-Clause 2.1 of
Instructions to Bidders (IB), PEC license valid for the year 2005
has been provided for Siemens Pakistan only, whereas, Bidder
has only provided Enlistment Certificate for Siemens AG,
Germany.
Continue… 13
C3:Bid – Schedule A Price Schedule is initialed by a
person for whom no Power of Attorney is available with
the Bid. In response to post bid query, Bidder provided
Power of Attorney of required person.
Discounts, if any
17
Preliminary
Examination:
Pertains to Verification, Eligibility, Bid Security and
Completeness of Bid
Eligibility of Bidders:
Have valid PEC License
Pre-qualification/ enlistment with Employer
From eligible countries
Qualification of Bidders:
Capacity to work & minimum years of work experience
From eligible source country
Continue… 18
Average Annual turn over in last five years equal to
or more than the Bid price
Adequate funding facility/line of credit
If foreign bidder; Notarized Joint venture agreement
with Local Contractor/ firm
Written power of Attorney for the signatory
Availability of minimum required skilled/ unskilled
manpower and critical construction equipment
Continue… 19
Joint Venture Agreement, in case the bidder is a J/V
J/V partners must satisfy experience requirement as
described in Bidding Documents
Properly signed by the authorized person(s) and the
authorization is bona-fide and available
Any other items, provided in the Bidding Documents due
to its peculiarity
Documents comprising the Bid are accompanied, duly
signed and stamped
Accompanied Bid Securities:
Amount is adequate and rightly written in the prescribed form
Continue… 20
From Scheduled Bank/ Insurance in Pakistan
Original Security
Continue… 21
Post – Bid Queries in writing
Continue… 24
Arithmetic Corrections:
Check for the substantially responsive bids
25
Detailed Evaluation
of Bids:
Correction for Prices:
Read-out total bid prices excluding provisional sums and
discounts
Corrected total bid price (discount +arithmetic
corrections)
Corrected price converted to single currency
Continue… 26
Computations & rates to be part of Bid Evaluation
Report:
Exchange Rate used will be 28 days prior to the
date of Bid submission for evaluation
Price Adjustments for Technical Compliance
Continue… 27
Domestic Preference (E&M):
For Civil Works – no preference
Continue… 28
Computation for Domestic Preference:
Domestic Goods (Value added in Pakistan)
[Bidders claiming eligibility for domestic preference should fill in for supply items only, all columns
hereunder and provide necessary documentation to substantiate their claim]
Domestic value
Total Price of added in the Amount of value
Sr. Description of
Goods Ex-Factory manufacturing addition
Indigenous Unit Qty
No. cost as
Goods (Pak Rs.) (Pak Rs.)
percentage of Ex-
Factory Price
1 2 3 4 5 6 7
Computations:
A. Total amount of Value Addition (from Col.7) Rs________
B. Total Ex-Factory Price of Indigenous Goods (from Col.5) Rs________
C. Total DDP Price of imported supply items Rs________
D. Total Price of supply items [B+C] Rs ________
E. % of value addition = [(A/D)x100] ________ %
F. Domestic Preference =(15,20 or 25)% of B Rs________
Continue… 29
Detailed Evaluation
of Bids:
Price adjustments (Loading):
For evaluation purpose only
Only against stated provisions
Completeness – included in other items
Missing items – competitor’s average price
Technical compliance – highest price of bidders
Completion Schedule
Commercial Compliance Prima Facie situation
Other deviations
Continue… 30
Read-Out Total Bid Prices and Discount:
Tender
Sr. Read-Out Tender Price Discount Security Discounted Tender Price
No. F.C.C. *L.C.C. Offered Provided F.C.C. L.C.C.
Tenderer's
Name
31
Corrected Total Bid Price
Converted to Single Currency:
Sr. Corrected Total Tender Price Corrected Total Tender
No. Tenderer’s (Ref. Table 3-1) Price Excluding
Name Provisional Sums
Eq.PKR
FCC L.C.C
EURO USD PKR
32
Computation of Evaluated Bid Prices:
Sr. Bidder A Bidder B Bidder C
No. Description
FCC LCC Total FCC LCC Total FCC LCC Total
EURO Pak. Rs. Eq.Pak. EURO Pak. Rs. Eq.Pak. Rs. EURO Pak. Rs. Eq.Pak. Rs.
Rs.
1 Corrected 44,091,683 468,097,715 3,635,196,122 45,947,000 692,744,640 3,993,117,650 44,129,577 757,999,734 3,927,827,245
Total Tender
Price
(Excluding
Provisional
Sums) Ref.
Table 3.3)
2 Price - - - - - - -
Adjustment
for
Technical
3 Price - - - - - - -
Adjustment
for
Commercial
Compliance
(Ref. Table
5.1)
33
Award of Contract:
(b)Competence
(c)Performance
(d)Financial
Continue… 35
No negotiations but clarifications on outstanding items
in Bid Evaluation Report
Conditional Acceptance (LOCA) by bidder is not
tenable under Section 7 of Contract Act 1872
Letter of Acceptance (LOA) or LOCA to be issued
prior to expiration of Bid validity period
Upon receipt of Performance Security, employer will
notify others and return their bid securities
Failure to furnish Performance Security within 28 days
of LOA may annul the contract and forfeit the bid
security
36
37
Main Phases of Construction
38
39
Different Types of Construction Contracts
on the Basis of Pricing Strategy:
Lump Sum or Fixed Price Contract
Continue… 41
Cost Plus Fixed Fee Contract
Continue… 42
Cost Plus Variable Percentage Contract
43
Different Types of Construction Contracts
on the Basis of Contracting Strategy:
BOO (Build Own Operate)
Continue… 44
BOOT (Build Own Operate Transfer)
Continue… 45
BOT (Build Operate Transfer)
Continue… 46
BOT (Build Operate Transfer)
Continue… 47
Design & Build
Continue… 48
EPC (Engineering, Procurement &
Construction)
Continue… 49
50
EPCC (Engineering, Procurement,
Construction & Commissioning)
52
Which FIDIC Contract Should I Use?
53
Remember…