Professional Documents
Culture Documents
The CAT Project: Entree 19
The CAT Project: Entree 19
ENTREE 19
Syndicate Group 1:
Anindita Putri 29320172 Daniel Roberto Simamora 29320231
Arvin Reinaldo Andrianda 29320079 Dhavina Durra 29320131
Ayu Rahmawati 29320062
Key Information
E (30)
0 30
30 44 44 58 58 72 72 82
E 0 30 0 30 0 days
F 30 44 30 44 0 days
Total (Activity) Slack:
G 44 58 44 58 0 days
H 20 27 40 47 20 days
S = LS – ES or LF – EF
I 27 34 47 54 20 days
J 34 55 54 75 20 days
K 55 62 75 82 20 days
L 58 72 58 72 0 days
M 72 82 72 82 0 days
N 82 86 82 86 0 days
The CAT Project | Syndicate 5
Conclusion
The normal time is defined as that duration of an activity that results in the smallest cost when only that
particular activity in itself is performed. The crashing of an activity results in expediting the effort so that it
takes less time but is higher in cost. (pmi.org)
Crashing an activity means that you reduce the time required to complete the activity by adding additional
resources, including man power and machinery. This not only adds efforts and reduces the time required to
complete the activity faster, but also increases the cost for completing the activity.
Objectives
- Finding the cheapest low cost in order to know which activity can
be crashed first and which cannot.
Source: pmi.org
ACTIVIT PREDE NORMAL TIME CRASH TIME Slope Cost Max Crash Time
Y CESSO DAY DAY
R COST COST
E - 30 Dn1 C1 Dc1 S1 15
F E 14 200 12 500 S2 2
G F 14 Dn3 c3 Dc3 S3 4
L G 14 Dn4 c4 Dc4 S4 7
M L 10 Dn5 c5 Dc5 S5 10
Variables: