Professional Documents
Culture Documents
Bed slope
In open trough: Flow is uniform, bed is kept parallel to
slope of energy line.
In closed trough: Flow is non-uniform, energy has to be
computed. Closed troughs are kept horizontal to carry
roads, inspection paths, etc.
Example
A distributary canal is to cross a Branch canal. Prepare
hydraulic design of an aqueduct with the following data:
Branch canal Distributary
Full supply discharge 20 cumec 10 cumec
Bed width 18.3 m 13 m
FSL 106.43 109.05
Bed level (BL) 104.90 107.71
Slope 1:6,666 1:6,666
Mean velocity 0.64 m/s 0.61 m/s
Angle of crossing 90o 90o
Aqueduct: Distributary crossing a Canal
Solution:
For economy, branch canal as well as distributary are
flumed at the entrance and exit of crossing, as shown
below.
Branch canal
Reduce waterway of the branch canal from 20.0 to 11.0 m by
providing 3 spans of 3.7 m with 2 piers of 0.8 m width each.
Distance b/w abutment to abutment = 11.0 + (2 x 0.8)
= 12.6 m
Discharge intensity, q = Q/12.6 = 20/12.6 = 1.82 cumec/m
Critical depth, Dc = (q2/g)1/3 = 0.969 m
Assume depth of crossing = 1.4 m
Assumed bed level = FSL of canal – depth
= 106.43 – 1.4 = 105.03 m
Adopt bed level same as bed level of the secondary canal.
Distributary canal
In order that trough bottom remains above the FSL of branch
canal, keep the BL of the trough at 107.71.
Assume,
thickness of the slab = 0.5 m
2 2
and δ tan -1 (0.2) 11.3 o
Putting the values, we get
f = 0.009992 and hb = 0.005 ft
Loss of head at Exit, h e
0.5 2
2g
V V12
where, V = Velocity in barrel = 4.0 ft/sec
V1 = Velocity in canal = 2.5 ft/sec
Putting the values, he = 0.012 ft
Total head loss = hi + hf + hb + he
= 0.12 + 6.0 + 0.005 + 0.012 = 6.14 ft
FSL of canal on d/s of the siphon = FSL – Head loss
= 478.70 – 6.14 = 472.56 ft
Example
A canal is crossing a stream. Design a suitable cross
drainage structure knowing the following data:
Stream
Discharge, Q = 12.33 cumec
Highest flood level = 475.58
Bed width, B= 30 m
Canal
Q = 2.5 cumec; V = 0.58 m/sec; BW = 1.95 m;
Bed Level = 474.7; Full supply depth = 1.30;
Free board = 0.46 m; Hydraulic slope = 1:4,000
Solution
To determine which type of cross drainage structure
would be suitable at this place, consider the following:
i.Canal discharge = 2.5 cumecs;
ii.Stream discharge = 10.33 cumecs
iii.Stream discharge > Canal discharge
iv.HFL of stream is at 475.58; BL of canal is at 474.70
Difference = 0.88 m, which is too small as free board
for an aqueduct.
Hence, Canal will cross the stream through a siphon.
Length of siphon = 30 + 10% + 2(15) = 63 m
Discharge of siphon = 2.5 + 10% = 2.75 cumec
Assume velocity of the barrels = 2.44 m/sec
Design of concrete square barrels,
A = Q / V = 1.02 m2
Let, side of barrel = a
Area of barrel, A = a2 = 1.02 m2
Therefore, a = 1.01 m
provide pre-cast barrels.
0.5
Cross Drainage Structure for a Canal and Drainage Line at
the same level
When the bed level of the canal and the drainage line
are at the same level, the usual method to allow canal to
cross the drain is to mix water of the canal with the water
of the drain and then to draw from it the canal's designed
discharge from the other side of the drain.
However, it is essential that the water of the drain is
suitable for irrigation purposes.
The works constructed to accomplish it, are called level
crossing.
A level crossing consists of three cross regulators; two
across the canal and the third across the drain.
In normal situation, i.e. when the drain is not running,
the canal water falls in the drain and the two waters are
allowed to be mixed.
The gates of the cross regulator across the drain are
manipulated in such a way as to allow the canal
regulator to draw its designed discharge at that point at
the required level.
When the drain is in flood, the canal Regulators are kept
closed and the drain regulator is kept fully open till the
sediment laden flood discharge passes downstream.
When the flood recedes and the water becomes
clearer in the stream, the canal regulators are
opened allowing the canal to draw water as
usual.
Another important factor is that only water from
the drain should be allowed to enter the canal
whose quality is suitable for the purposes of
canal water. Otherwise, another type of cross
drainage structure should be used.
Selection of Site for a Cross Drainage Structure
The site for cross drainage structure should be such that:
A. The canal and the drain should cross each other at a
right angle. Acute or obtuse angle crossing should be
avoided.
B. There should be sufficient straight reaches of canal and
drain on both the upstream and the downstream sides.
C. A sufficient reach of drain on the upstream should be
stable and uniform.
D. The foundation should be suitable for cross drainage
works.
Selection of the Type of Cross Drainage Structure
A. When the bed level of canal is sufficiently above the
highest flood level of the drain, an aqueduct is constructed.
B. When the highest flood level of the drain is higher than the
bed level of the canal, the aqueduct should be designed as
siphon aqueduct.
C. When the bed level of the drain is sufficiently higher than
the full supply level of canal, cross drainage work will be a
super passage.
D. When the full supply level of the canal is above the bed
level of the drain, cross drainage work will be a siphon.
E. If the bed levels of canal and drain are at the same level,
cross drainage structure is known as a level crossing.
Design of Siphon
Loss of Head
Due to:
shape of Inlet and Exit;
skin friction in pipes/conduits; and
bends.
Designed for minimum losses.
At entrance PE changes into KE.
Proper design to avoid loss of KE in form of eddies causing
scouring/erosion of bed and sides.
Commonly used Transitions:
i. Transitions with Splayed walls
ii. Transitions with Wrapped-up walls
i. Transitions with Splayed walls
Most commonly used due its simplicity.
Splay of 1:3 at inlet;
Splay of 1:5 at exit;
Maximum splay of walls, 45o;
Suitable for small and medium size canals.