MONITORING
1
OUTLINE
1. What is planning?
2. Nature of Planning
3. Procurement Planning
3.1 Importance of Planning
3.2 Preparing the PPMP
3.3 Preparing the APP
4. Procurement Monitoring
4.1 Importance of Monitoring
4.2 Preparing the PMR
2
PROCUREMENT PLANNING
Preparation of PPMP and APP
3
PHILIPPINE PROCUREMENT PARADIGM
NEEDS SATISFACTION
PLANNING
- refers to predetermined
course/s of action to achieve a
desired end/goal.
PROCUREMENT PLANNING
6
WHY PROCUREMENT PLANNING
Procurement Planning ensures that the overall goal of a
particular project will be effectively and efficiently
achieved.
− advance deliveries
− suki system
− unwarranted resort to alternative methods
procurement
7
SECTION 7.1 OF IRR
Procurement Planning and Budgeting Linkage
9
ACTORS IN PROCUREMENT
PLANNING
TECHNICAL
END USER WORKING GROUP
BUDGET
OFFICE (TWG)
12
PROJECT PROCUREMENT
MANAGEMENT PLAN (PPMP)
Contracting
Arrangement
PPMP
Time
Extent/size
schedule
Procurement
methods
13
IDENTIFYING THE NEED
14
TECHNICAL SPECIFICATIONS, SCOPE OF
WORK, AND TERMS OF REFERENCE
Consult Stakeholders
In developing the project requirements and TS/SOW/TOR,
the Procuring Entity may engage the services of technical
experts, whether in-house or consultants, to ensure that the
requirements and the TS/SOW/TOR are adequate to achieve
the objectives of the particular procurement.
Set clear Specifications:
– Generic and flexible
– Clear and unambiguous
– Reminder on Reference to Brand Names (Section 18)
– Updated, where technology is taken into account
– Fits the actual requirements of the PMO/End-user
15
APPROVED BUDGET FOR THE
CONTRACT (ABC)
The ABC reflected in the APP and PPMP shall be consistent
with the appropriations for the project authorized in the
GAA, continuing and automatic appropriations, the
corporate budget, and the appropriations ordinance, as the
case may be.
For multi-year contracts, for which a Multi-Year Obligational
Authority (MYOA) or an equivalent document is required, the
ABC shall be that incorporated in the project cost reflected
in the MYOA or equivalent document
For Foreign-funded Procurement, the ABC refers to the cost
estimate prepared by the PE and approved by the foreign
government/foreign or international financing institution as
specified in the Treaty or International or Executive
Agreement
16
APPROVED BUDGET FOR THE
CONTRACT (ABC)
End user to conduct market study
Market price, inflation and cost of money related to the
procurement time table must also be considered.
In determining the ABC, the end-user unit, with the
assistance of the TWG (when necessary), must consider
the different cost components.
17
METHOD OF PROCUREMENT
18
PPMP vs PR
19
ANNUAL PROCUREMENT PLAN (APP)
20
ANNUAL PROCUREMENT PLAN (APP)
All procurement should be meticulously and judiciously planned
by procuring entity
21
ANNUAL PROCUREMENT PLAN (APP)
1 2 3 5 7
4 6
22
PREPARATION OF APP
HOPE/Approving
APP
When GAA, Corporate
Body Budget or
BAC & Appropriation
Secretariat Submit Indicative
Ordinance becomes
final, PPMPs will be
Budget APP and budget finalized and submitted
proposal to to BAC Secretariat for
Office Consolidation HOPE/oversight consolidation, to BAC
of PPMPs to body for approval
Indicative APP for final
End-User Submit to by BAC Sec
recommendation of
modality and final
and
Unit Budget
recommendatio
approval of the HOPE
Office for
evaluation n by BAC of
Prepare Project modality
Procurement
Management
Plan (PPMP) During Budget Preparation
23
PPMP CONSOLIDATION
• Checking of • Recommendation of
procurement procurement methods
methods by the BAC
• Propose procurement
methods (End-user)
24
REVISIONS ON APP
End-User Update
/Supplement
PPMP
Consolidate
PPMP to
BAC & BAC Sec Updated/
Supplemental
APP
Approve
Updated
HOPE /Supplemental
APP
25
ANNUAL PROCUREMENT PLAN (APP)
Procurement Short of Award
To facilitate the immediate implementation of procurement ,
even pending approval of the GAA, corporate budget or
appropriations ordinance, as the case may be, the PE may
undertake the procurement activities short of award
For a contract with a period not exceeding one (1) year,
the ABC shall be based on the amount in the approved
indicative APP as included in the proposed national budget
(NEP) submitted by the President to Congress; on budget
levels as proposed to the governing board for GOCCs
No award of contract shall be made until the GAA or
corporate budget has been approved
26
APP vis-a-vis APP-CSE
27
APP-CSE
28
TIPS IN CONSOLIDATING PPMPS
Mode of Procurement
Sources of Funds
29
POSSIBLE CONSEQUENCES
3. Suspension of Officials
5. Project Delays
6. Project Failures
30