Professional Documents
Culture Documents
VelocityPlay
Playbook
1 1/21/22
TAKT Analysis –
2
WIP Map
Little’s Law (l = λ*w)
WIP = Demand x Time
= (1x25) = 25
Actual WIP =
3
Work Stream Terminology
Play book – a document describing how the team members move to support
work cell.
Example: What specific actions need to take place if another team
member is absent
Example: What actions should be taken if the inventory in front of the
pacesetter drops to a minimum level
Example: What action do operators take when they meet their daily output
requirements
4
Work Stream Terminology
Material Presentation
POU – Point of Use, located where the operator needs it
Supermarket – The location where predetermined standard inventory is kept to
supply downstream processes
Material Handler – Moving necessary material and Kanban cards to its proper
location within the process flow
Constraint – Often referred as the bottleneck; it is anything that prevents the work cell
from making its goal. Constraints should be exploited to improve throughput.
6
Work Stream Terminology
Process Time – Amount of touch time to perform the process or build a product (i.e.
router hours/bid hours)
Lead Time – Amount of time for product to physically move through a process or work
cell to be placed into finished goods (i.e. work order start date to product in FG)
TAKT Time
TAKT = Effective working time per shift
Customer requirement per shift
Activity Ratio
Activity Ratio = Router Hours
LT (days) * 24
% Complete and Accurate – The percent of time to which work from an upstream
process is determined by the downstream process to be error free
1/21/22
7
TAT TEAM
RUN RULES
Populate LP#8 first then LP#7, LP#6…to minimum level as a priority
Each landing pad must be handled FIFO due to priority and expedite turn around
need.
All WIP must be kept in assigned location at all times
• WIP locations must be identified.
Production operators cannot work on non-Priority expedite items that would
interrupt daily flow until all in-process is current or ahead of demand.
8
TAT TEAM
9
Planned WIP levels by location
Description
of process
Date steps
10/27/2021 0 0 1 1 0 1 0 1
10/28/2021 0 0 0 0 4 1 0 0
10/29/2021 0 0 9 4 1 4 1 2
11/2/2021 12 4 0 1 0 0 0 16
11/3/2021 12 15 40 0 2 5 1 3
11/4/2021 18 41 12 4 7 8 1 2 50 16
11/5/2021 12 61 16 9 4 7 2 8 48 16
11/6/2021 12 37 25 15 5 16 3 1 51 18 25
10
Cross Training Matrix – Example for Cross training
MESA/ ASPS / Cross Training Metric
Name / Task
Kristina Westlin
Alexis Easterling
Dixie Whittle
Emma Thomas
Nicol Ramirez
Loren Mars
Tammy McClendon
Charles Rowland
Colton Prouty
Joey Johnson
11
Operation Steps 1-2-3-4 Playbook
a. Check daily status to determine where help is needed- If you are qualified to perform that operation
steps task then help that area meet the daily goal to keep the product flowing forward.
b. See Lead/ supervisor for additional assignments
4.When/If downstream of the pace setter operations are meeting their throughput
requirements, evaluate the need to support/cross train operations inside the cell or
feeder processes as necessary.
12
TAT Playbook
1. Meet your daily throughput requirement for testing
a. Testing and verification of programming
b.
c.
2. Assist operations with other tasks as needed to meet demand.
13