CHAPTER 6
THE PLAN-MONITOR-
CHAPTER 6
CONTROL CYCLE
Monitoring and Controlling the
Project
Plan-Monitor-Control Cycle
Project Management 4
Figure 7-1 Project Authorization and Expenditure
Control System Information Flow
Project Management 5
Designing the Monitoring
System
• Identify special characteristics of performance,
cost, and time that need to be controlled
– performance characteristics should be set for each
level of detail in the project
• Real-time data should be collected and compared
against plans
– mechanisms to collect this data must be designed
• Avoid tendency to focus on easily collected data
Project Management 6
Project Management
DATA COLLECTION AND
REPORTING
CHAPTER 6
• Frequency Counts
• Raw Numbers
• Subjective Numeric Ratings
• Indicators and Surrogates
• Verbal Characterizations
Project Management 8
Data Analysis
• Aggregation Techniques
• Fitting Statistical Distributions
• Curve Fitting
• Quality Management Techniques
Project Management 9
Figure 7-2 Number of Bugs per
Unit of Test Time
Project Management 10
Figure 7-3 Percent of Specified Performance
Met During Successive Repeated Trials
Project Management 11
Figure 7-4 Ratio of Actual Material
Cost to Estimated Material Cost
Project Management 12
Reporting
• Reports
– Project Status Reports
– Time/Cost Reports
– Variance Reports
• Not all stakeholders need to receive same information
• Avoid periodic reports
• Impact of Electronic Media
• Relationship between project’s information system
and overall organization’s information system
Project Management 13
Report Types
• Routine
• Exception
• Special Analysis
Project Management 14
Meeting Guidelines
Project Management 15
Meeting Guidelines continued
Project Management 17
Project Management
CHAPTER 6
EARNED VALUE
Monitoring and Controlling the
Project
Earned Value
Project Management 19
Conventions Used to Estimate
Progress on Tasks
• 50-50
– 50% complete when task started and other
50% added when task finished
• 100%
– 100% complete when finished and zero
percent before that
• Ratio of Cost Expended to Cost Budgeted
Project Management 20
Variances
• Cost/Spending Variance
EV - AC
• Schedule Variance
EV - PV
• CPI
EV/AC
• SPI
EV/PV
Project Management 21
Additional Items of Interest
Project Management 22
Project Management
CHAPTER
PROJECT 6
CONTROL
Monitoring and Controlling the
Project
Background
Project Management 24
Purposes of Control
Project Management 25
Project Management
Project Management 27
Primary Mechanisms by Which
PM Exerts Control
• Process Reviews
• Personnel Assignments
• Resource Allocations
Project Management 28
Components of a Control System
• Sensor
• Standard
• Comparator
• Decision Maker
• Effector
Project Management 29
Types of Control Systems
• Go/No-Go Controls
– predetermined standard must be met for
permission to be granted to continue
• Post-Control
– done after project completed
– purpose is to allow future projects to learn
from past project experience
Project Management 30
Figure 7-7 Sample Project
Milestone Status Report
Project Management 31
Tools for Control
• Variance Analysis
• Trend Projections
• Earned Value Analysis
• Critical Ratio
actual progress budgeted cost
scheduled progress actual cost
Project Management 32
Figure 7-8 Trend Projection
Project Management 33
Figure 7-9 Critical Ratios with
Control Limits
Project Management 34
Figure 7-10 Cost Control Chart
Project Management 35
Project Management
Project Management 37
Purpose of Change Control
System
Project Management 38
Purpose of Change Control
System continued
Project Management 39
Rules for Controlling Scope
Creep
• Include in contract change control system
• Require all changes be introduced by a
change order
• Require approval in writing by the client’s
agent and senior management
• Consult with PM prior to preparation of
change order
• Amend master plan to reflect changes
Project Management 40