Professional Documents
Culture Documents
1
2
Validate Scope
3
4
5
Inputs
•Project Management Plan
•Project Documents
•Verified Deliverables
6
Project Management Plan
•Contains the scope management plan, Requirement
Management Plan and the scope baseline
7
Project Documents
–Lesson Learned Register – Manage Project Knowledge
output
8
Verified Deliverables
Verified deliverables are project deliverables that are completed
and checked for correctness through the Control Quality
process – Control Quality
9
Tools
• Inspection
10
Inspection
•Inspection includes activities such as measuring,
examining, and validating to determine whether work and
deliverables meet requirements and product acceptance criteria
11
Output
•Accepted Deliverables
• Change Requests
12
Accepted Deliverables – Close Project or Phase
•Deliverables that meet the acceptance criteria are formally
signed off and approved by the customer or sponsor
13
Work Performance Information - Monitor and Control Project Work
Work performance information includes information about project
progress, such as which deliverables have started, their progress,
which deliverables have finished, or which have been accepted
14
Control Scope
15
16
17
Inputs
•Project Management Plan
•Project Documents
18
Project Management Plan
•Scope Baseline
19
Project Documents
• Lesson learned Register – Manage Project Knowledge output
• Requirements Documentation – Collect Requirements
Requirement Documentation should be
– Unambiguous (measurable and testable)
– Traceable
– Complete
– Consistent, and
– Acceptable to key stakeholders
Well-documented requirements make it easier to detect any
deviation in the scope agreed for the project or product
20
Work Performance Data - Direct and Manage Project Work
21
Tools
•Trend Analysis
•Variance Analysis
22
Variance Analysis
23
Output
24
Work Performance Information – Monitor and Control
Project Work
25
Change Requests – Perform Integrated Change
Control
•Analysis of scope performance can result in a change
request to the scope baseline or other components of the
project management plan
26
Project Management Plan Updates
27
Project Documents Updates
28
Validate and Control Scope Exercise
1. A work breakdown structure numbering system is used for:
A. Methodically estimate cost of elements work breakdown structure.
B. Explain justification of project.
C. Identification of level at which elements are found.
D. Use in project management software.
29
Validate and Control Scope Exercise
4. Project scope statement is created in which process group?
A. Initiating
B. Planning
C. Executing
D. Monitoring and controlling
6. Project manager is asked to add work to project scope. The project manager
remembers that sponsor had previously denied funds for this scope. The project
manager should:
A. Inform sponsor of the request.
B. Evaluate impact of adding the scope.
C. Inform the scope cannot be added.
D. Add the work if there is time is available in project schedule.
30
Validate and Control Scope Exercise
7. For which purpose can a work breakdown structure be used?
A. Communication with the project team.
B. Explaining calendar dares for each work package.
C. Illustrating the functional managers for each team member
D. Show business need for project.
31
Validate and Control Scope Exercise
10. Advantage of WBS?
A. Avoids work from slipping through the cracks.
B. Not needed.
C. Required only if project includes contracts.
D. Only method to identify risks.
12. A project manager uses to ensure the team members know what work is
incorporated in their work package.
A. Project scope statement.
B. Product scope.
C. WBS dictionary.
D. Schedule.
32
Validate and Control Scope Exercise
13. You have held periodic meetings with stakeholders. Project is on schedule and
budget, but stakeholders are not pleased. The MOST significant process that could
have avoided this situation is:
A. Monitor and Control Risks.
B. Control Schedule.
C. Define Scope.
D. Control Cost.
33
Validate and Control Scope Exercise
16. Project requirements have been changing. What is MOST likely to occur?
A. Reduce costs.
B. Ensure that customer approves the project scope.
C. How to determine project completion.
D. Always add resources to project.
34
Validate and Control Scope Exercise
19. Validate Scope process:
A. Promises that deliverable meets specifications, is an input to project
management plan, and an output of Perform Quality Control.
B. Ensures that deliverable is complete on time, make certain customer
acceptance, and explains that deliverable meets specifications.
C. Ensures customer acceptance, deliverable meets specifications, and provides
a chance for difference of opinion.
D. It is an output of Perform Quality Control, happens before Define Scope, and
ensures customer acceptance.
35