Cross-Project Links Report

Madison MPUG Chapter Meeting


April 13, 2011

1
Background

 Project Sponsors want a clear high-level


view of dependencies between projects

 Communicate early on how schedule


changes within one project impact
dependent projects

2
Current Process

 Report is updated and published monthly

 As new cross-project dependencies are identified,


these projects are being added to the report

3
Milestones Professional
 Software recommended by a co-member of the
Madison MPUG (Microsoft Project Users Group)
Chapter

 Produced by KIDASA Software, Austin, TX

 Contains numerous templates that can be used to


create custom reports with MS Project data

 Provides more flexibility than Visio for this type of


reporting

4
Sample Report

5
MS Project Server
 Some setup needed in project server –
 External predecessor logic:

AMI-RCDM\28

Example: AMI-MDMS schedule:


• External predecessor is Task ID # 28 in the AMI-RCDM schedule
• In the MDMS schedule, enter “AMI-RCDM\28” in Predecessor ID
field to set up the link

6
MS Project Server

 AE uses the Text 30 field in MS Project


 Populate Portfolio ID with PM initials +
number scheme
 Must be unique across all projects on server

7
MS Project Server

Another option is to create a formula to populate


the Portfolio ID field – ensures ID is unique:

8
MS Project Server

When viewing the schedule in project server, the


predecessor task from the external project appears in gray
(disabled) above the dependent task

Note: We are currently viewing the AMI-MDM schedule

9
MS Project Server
Vice-versa when viewing the schedule with the
predecessor milestone (successor task in external
project appears in gray)

Note: We are currently viewing the DMS


Upgrade schedule

We’ve found this functionality to be useful – makes it clear to the PM


that there is an external project dependency, and which task is impacted.

10
Milestones Professional

Can set up
smart symbol
tags to track
project
milestones and
timelines

11
Milestones Professional

 Refresh report with updated project schedule


with the push of a button – automatically updates
timeline/milestones

12
Milestones Professional

13
Milestones Professional - Tips
 Timing: Consider how you will sync timing of report
creation to when PMs update schedules (might require
expectation setting with report recipients)

 User Interface: This is not a Microsoft product – different


user interface – there is a bit of a learning curve

 Refresh Process: When refreshing, first open the project


schedule in MS Project before selecting “refresh” in
Milestone Professional – speeds up refresh process

14
Questions:

15