Professional Documents
Culture Documents
Allocating Resources
to the Project
zahid
Managing Resources
CPM is NOT actually a resource allocation method.
Time is viewed as a resource.
Trade-offs between time and other resources are major
problems in resource management.
ADM/PERT and PDM/CPM are there to estimate activity
times under the assumptions of resource loading that are
assumed as ‘normal practice’.
Careful planning is required while expediting (CRASHING)
the project.
Difficulties notwithstanding, the PM must remain prepared
Critical Path Method—Crashing a Project
Time and cost are interrelated
The faster an activity is completed, the more
it costs
Change the schedule and you change the
budget
Thus many activities can be speeded up by
spending more money
zahid
What is Crashing?
To speed up, or expedite, a project
Of course, the resources to do this must be available
Crashing a project changes the schedule for all
activities
This will have an impact on schedules for all the
subcontractors
Crash Cost --
In CPM, an activity can be conducted at a normal pace or
at an expedited pace, known as crashing, at a greater cost
zahid
Activity Slope
zahid
An Example of Two-Time CPM
zahid
table_09_01
Activity Slopes
Cost per Period for Crashing
zahid
Crashing the Project
zahid
Seven Day Schedule
zahid
Six Day Schedule
zahid
Five Day Schedule
zahid
Four Day Schedule
zahid
fig_09_01
Cost-Crash Curve
zahid
Other Methods of Crashing
Rush& Blitz
Mostly to deal with optimal utilization of resources with a
view to hasten the completion of linked activities. For
details refer to Table 9-3
Fast Track
Usually related to construction project. Activities can
commence concurrently. In this process design and build
phases of the project usually overlap each other. This is a
time saving technique. It entails detailed planning coupled
with intimate supervision and acute involvement of PM.
unfig_09_01 Solve the problem
Find the lowest cost to complete
the project in 10 days
unfig_09_02
Answer
# Current time and cost: 12 days and $ 210
# Cut e two days at a cost of 60 thus project cost would be $ 270
The Resource Allocation Problem
As discussed, CPM/PERT ignore resource utilization
and availability
With external resources, this may not be a problem
It is, however, a concern with internal resources
Schedules need to be evaluated in terms of both time
and resources
zahid
Resource Allocation
It is common to see the resource allocation problem
in terms of manpower, but it can apply to equipment
and capital as well
zahid
Resource Loading
Resource loading describes the amount of
resources an existing schedule requires
Gives an understanding of the demands a
project will make of a firm’s resources
zahid
Example – Resource Loading
fig_09_04
fig_09_05
Resource A
zahid
Resource B
zahid
fig_09_06
Resource Leveling
Less hands-on management is required
May be able to use just-in-time inventory
Improves morale
Fewer personnel problems
zahid
fig_09_07
Resource Leveling Continued
zahid
Constrained Resource Scheduling
zahid
Common Priority Rules
As soon as possible
As late as possible
Shortest task first
Most resources first
Minimum slack first
Most critical followers
Most successors
Arbitrary
zahid
Heuristic Methods
As soon as possible --- General solution for CP and time
As Late as Possible --- To defer cash outflows as long as
possible
Shortest Tasks Firsts --- Tasks are ordered in terms of duration
Most Resources First --- Important tasks first since they
demand equally important resources
Minimum slack first --- Opposite of shortest tasks firsts. By far the best. Generally
resulting in minimum schedule slippage, minimum resource
idle time, and minimum in-process inventory
Most Critical Followers -- The ones with the greatest number of
critical followers
Most Successors --- Same as most critical followers
Arbitrary --- Locally adopted rules
Optimization Methods
Finds the one best solution
Uses either linear programming or
enumeration
Not all projects can be optimized
Approaches only work with small to medium
projects
zahid
Multi-Project Scheduling and Resource
Allocation
Scheduling and resource allocation problems increase with
more than one project
The greater the number of projects, the greater the problems
One way is to consider each project as part of a much larger
project
However, different projects have different goals so combining
may not make sense
zahid