Professional Documents
Culture Documents
Evaluation Of Proposed
Public Expenditures
Before determining the NPV of a proposal, the costs (C) and benefits (B)
need to be quantified for the expected duration of the project.
NPV is the present value of all benefits, discounted at the appropriate
discount rate, minus the present value of all costs discounted at the same rate.
The NPV is calculated as follows:
Where:
Bt is the benefit at time t;
Ct is the cost at time t; and
r is the discount rate.
• The net social benefit (NSB) of the proposal is
calculated by subtracting the cost stream from
the benefit stream and is represented as follows:
• NSB = B – C
Decision rule:
If NPV is positive (+): accept the project
If NPV is negative (-): reject the project
1) For example, if the initial investment of project A is
$100 and it will be $70 in benefits and $25 in costs for each
of 3 years, and the discount rate is 10 per cent per annum,
then the NPV will be:
NPV = −$100 + ($70 − $25)/ (1 + 0.1 )1 + ($70 − $25)/
(1 + 0.1)2 + ($70 − $25)/ (1 + 0.1)3
= −$100 + $40.91 + $37.19 + $33.81
= $11.91
2) A firm intends to invest $1,000 in a project that
generated net receipts of $800, $900 and $600 in the first,
second and third years respectively , At the discount rate of
10%.Should the firm go ahead with the project?
The CBA report should include the following information:
Executive summary outlining the critical assumptions, key results and
recommendation(s)
Background to the analysis why it was undertaken
Objectives of the project, programme or activity
Key risks associated with the proposal
Outline of alternatives considered
Time profiles of costs, benefits and net benefits
Key assumptions underpinning the analysis
The discount rate applied
NPV calculations
Sensitivity analysis
Other important information including distributional effects, other quantified costs and
benefits, and intangible costs and benefits
Comparison of the preferred option to alternatives
How the outcome of the proposal could later be evaluated
Concluding comments
8.2 Cost-Effectiveness Analysis (CEA)
Where
CE is the cost-effectiveness of the proposal,
C is the cost (measured in dollars) and
E represents the effectiveness (i.e. the benefit measured in
physical units).
Where this is the case, the incremental cost-effectiveness ratio (ICER)
could be used. This is represented as follows:
or
Where
o Cn is the cost of the new proposal,
o Cc is the cost of maintaining the current programme,
o En is the effectiveness of the new proposal and
o Ec is the effectiveness of continuing with the current programme.
Example
1) Consider a project for which there are four alternative, the project
involves adding's a safety barrier to the centre reservations of a
major road .the per mile of the barrier doffers depending on the
quality of the material used. Scheme A users a reinforced wooded
barrier .scheme B uses iron ,C uses steel, Uses concrete reinforced
with steel. The costs and effectiveness in terms of lives saved are
shown in the table below
E(lives
Scheme Costs(c) saved per
annum
C/E
C E C/ E
A 9,000 5 1800 - - -
B 15,000 8 1875 6000 3 2000
C 20,000 11 1818 5,000 3 1667
D 30,000 12 2500 10,000 1 10,000
YOUCANASK
•
QUIZZ
End Of Chapter eight
THANK YOU