Professional Documents
Culture Documents
Structural Design Post Tensioned Slab Design1
Structural Design Post Tensioned Slab Design1
Introduction
The technique of prestressing has several different applications within civil engineering ,
often being used to keep cables taut when subjected to compressive forces. However,
by far the most common application is in prestressed concrete where a prestress force is
applied to a concrete member, and this induces an axial compression that counteracts
all, or part of, the tensile stresses set up in the member by applied loading.
Within the field of building structures, most prestressed concrete applications are in the
form of simply supported precast floor and roof beams. These are usually factory made,
where the advantages of controlled mass production can be realized. Where large spans
are required, in situ prestressed concrete beams are sometimes used, and in situ
prestressed concrete flat slab construction is increasingly being employed.
Most prestressed slabs utilize uniform –depth slabs with draped tendons, but an
interesting development is the use of variable-depth slab with straight tendons.
No design guidance is given in EC2 regarding prestressed concrete slabs. Design is,
therefore, be based on the recommendations given in the Concrete Society (1994)
Technical Report TR43.
Prepared by: Eng. Chamil Duminda Mahagamage
1 B.Sc.Eng (Hons), C Eng, MIE(SL)
08/19/2021
Since the tendons must have a minimum spacing between them, the stress distribution
within the slab will not be exactly uniform, but in practice it would be reasonably so.
Prestressed concrete slabs such as that shown in figure above are rarely found in
practice, and the more common form is the flat slab.
In practice, the sharp changes of curvature in the tendons are avoided by adopting
smooth reversing in curvature. An alternative pattern of tendons which is often used
based on the distribution of primary and secondary tendons is well suited to slabs with
irregular column layouts, but shear strength will be reduced.
A commonly used layout of tendons is to place 70% of the total number of tendons in a
panel, determined from an equivalent frame analysis, in a band of width equal to 40%
of the bay width, centered on the columns. The remaining tendons are uniformly
distributed across the panel. Maximum spacing of tendons, or groups of tendons,
should be 6 times the slab depth for unbonded tendons or eight times the slab depth
for bonded tendons. The minimum spacing between ducts or groups of ducts, should be
75mm, or the width of the group of ducts.
Untensioned reinforcement should be placed in the top of all slabs over the columns,
equal in area to a minimum of 0.075% of the gross cross section of the slab, placed in a
width equal to that of the column plus one and a half times the slab depth on each side
of the column. Bars should extend at least one-fifth of the span on either side of the
column and have a maximum spacing of 300mm. The combination of tendons and
reinforcing bars in the region of the columns could lead to congestion and careful
attention should be paid to the detailing in this area.
Example
A prestressed concrete flat slab warehouse floor has the layout shown in figure below.
The imposed load is 10KN/m2.
i). Determine a preliminary slab depth and layout of unbonded prestressing
tendons.
ii). Determine whether the ultimate strength capacity of the slab is adequate.
iii). Determine the shear resistance at column B3