Professional Documents
Culture Documents
Management
4th
Lecture
Approximation
3
Estimate Cost Process
Figure 7-4. Estimates Cost : Input, Tools & Techniques, and Outputs 4
Project
Estimate Cost Process
Management Plan
7.2
Estimate
Project Costs Project
Documents Documents
Project documents
● Lesson learned register
● Project schedule
● Resource requirements Project documents updates
● Risk register ● Assumption log
● Lesson learned register
Enterprise / ● Risk register
Organization
● Enterprise environmental factors
● Organizational process assets
• Market condition
• Published commercial information
• Exchange rates and inflation
7.2.1.4 Organizational Process Assets
The organizational process assets that can influence the Estimate Costs process
include but are not limited to:
7
7.2.2 Estimate Cost: Tools and Techniques
7.2.2.1 Experts Judgment
8
7.2.2 Estimate Cost: Tools and Techniques
7.2.2.5 Three-Point Estimating
Described in Section 6.4.2.4. The accuracy of single-point cost estimates may be
improved by considering estimation uncertainty and risk and using three estimates to
define an approximate range for an activity’s cost:
• Most likely (cM). The cost of the activity, based on realistic effort
assessment for the required work any predicted expenses.
• Optimistic (c0). The cost based on analysis of the best-case scenario for
the activity.
• Pessimistic (cP). The cost based on analysis of the best-case scenario for
the activity.
Depending on the assumed distribution of values within the range of the three
estimates, the expected cost, cE, can be calculated using a formula. Two
commonly used formulas are triangular and beta distributions. The formulas are:
• Pessimistic (cP). cE = (c0 + cM + cP) /3
• Beta distribution. cE = (c0 + 4cM + cP) /6
9
7.2.2 Estimate Cost: Tools and Techniques
7.2.2.6 Data Analysis
• Alternatives analysis.
• Reserve analysis.
• Cost of quality.
10
7.2.3 Estimate Cost: Out Puts
7.2.3.1 Cost Estimates
• Assumption log.
• Lesson learned register.
• Risk register.
11
Estimate Cost Input Project Schedule
14
Thank You