Professional Documents
Culture Documents
Environmentally
Critical Projects
Heavy Industries 11
• Major dams
• Major power plants
• Major reclamation projects
• Major
14
Environmentally
Critical Areas
15
PROJECT
CATEGORIES
19
CONTENTS OF
TYPICAL EIA
REPORT
These documents include substantive analysis, key
findings, and conclusions on environmental
characterization, comparison to Philippine
statndards, typical baseline environmental values,
and country statistics or other reference standards.
34
Project Description
including its location, scale and duration, rationale, alternatives, phases and
components, resource requirements, manpower complement, estimate of waste
generation from the most critical project activities and environmental aspects,
project cost
PAGE LIMIT: 350 PAGES
35
Impact Assessment
• focused on significant environmental impacts (in relation to pre-construction,
construction/development, operation and decommissioning stages), taking into
account cumulative, unavoidable and residual impacts
DECISION
DOCUMENTS
39
Certificate of Non-Coverage
(CNC)
• The CNC is issued by the EMB certifying that, based on the submitted project
description, the project is not covered by the EIS system and is not required to
secure an ECC.
41
Denial Letter
• shall include an explanation as to why the application of EIA was disapproved
and a guidance on how the application of EIA in the next process be improved to
be order to be accepted.
42
EIA process
43
SCREENING
• determines if the project is covered or not covered by the PEISS.
• DENR-EMB classifies a project into 4 categories: single project, co-
located project, new undertakings project and existing project.
44
SCOPING
• identifies the most significant issues/impacts of a proposed project, and
then, delimits the extent of baseline information to those necessary
to evaluate and mitigate the impacts.
Three-levels of scoping
1st level – project briefing with review team
2nd level – Public scoping with community/stakeholders
3rd level – Technical scoping with review team
45
DECISION MAKING
• to approve or deny the project through the issuance of an ECC, CNC or
denial letter.
• Deciding Authority: DENR Secretary, DENR-EMB Director and
DENR-EMB Regional Directors, depending on the project category.
47
Other PEIA
features
49
Public participation
• Consultations are held at various stages in EIA process including
scoping, EIA study, EIA review and evaluation, and compliance
monitoring.
51
Social acceptability
Monitoring,
Validation and
Evaluation/Audit
Procedures
56
Objectives
To ensure the judicious implementation of sound environmental
management
Specifically aims to ensure:
1. Project compliance with the conditions set in the ECC
2. Project compliance with the Environmental Management
Plan (EMP)
57
Objectives
3. Effectiveness of environmental measures on prevention or
mitigation of actual project impacts in relation to the predicted impacts
used as basis for the EMP design
4. Continual updating of the EMP for sustained responsiveness to
project operations and project impacts.
58
Functions of MMT
a) Validate project compliance with the conditions stipulated in the ECC and the
EMP;
b) Validate Proponent’s conduct of self-monitoring;
c) Receive complaints, gather relevant information to facilitate determination of
validity of complaints or concerns about the project and timely transmit to the
Proponent and EMB recommended measures to address the complaint;
61
Functions of MMT
d) Prepare, integrate and disseminate simplified validation reports to community
stakeholders;
e) Make regular and timely submission of MMT Reports based on the EMB-
prescribed format.
62
Fines, Penalties
and Sanctions
67
Suspension of ECCs
• ECCs may be suspended for violation of Proponents to comply with ECC
conditions. It is noted that ECC suspension does not necessarily mean the
Proponent is absolved of its responsibility in implementing its approved
Environmental Management Plan (EMP).
68
Publication of Firms
• The EMB may publish the identities of firms that are in violation of P.D. 1586
and its Implementing Rules and Regulations despite repeated Notices of
Violation.
71
Scope of Violations
• Projects with or without ECCs
• Projects are established and/or operating without an ECC
• Violations of conditions of ECCs with old format referring to submission of
documents, conduct of studies and other conditions within the mandate of other
agencies
72
Assessment and
Computation of
Fines
73
Thank you