You are on page 1of 3

What are Crashing and Fast Tracking?

Schedule Compression

I have been involved in the ‘Recovery Plan’ submissions. A recovery plan is where
we do schedule compression without changing or extending the Project Finish Date.

We use Crashing & Fast Tracking for schedule compression. In crashing, we use
more resources, and in fast-tracking, we do more activities in parallel, increasing the
project risks.
The project planner is the one who does this and as a planner, always make sure to
use any technique with the consent of your project manager and the project
management team. Team buy-in is the key to managing a successful project.
We will discuss in detail which technique to use when & where.

Why Schedule Compression?


It is typical for a project to lag behind the baseline schedule and be project
management professionals; you need to deal with it. Make sure a schedule
compression can be done at any stage of the project. Like when we submit
a baseline schedule, and the client/owner can ask to compress it.
A recovery plan can be submitted during the project execution phase, where we are
left behind the project schedule. Never compromise on agreed timelines unless there
is any scope change. Schedule compression mainly covers two techniques;
1. Fast Tracking
2. Crashing

Fast Tracking
You need to be an experienced person to use fast-tracking. You need to find
activities only where you can apply fast-tracking first. Make sure that all the
resources are optimized well.

We say that activities are done simultaneously without waiting for the completion of
other activities.

Remember, this technique can’t be applied to every activity; we’ll have to see &
discuss with the project team if the activities can be executed in parallel.

How to apply Fast-Tracking?


For example, we have a schedule that we are told to compress for. Here, we have
only 12 days for simplicity, and we need to compress it for three days. We will keep
the resources constant in fast-tracking but make activities parallel, as shown in the
below picture.
Employing this technique will increase risk and rework chances as two or more
activities will be done simultaneously. So ultima, we, as project managers er, will
have to decide which technique to be used based on the nature and criticality of a
project.

During the planning phase of a real-time project, it may seem impossible to work on
parallel activities. Still, it is necessary to think out of the box, and you may find the
solution even for the most critical problems. In the above example, we assume that
the activities’ resources are different; hence we can go for the parallel operation.

It is recommended for the interlinked activities to have a risk assessment to analyse


how early the second activity can be started. If the risk is not too high, the parallel
activity can be easily managed. After schedule adjustment, the first thing to be
looked at is resource allocation and ensuring its availability without putting too much
pressure on the project team or a project team member.

Fast-tracking has its challenges, and it’s not without its risks. It is the opposite of
initial project planning, as one allows the planning at the beginning, and the other
deals with preparation during the project’s execution phase. In general, fast-tracking
increases the overall risk of the project.

For example, you can purchase all the furniture for a new office before its
completion. But there could be a possibility that you may have to make some size
adjustments in office design in the execution, and your furniture may not fit into the
new design. Now the furniture is useless for you. Therefore, it is recommended to
focus on the right activities on the critical path, keeping in view the risks attached to it
to have favourable schedule compression outcomes.
So to summarize, the following are step-by-step guidelines for the Fast-tracking
technique.

 Define the goals expected from the fast-tracking of a given project


 Analyse project plan to define interlinked milestones/activities
 List down critical risks (risk register)
 Analyse critical paths & critical chain for possible adjustments in schedule.
 Adjust according to the available information.
 Project execution and monitoring

Advantages of Fast Tracking


 Possibility of Early delivery of the project
 Timely delivery of delayed project
 Enhanced productivity and efficient utilization of project resources

Disadvantages of Fast Tracking


 Requires expertise to use this technique, so not recommended for an inexperienced
project manager.
 Requires close monitoring of critical path.
So, to summarize, we can say that more than that, there is more than one
technique/approach available in project management, and we, as project managers,
have to decide which technique to be used depending upon the nature and
requirement of the project.

Hope crashing is clear to you.

How to apply Crashing Technique


Crashing is where we need to get permission from the concerned project
stakeholders to add more resources. Most of the time, it is not permitted easily
unless we show them the delay impact (late penalty) vs. resource cost.

The project manager will evaluate the activities/tasks that will save much time with a
smaller budget increase. It can do with an increase in overtime, adding more
resources, adding incentives. Crashing techniques needs more buy-in from the top
project management, whereas fast-tracking is done with project team involvement.

You might also like