Professional Documents
Culture Documents
LastPlanner 10.17.17 - Seiler - AIA Quality Assurance Slides
LastPlanner 10.17.17 - Seiler - AIA Quality Assurance Slides
Introduction to Last
Planner System
Rich Seiler, Unified Works
2
I N T R O D U C TI O N TO L A S T P L A N N E R ® S Y S T EM
Course Description
Learning Objectives
Mastery
Competency
Understanding
Continuous
Awareness
Learning Loop
Unaware
Learning Overview
8:00 AM – Introductions
10:00 AM – Resume
11:45 AM – Plus/Delta
Discussion Question
3 Generate Value
4 Eliminate Waste
5 Focus on Flow
6 Continuous Improvement
© LEAN CONSTRUCTION INSTITUTE 14
I N T R O D U C TI O N TO L A S T P L A N N E R ® S Y S T EM
54%
of commitments made
on construction
projects were
completed on time
Time — Cost —
70% were delivered late 73% were over budget
13%
20% Under Tender
Delivered On Price
Time
14
70% 10% 73% %
Delivered Late Delivered Early Over Tender On Tender
Price Price
2X
3X
MUDA: WASTE
DEMAND Goal: Align Demand
with Capacity to even
VOLUME OF WORK
out
workflow/reliability
CAPACITY
MURA: FLUCTUATION
MURI: OVERBURDEN
TIME
KEY CONCEPTS:
Project is a Promise
Preparation Negotiation
Request or Offer
Acceptance
(2 mutual promises)
Conditions
CUSTOMER of PERFORMER
Satisfaction,
Time
Declaration of
Satisfaction
Report of Completion
Acceptance Performance
Credit: Dr. Fernando Flores
Discussion Question
SHOULD
Phase “Pull” Planning Specify handoffs
5 Connected
CAN Look Ahead Planning Make work ready
Conversations
System
Learning Milestone
informs informs
Milestone Phase Pull
Milestone
Phase
Learning Pull
Phase Pull
informs
Look Ahead
Weekly Look
informs Weekly
Ahead
Learning
Look Ahead
informs Weekly
M Milestone Planning
Milestone Planning
Milestone Planning
Parade of Trades
through Floor 35
01. The building has 35 floors. etc . . .
Floor 14
Floor 13
Parade of Trades
How will you develop the
project schedule?
Build-out 35 Floors
Build-out 35 Floors
Week 1 Week 2 Week 3 Week 4 Week 5
Work Sequence
35
Chips START in the queue of Layout
Casework
Drywall
Paint
Establish queue spaces
Week 1
COLUMN 3
COLUMN 1 COLUMN 2
REMAINING INCOMING
WEEK CAPACITY CAPACITY
INVENTORY (BACKLOG)
NUMBER ON DICE PIECES PASSED
AVAILABLE -
PASSED
1 3 3 32
Rough Layout
Electrical
32
Week 2
Framing
COLUMN 3
COLUMN 1 COLUMN 2
REMAINING INCOMING
WEEK CAPACITY CAPACITY
INVENTORY (BACKLOG)
NUMBER ON DICE PIECES PASSED
AVAILABLE -
PASSED
Week 3
Layout
COLUMN 3
COLUMN 1 COLUMN 2
REMAINING INCOMING
WEEK CAPACITY CAPACITY
INVENTORY (BACKLOG)
NUMBER ON DICE PIECES PASSED
AVAILABLE -
PASSED
1 3 3 32
2 1 1 31
3
1+0
Rough
Framing
Plumbing
Rough Layout
Electrical
30
Drywall Casework
Paint
Casework
Rough
3
Framing
It’s your job to keep everyone at Plumbing
Summary
MAX
WEEK WEEK TOTAL TOTAL
INVENTORY
TABLE LAYOUT PROJECT USED REMAINING
IN ANY
COMPLETE COMPLETE CAPACITY
WEEK
INVENTORY
Blue
Black
Green
Red
Results
40
35
30
25
Worst
20 Average
Best
10
10
0
1.1.1.6.6.6 1.2.2.5.5.6 1.2.3.4.5.6 2.2.3.4.5.5 2.3.3.4.4.5 3.3.3.4.4.4
Discussion Question
SHOULD
Phase “Pull” Planning Specify handoffs
Conversations
WIL Weekly Work Planning Make promises
L
Promise/
Request
Work
Elements of Sticky
Name Crew size # Days
1 week max
MY PROMISE/ACTIVITY
• What I will Deliver
• Be specific
• Small batch
WORK AREA/ZONE
MY REQUEST/TRIGGER
• What Releases my Work
• Be specific
Pull Example
Promise Promise Promise
Mike G 4 Crew 3 days Dave S 3 Crew 3 days Mike G 4 Crew 5 days Dave S 3 Crew 3 days
Request Request
Start at End
© LEAN CONSTRUCTION INSTITUTE 54
I N T R O D U C TI O N TO L A S T P L A N N E R ® S Y S T EM
SHOULD
Phase “Pull” Planning Specify handoffs
Conversations AheLaodokPAlahenandinPgalnnnig
Constraint
Log Look
Ahead
Track PPC
& Variance
Electronic
• P6 • LeanKit
• Microsoft • vPlanner
Project • Others
• TouchPla
n
Electronic
• P6 • LeanKit
• Microsoft • vPlanner
Project • Others
• TouchPla
n
Date
Resolved
D
PromDate
Promised
Discussion Question
SHOULD
Phase “Pull” Planning Specify handoffs
Commitment Description
Crew Size?
SHOULD
Phase “Pull” Planning Specify handoffs
Daily Huddle
SHOULD
Phase “Pull” Planning Specify handoffs
5 Connected
CAN Look Ahead Planning Make work ready
Conversations
Work Register
Weekly Work & Constraint Log
Planning (Can)
Promise/ Promise/
Request Request
Promise/
Request
Promise/ Promise/
Request Request Promise
/Request
Promise/ Promise/
Request Request
Promise/
Request
Promise/
Request
Work
Discussion Question
Mastery
Competency
Understanding
Continuous
Awareness
Learning Loop
Unaware
Plus/Delta