Professional Documents
Culture Documents
Estimating Resources
Cost Estimation Project
Budgeting
P r o j e c t C a s h F lo w Analysis a n d C o s t A l l o c a t i o n
PPEC
3. Project Resource Estimation and Planning
Solomon K.(PhD)
July, 2021
Table of Contents
• The purpose of the project estimating process is to describe the steps for
developing size, effort, cost, schedule, and critical resource estimates for a
project throughout its life cycle.
• The project estimation process can be hard, especially if there is less
information available.
• In order to have accurate project estimate, you need to know your team,
deliverables, and tasks (activities).
• Accuracy of estimates depends on:
Level of detail: the degree of decomposition of the WBS.
Risk assessment results and the remediation plan.
The estimator's experience.
The estimating method.
• These information are used to compare among available estimate
and select most accurate project estimates.
Solomon K. Project Planning....
Project Estimating
Processes Estimating
Resources C o st Ty p e s of P r o j e c t E s t i m a t e s
Estimation Project
Budgeting
P r o j e c t C a s h F l o w Analysis a n d C o s t A l l o c at i o n
Levels of Estimating
Accuracy
There are three levels of estimating accuracy:
1. Ballpark estimates
• Ballpark or approximate estimates are made when little
information about the project is available and there are no
detailed requirements, except the initial project request.
2. Preliminary estimates
3. Accurate estimates
• Accurate or definitive estimates are prepared from a
well-defined detailed data and WBS. This is the most
detailed estimate.
• This type of estimate is done just before the project plan
package is created or updated.
• It is not usually possible to do accurate estimates for the
entire project, because the lack of detailed information
for the required activities in the distant future.
b) Estimate Effort
• Estimates of time required to complete tasks outlined in the WBS.
• This effort (time), say, labor hours per task may be calculated
using one of the following major types of estimation:
E=
to + 4 (t m )+tp
E= expected estimate 6
Example
• Consider a lawyer believes a project will cost ETB 1000
in the best-case scenario and ETB 1500 in the worst-
case scenario, with ETB 1199 being the most likely
Figure. Then what is the estimate cost of the project?
+ 4 ( t m )+tp = 1000 +4 ( 11 99 ) +1 5 0 0
Estimate = t o
6 6
= ETB
1216
Cost Estimation
Cost Estimation
• Cost Estimation is the process of developing an approximation of the monetary
resources needed to complete project activities.
• Cost estimating is linked closely with scope, schedule, and resource planning.
• To estimate project costs accurately, the project manager must
understand
o the various types of cost,
o the timing and accuracy of cost estimates,
o the different methods that can be employed to estimate
costs, and
o a variety of cost estimating issues.
• Let us first discuss different types of project cost.
Estimating Resources
➢ Resource estimation is the process of estimating the types
and quantities of material, human resources, equipment, or
supplies required to perform each activity.
Project Budgeting
• Once the project costs have been estimated, it is time
to establish the project budget.
• Project budgeting is simply the process of forecasting
what resources the project will require, what quantities
of each will be needed, when they will be needed, and
how much they will cost.
• Budgeting skills are necessary when estimating the
resources and materials you will need for the project.
• Here, you have reached a major milestone in the
project's planning process; the budget is the last
Planning document you will create.
Solomon K. Project Planning....
Project Estimating
Processes Estimating
Resources C o st M e t h o d s of P r o j e c t B u d g e t i
Estimation Project
Budgeting
P r o j e c t C a s h F l o w Analysis a n d C o s t A l l o c at i o n ng
Project Budgeting
• A budget must be developed in order to obtain the
resources needed to accomplish the project's objectives.
• A budget is simply a plan for allocating
organizational resources to the project activities.
• Hence, the project budget is nothing more than the
project plan, based on the WBS, expressed in
monetary terms.
• Once the budget is developed, it acts as a tool for
upper management to monitor and guide the
project.
Solomon K. Project Planning....
Project Estimating
Processes Estimating
Resources C o st M e t h o d s of P r o j e c t B u d g e t i n g
Estimation Project
Budgeting
P r o j e c t C a s h F l o w Analysis a n d C o s t A l l o c at i o n
1. Top-down Budgeting
• This method
1
is based on the collective judgments and experiences of top
and middle managers concerning similar past projects.
• These managers estimate the overall project cost by estimating the
costs of the major tasks.
• Then these estimates are given to the next lower level of managers to
split up among the tasks under their control, and so on, until all the
work is budgeted.
Solomon K. Project Planning....
Project Estimating
Processes Estimating
Resources C o st M e t h o d s of P r o j e c t B u d g e t i n g
Estimation Project
Budgeting
P r o j e c t C a s h F l o w Analysis a n d C o s t A l l o c at i o n
Bottom-up Budgeting
2. Bottom-up Budgeting
Best Practice