Sewerage Rehabilitation This deals with ‘upgrading’ existing sewers which might be deficient in some way. The deficiencies can be categorised as follows:- a) Hydraulic Sewer may have insufficient capacity or insufficient gradient to achieve self cleaning velocities. An assessment is made as to whether this leads to excessive surcharging or flooding and whether there is excessive build up of sediment due to lack of gradient.
Energy Environment Infrastructure
b) Structural The condition of the sewer is likely to be affected by the age of the sewers, the extent and quality of connections made, the pipeline material and the quality of workmanship during construction. c) Maintenance The ease or otherwise of the sewer maintenance is related to the hydraulic & structural conditions of the sewer. High Priority sewers are normally those that require excessive maintenance e.g. repairs to collapsed sewers etc. d) Environmental What is the effect on the receiving waters and groundwaters of the defective sewer? Energy Environment Infrastructure How are deficiencies determined? a) Hydraulic Hydraulic deficiencies can be determined by:- • Flow measurement – this validates the extent of flows and must be for a sufficiently long time to capture all flow variations – seasonal as well as diurnal; • Modelling – based on theoretical and validated by the flow measurement data collected; • Examination of previous maintenance issues. This will add validity or to the flow measurement & modelling of the sewerage system. It may also point to particular issues not captured by either the flow measurement or the modelling Energy Environment Infrastructure How are deficiencies determined? a) Hydraulic (contd…) It may be possible to better manage the hydraulics of a particular sewer by flow diversion or flow reduction (e.g. CSO). (Beware of worsening environmental effects by introduction of CSO’s).
Management of the system hydraulics should be
carried out at an early stage. The results of such an exercise, if successful, provides an economical solution to a network issue
Energy Environment Infrastructure
How are deficiencies determined (contd…) b) Structural Inspection, generally by CCTV survey. Such an inspection results in a report (& DVD of surveyed sewer) compiled in accordance with the WRc Publication ‘Manual of Sewer Condition Classification’.
This document also sets out procedures for CCTV
inspection and coding guidelines for pipeline and manhole defects.
View: CCTV Survey CCTV Survey.mpg
Energy Environment Infrastructure c) Maintenance Reports from Local Authorities, number of repairs carried out, number of times sewer jetted & cleaned etc.
d) Environmental A bit more difficult to quantify but by data collection & sampling & testing.
Procedures for rehabilitation are set out in ‘Sewerage
Rehabilitation Manual’ (Available on-line)
Energy Environment Infrastructure
Rehabilitation Techniques i. Repairs These can be carried out manually with man entry sewers, for example grouting of defective or leaking joints or lining sections of the sewer. The sewer is cleaned and jetted prior to work commencing. Given that these large sewers are critical to the operation of the network, such repair work is normally carried out by night when the sewer can be temporarily decommissioned and low flows overpumped for the duration of the repairs.
Energy Environment Infrastructure
i. Repairs (Cont’d) Where sewers are too small to accommodate a person, then repairs are carried out remotely using robotic equipment fitted with CCTV cameras. This method of works can be carried out for example to chemical grout defective joints or connections. This involves isolating the pipe at each side of the joint with inflatable stoppers and applying the grout under pressure to the defective pipe. A high watertable might provide resistance to such repair techniques if the external pressure around the pipe is too high.
Energy Environment Infrastructure
ii. Lining Lining of sewers is a common method of increasing its hydraulic capacity (by decreasing the pipewall resistance) as well as reducing infiltration. The downside is that the nominal diameter of the sewer will be somewhat reduced.
Lining may be in the form of sliplining – a continuous
length of HDPE lining rolled out within the pipe and placed against the existing pipe wall.
Energy Environment Infrastructure
Sliplining of brick sewer using GRP lining Energy Environment Infrastructure ii. Lining (Cont’d) An alternative lining method is to pull a continuous length of welded HDPE pipe through the sewer. This is normally carried out if it is considered that the structural integrity of the existing sewer is inadequate. Sometimes this new pipe is pulled through following a pipe bursting exercise either to maintain or increase the existing pipe size. The slow and difficult parts of lining tend to be the reconnection of existing connections to the newly lined pipe. One option is to trace back the connection pipes and construct a new high level sewer (rider sewer) which will collect flow from all connections, leaving just a single connection to the low level sewer. Energy Environment Infrastructure ii. Lining (Cont’d) Cured in place linings (GRP) are also used. Such liners are installed in a flexible state and are cured (hardened) against the existing pipe wall when filled with water.
Section through lined pipe
Continuous pipe lining Energy Environment Infrastructure ii. Lining (Cont’d) The upgrading of a sewerage network normally comprises a combination of replacement and rehabilitation works. Costs (capital & operational) as well as technical requirements frequently determine the optimum solution and hence the balance between both methods. Indeed sewerage rehabilitation is often carried out on a phased basis to facilitate assessment of upgrade works on the overall scheme.
Energy Environment Infrastructure
Final note on self-cleansing design of sewers While we design new sewers for a specified self cleansing velocity, it should be recognised that a single value of minimum velocity, unrelated to the characteristics and concentration of the sediment or the other aspects of the hydraulic behaviour of the sewer, does not properly represent the ability of sewer flows to transport sediment. A more particular definition of self cleansing as presented in CIRIA report 141 ‘Design of sewers to control sediment problems’ is as follows:-
Energy Environment Infrastructure
‘An efficient self-cleansing sewer is defined as one with a sediment transporting capacity that is sufficient to maintain a balance between the amounts of deposition and erosion, with a time averaged depth of sediment deposition that minimises the combined costs of construction, operation and maintenance. Three sediment movement criteria should be met to ensure adequate self cleansing, based on the capability of flows in the sewer to: • transport a minimum concentration of fine grain particles in suspension • transport coarser granular material as bedload • erode particles from a deposited bed. Evidence is presented to show that different criteria can govern the design at particular pipe sizes, depending on the applicable sediment characteristics and concentrations’. Ref:- CIRIA report 141 ‘ Design of sewers to control sediment problems’ Energy Environment Infrastructure In addition, this document examined and makes recommendations on sediment transport methods as follows:- ‘Two alternative mobility criteria can be considered in association with the transport of coarse sediment (grit) as bedload: • either to ensure there is no deposited material on the pipe invert under design flow conditions (the ‘limit-of-deposition’ condition) • or to allow a certain, controlled amount of deposition’.
Energy Environment Infrastructure
Thus sewers can be (and frequently are) designed on the basis that they are not completely sediment free all of the time. Such criteria might apply particularly to existing sewers and the design should take account of sediment deposits in the sewer and the consequent reduction in hydraulic efficiency. For combined sewers a design scenario could be that the sediment will be fully or partially flushed out during storm conditions. The design of sewers for these conditions (i.e. incorporating sediment in the sewer design) is outside the scope of this module. Energy Environment Infrastructure