Professional Documents
Culture Documents
Gourav Vallabh
XLRI
Jamshedpur
Evaluation Techniques
Estimated Life 5 5
Estimated Salvage 3000 3000
Pay Back Method
How many years will it take for the cash
benefits to pay the original cost of an
investment.
There are 2 ways of calculating the PB
period:
1. When the cash flow stream is in the nature of Annuity
2. When the cash flows are not uniform, In such case, PB
is calculated by the process of cumulating cash flows till
the time when the cumulative cash flows become equal
to the original investment outlay
Problem
Calculate Pay Back Period if the Cost of
Project is 60000
2 16000 20000
3 18000 18000
4 20000 16000
5 25000 17000
The Naïve rate of return
When a manager who relies on the
payback criterion speaks of rate of
return, this normally refers to
something other than time-adjusted
return on investment.
Naïve rate of return = 1/Payback (in years)
Unrecovered Investment
A concept related to payback, but
taking the time-value of money into
account, is unrecovered investment.
It suggests that how long it will take for
the firm to recover its investment in the
project plus the cost of the funds
committed to the project.
Comprehensive Example
Now -1000
were perfect.
Income Taxes, NPV and
wealth creation – Example
Assume that for B Ltd., applicable tax
rate is 40% and depreciation allowable
is Rs 900 and Rs 600 in year 1 and year
2 respectively.
Solution
After tax cash flows from (1500) 1080 720
investment
PV of remaining cash flows 1576.8 654.5 0
of WACC ie 10%
Debt 788.43 327.2 0
Borrow (Repay) 788.43 (461.1) (327.2)
Cash Flow to (from) equity (711.5) 571.55 373.08
NPV @ 14% = 76.86
Overall Conclusion
Conceptually Superior.
Takes into consideration the entire period of the
project life and time value of money.
Consistent with the basic valuation model.
Favors early cash flows over later ones.
$35,000.00
$30,000.00
$25,000.00
$20,000.00
$15,000.00 NPV
$0.00
($5,000.00)
Discount Rate
IRR diagram concave from above and below
X= R / (1+d)
t
t = R (1+d) t
-t ---------------------- (1)
t=0 t=0
N N
X (1+d)N = R / (1+d)
t
t-N = R (1+d)
t
N-t ---- (2)
t=0 t=0
cont……
For the initial outlay this may be interpreted
as the opportunity cost of committing funds to
this project in which rate d could be earned.
Or in the case where d= K the opportunity
cost may arise from the decision to undertake
a project requiring funds to be raised where
as without the project no new funds would
need to be raised.
The implication of future value formulation is
that the project return whether by IRR or by
NPV will depend on the rate at which cash
flows can be reinvested.
Let us now consider the IRR and reinvestment rate in
another light.
From the point of view of borrower of money cash
flows are identical as that of lender of money except
that the signs are reversed.
The pre tax return to the lender cannot be less than
cost to the borrower even if the lender reinvest it or
not.
The return is measured as a time adjusted
percentage of the principal amount outstanding and
is independent of what disposition is made of the
cash flows as they are received.
Although the yield on the funds originally invested
may be increased by such uses, it cannot be reduced
by lack of such investment opportunities.
cont……
Problem
IRR IS 20%
Problem
IRR IS 20%
Problem (per period return on remaining principal on
t Principal % return
remaining
1 100000 13.438
2 80000 16.798
3 60000 22.397
4 40000 33.595
5 20000 67.190
IRR IS 20%
The IRR is thus a minimum return on the
loan, and this minimum is independent of
investment opportunities.
Percentage return on an investment does not
depend on the available reinvestment rate.
The actual gain to the lender may, of course,
be higher than this minimum amount if the
available reinvestment rate is greater than
zero, but that is condition external to the
investment.
The IRR is concerned with the internal
characteristic only and therefore provides a
measure of the minimum return on the
investment.
To conclude the conceptual difficulty
with the reinvestment rate assumption
arises from focusing on the superficial
aspects of the mathematics of IRR while
neglecting the economic interpretation
of the initial investment and the
subsequent cash flows.
Adjusted or Modified IRR
Investment 1000
$600
$500(1.15)
$575
$400(1.15)2 $529
$300(1.15)3 $456
0= R (1+r)
t
-t -------------------------- (1)
t=0
N
NPV = R (1+k)
t
-t -------------------------- (2)
t=0
Subtract (1) from (2)
N
this project?
If your cost of capital is 12.32%, would you
Explain.
Profitability Index (PI)
/I
t
(1 k )
o
t 1 t
Year 0 1 2 3 4
Cash Flow -1,000 500 -2,000 2,000 2,000
-1,818
-1,318
-1,198
INITIAL COMMITMENT 2,198
670
MPI 1
2,198
If the only question is whether the benefit
exceed the cost, the 2 profitability indexes
give the same signal. Both will be greater
than 1.0 when the NPV is positive.
If PI is used to discuss the degree of
attractiveness, then the two measures are
substantially different.
Contd.
264.5
PV PBP 2 2.35 years
751.30