Professional Documents
Culture Documents
E a r n e d Val u e Anal ys i s
S c h e d u l e a n d C o s t Va r i an c e F o r e c a s t i n g
Resource M an a g e m e n t a n d Co st Control
PPEC
4. Project Execution and Control
Solomon K.(PhD)
July, 2021
Table of Contents
1
Progress Tracking and Monitoring
2
Earned Value Analysis
o Efficiency Indices
3
Schedule and Cost Variance Forecasting
4
Resource Management and Cost Control
o Identify Potential Resources
o Determine Resource Availability
o Decide Timing Issues when Resourcing Projects
• The project team wants to see how one specific aspect of the work process
may change over time.
• Control charts are graphs that display periodic results along with established
control limits, to determine whether the project performance is improving or
getting worse.
• If they collect data for two weeks on a daily basis and show them
on a control chart (Figure 4.1), they could determine trends in
how the process is changing over time.
• Figure 4.1: Project control chart
Given:
Project duration:
1 12 months
Project cost (BAC): 100,000 USD
Percent complete: 50% (as per the schedule)
Solution: Planned Value is the value of the work that should have been completed
so far (as per the schedule). In this case, we should have completed 50% of the
total work.
Planned Value = 50% of the value of the total work
3
= 50% of BAC
= 50% of 100,000
= (50/100) X 100,000
= 50,000 USD
Therefore, the project’s Planned Value (PV) is 50,000 USD.
Variable measure in the vertical axis is monetary value (say in Birr) and
time is measured along the horizontal axis (in months).
Efficiency Indices
• Schedule Performance Index. is a measure of schedule
efficiency expressed as a ratio of earned value to the planned
value.
SPI = EV
PV
o It is a measure of schedule efficiency.
o How efficient is the project so far with its schedule
• SPI < 1 means the project has accomplished less work than planned and is
behind schedule; SPI > 1 means the project is ahead of schedule (more work is
completed than the plan).
• Cost Performance Index:- is a measure of cost efficiency of budgeted
resources expressed a ratio of the earned value to the actual cost.
CPI = EV/AC
• This ratio is a measure of cost efficiency (how efficiently birr is being
spent). How efficient is the project so far with its budget?
CPI < 1 means the work is costing more than planned;
CPI > 1 means the work is costing less than planned.
Solomon K. P roject Planning....
P r o g r e s s Tr a c k i n g a n d M o n i t o r i n g
E a r n e d Val u e Anal ys i s
E f fi c i ency I ndi c es
S c h e d u l e a n d C o s t Va r i an c e F o r e c a s t i n g
Resource M an a g e m e n t a n d Co st Control
Example 1
The ABC Project was scheduled to cost ETB 1,500 and was
originally scheduled to be completed today. As of today,
however, the project has spent ETB 1,350 and it is estimated
that only two-thirds of the work has been completed.
1 Calculate and interpret the Schedule and Cost Variances.
2 Find and interpret the Schedule and Cost Performance Indices.
3 Calculate and Estimate to Complete First method and Second
method provided that Budget at Completion is Birr 6500.
4 Compute and interpret Estimate at Completion.
5 Find and interpret To-complete Performance Index.
Solution: SV and CV
Given
PV = 1500 EV = 2
3
∗ 1500 = 1000 AC = 1350 BAC = 6500
CV = EV - AV =1000-1350= -350
=
Estimate to Complete
• ETC First Method
• It is calculated by subtracting the earned value from the BAC,
then dividing the result by the CPI.
ETC =BAC−EV CPI (ETC − First
Method
• It shows the expected )
additional cost needed to finish the
project based on project performance to date.
• It is based on the assumption that our future performance will
have the same efficiency as our past performance.
• ETC Second Method
• It is calculated by subtracting the earned value from BAC.
ETC = BAC − EV (ETC − Second Method )
• This method is based on the assumption that the original plan is a
better predictor than the work to date (maybe because of unusual
circumstances that are unlikely to continue).
Solomon K. P roject Planning....
P r o g r e s s Tr a c k i n g a n d M o n i t o r i n g
E a r n e d Val u e Anal ys i s
S c h e d u l e a n d C o s t Va r i an c e F o r e c a s t i n g
Resource M an a g e m e n t a n d Co st Control
Example: ETC
Estimate at Completion
• It is the expected total cost of completing all work expressed as
the sum of actual cost to date and the estimate to complete.
EAC = AC + ETC
• In our example, if we believe our efficiency to date is a good
predictor of the future, EAC is :
EAC = AC + ETC 1 s t = 1350 + 7432.4 = 8782.4
• But, if we believe what happened so far will not be repeated and
our original plan is good for the remaining work, EAC is: EAC
= AC + ETC 2 n d = 1350 + 5500 = 6850
• Interpretation: Because our cost efficiency is only 74% (see
CPI), which is less than our plan , unless we become more
efficient, we can expect to pay extra 35 percent of our original
estimate! Even if we match our original plan for the rest of the
project, we will still be way over budget in the end.
Solomon K. P roject Planning....
P r o g r e s s Tr a c k i n g a n d M o n i t o r i n g
E a r n e d Val u e Anal ys i s
S c h e d u l e a n d C o s t Va r i an c e F o r e c a s t i n g
Resource M an a g e m e n t a n d Co st Control
• Of course, a project manager may need to negotiate not just for who
will be assigned to his project, but when they will be assigned.
• As members are brought on board, timing issues involve getting the
team functioning effectively and keeping them motivated and on
schedule.
• Near the end of a project, timing issues include rewarding,
recognizing, and releasing project team members.
• The staffing management deals with these three issues:
o how the project planners identify potential people for
the project,
o how they determine which people are available and secure
their services, and
o how to deal with timing issues of building up and then
releasing the workforce.
Solomon K. P roject Planning....