PHASE I – Q1

Process Jan Feb Mar


AS-IS

TO-BE & Blue Print

Baseline Configuration (PM/MM/FICO) Now We are Here


(5 Feb – 10 March)
Final Preparation for Testing
(10 March – 15 March)
Customize Reports and Scripts
(20 Feb – 15 March)
Data Uploading
(15 March – 20 March)
End User Training
(10 March – 25 March)
User Acceptance Testing
(20 March – 25 March)
Go-live(30 March)
PHASE I – Q2
Process April May June

Get requirement (1 – 10 April)

Blue print (10 – 20 April)

Development (20 April – 31 May)

Testing Develop (1 May – 10 June)

Training (5 June – 20 June)

Testing Production (21 June – 28


June)
Go-live (30 June)